Fill the application form with Required Documents and submit at I/O section of designated offices/Centres. (DAY-1)
Senior Health Inspector prepares a Report of Inspection and submits to MOH. (DAY- 2 to 8)
AEE (works) to certify for Building deviation as per occupancy certificate and submit the report to MOH. (DAY- 9 to 11)
MOH approves based on the Hierarchy Of Approvals as per each case and License is issued. (DAY- 12 to 13)
Certain files are marked to DHO based on the Hierarchy Of Approvals as per each case and License is issued. (DAY- 13 to 15)
Certain files are marked to HO based on the Hierarchy Of Approvals as per each case and License is issued. (DAY- 13 to 16)
Certain files are marked to Zone Commissioners based on the Hierarchy Of Approvals as per each case and License is issued. (DAY- 14 to 17)