Precedence Diagrams

Earliest Duration Start

Earliest Finish

Activity description & relevence Latest Start Float Latest Finish

Critical Path

Bar Chart
Critical Path Non-Critical Path Float

1 2 Base Wall 1 Wall 2 Roof Cuve Roof Columns Ch. Base Ch. Walls

3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

Total float = 3+16 = 19

*Do Not Get Arrow Diagrams/ Time Bar Diagrams AND Precedence diagrams/ Link Bar chart Mixed together

1 2 Base Wall 1 Wall 2 Roof Cuve Roof Columns Ch. Base Ch. Walls 10 9 8 7 6 5 4 3 2 1 6

3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 6 6 6

2 2 2 Ch. Base Columns Ch. Walls MAX 6 men Base Wall 1 Wall 2 Roof Ch. Base Ch. Walls

EXTRA MEN = 50 /man/day Es = (6 + 20 + 8) 50 = 34 50 = 1700 Reschedule = 20 50 = 1000