Activity ID: Activity ID is the unique assigned number to activity name.

Activity Name: Name the activity you will perform. Start Date: Start Date is the date on which activity will begin. Finish Date: Finish Date is the date on which activity will finish. Human Resources: Assign Human resources to the activity Example: ABC (unit name) Material Resources: Assign Material needed to the activity Example: ABC (unit name) Predecessor: Predecessor is the activity that comes just before a particular activity. Successor: Successor is the activity that comes just after a particular activity. Example of Predecessor and Successor
Activity ID
A1010 A1020 A1030 A1040 A1050 A1060 A1070

Activity Name
Project Kick Off Project Sponser initial meeting Initial Feasibilty Study Computer Aided Drawing Model Model Simulations Model Testing Final Design Approval

Predecessors
A1010 A1010, A1020 A1030 A1040 A1050 A1060, A1040

Successors
A1020, A1030 A1030 A1040 A1050, A1070 A1060 A1070