Professional Documents
Culture Documents
Article Liability After Takeover
Article Liability After Takeover
November 2009
1. Describe the system of liability after take-over according to the rules used most often
Under English law, upon take-over of a project, the relevant statutory provisions governing liability of a contractor, subcontractor or consultant are found primarily in the Limitation Act 1980 (the Act). There is no statutory defects liability period whereby the contractor has a positive obligation to rectify defects. Rather, it is usual practice for the parties to agree a defects liability period as a matter of contract. The period is typically 12 to 24months for general construction contracts. In the absence of an agreed defects liability period, or if the contractor refuses to rectify a defect notwithstanding an agreed defects liability period, the aggrieved party will have to commence legal proceedings in order to recover any damages or losses occurring after take-over. There is no guarantee that the aggrieved party will succeed, as it will need to prove that the other party was at fault and that it suffered damage or loss as a result. Thetime for the aggrieved party to commence legal proceedings is limited by the Act so that if the time has expired, the aggrieved party is time-barred from pursuing its claim.
The limitation time periods most relevant to construction projects are: a. Contract claims - 6 years from the date the cause of action accrued,2 which is the date of the breach of contract complained of. In construction contracts, if the contractor is responsible for completing the works under an entire contract, the limitation period for defective work generally runs from the date of completion. As to liability for defective design, the English courts have held that while the cause of action accrues generally on practical completion (at the latest), the designer may have a duty to reconsider the design as a result of defects arising after completion. Such duty could arise either under the existing contract or the terms 3 of a new retainer; b. Tort actions - 6 years from the date the cause of action accrued,4 which is the date the physical damage occurs; and c. Deed claims - 12 years from the date the cause of action accrued,5 which is the date of the breach of the obligation in thedeed. It is possible for the parties to reduce or increase the limitation periods prescribed by the Act in their contracts.6 Generally, the courts will not interfere with the parties contractual agreement, especially if the parties are experienced commercial entities
A version of this article was first published by Instituut voor Bouwrecht (Institute of Construction Law - Netherlands) in Tijdschrift voor Bouwrecht, nr. 9 - September 2009
1 Senior Associate at the London office of White & Case LLP and a member of the UK Society of Construction Law. 2 Section 5 of the Act. 3 See New Islington & Hackney Housing Association v Pollard Thomas & Edwards [2001] BLR 74. 4 Section 2 of the Act. 5 Section 8 of the Act. 6 See for example Oxford Architects Partnership v Cheltenham Ladies College [2006] EWHC 3156.
2.1. Does it make a difference if prior to take-over or during take-over, the employer was assisted by professionals (like an architect or civil engineer)?
If the contract is a construct-only contract, the contractor will generally not be liable for a defect in design, whether before, during or after take-over. As between the employer and the contractor, the responsibility for a design defect lies with the employer. As between the employer and its professional consultants (eg. architect or civil engineer), the responsibility lies with the consultant who bears the risk of the design. The employer will look to the relevant consultant for relief and the considerations mentioned in paragraph 1 above apply.
10 Section 14A of the Act, which was introduced into the Act by the enactment of the Latent Damage Act 1986. This was prompted by the House of Lords decision in PirelliGeneral Cable Works Ltd v Oscar Faber & Partners [1983] 2 AC 1 which held that the claimant was time barred from bringing a claim against its architect for damage to its chimney, which first occurred in 1970, even though the claimant only found out about the damage in 1977 . More than 6 years had passed from the date the cause of action arose in 1970 when the claimant commenced proceedings in 1978. 11 Section 14B of the Act, which was also introduced into the Act by the enactment of the Latent Damage Act 1986 following the Pirelli case.
4. How long can the employer take action against the contractor after take-over?
This question has been addressed in paragraphs 1 and 2.1 above.
3. Does it make a difference to the liability of the design and build contractor if a defect was or could have been discovered (a) prior to, or (b) at the time of take-over; or (c) after take-over? If so, describe the difference.
Generally, there is no difference to the liability of the design and build contractor as stated in paragraphs 1 and 2 if the defect was discovered prior to or at the time of takeover, or after take-over. A defect discovered prior to or at the time of take-over will be a patent defect. It may be a patent defect after take-over if it fallsoutside the latent defect provisions discussed in paragraph2.1(b). In any of these cases, the limitation periods set out in paragraph 1 apply.
36 Offices. 25 Countries.
7. Which specific legal problems play a role in your system concerning liability after takeover when the contractor is responsible for the designing and building?
This is merely an observation and not a problem as such but the obvious comment is that unlike other jurisdictions, there is no statutory obligation on a contractor (whether responsible for design and build, or just construction) to positively rectify defects after take-over, and it is up to the claimant to ensure that this is covered in the construction contract or pursue legal proceedings for breach of contract or negligence. The knowledge required of the factual essence of negligence in the case of latent defects can be problematic, and indeed, in the Haward case itself, the judges differed on whether the essence was the giving of deficient advice, or the giving of advice per se. In the first, the claimant is said to know that something had gone wrong so that he had a justifiable complaint against his advisers, while in the second, he need only know that he had invested money in reliance on the advice and had made losses. Whether a claimant is successful ultimately depends on the courts interpretation of the rules against the facts in question.
www.whitecase.com
In this publication, White&Case means the international legal practice comprising White&CaseLLP, a NewYorkState registered limitedliabilitypartnership, White&CaseLLP, a limited liability partnership incorporated under Englishlaw and all other affiliatedpartnerships, corporations and undertakings.
LON1009072