PERENCANAAN TEKNIK JALAN : UNTUK MENDAPATKAN SUATU DISAIN YANG OPTIMUM, DALAM ARTI SESUAI KONDISI LAPANGAN, DAPAT DILAKSANAKAN, SERTA EFFEKTIF DAN EFFISIEN UNTUK MENANGANI JALAN YANG MENJADI OBJEK PERENCANAAN.
SUATU JALAN ATAU BAGIAN DARI SUATU JALAN MENJADI OBJEK PERENCANAAN BERARTI ADA SUATU "MASALAH" PADA JALAN TERSEBUT YANG AKAN DIPERBAIKI.
KEAMANAN
2 3
KENYAMANAN KELANCARAN
KEAMANAN
1 GEOMETRIK JALAN
2 BANGUNAN PELENGKAP
3 RAMBU - RAMBU LALU - LINTAS 4 VEGETASI UNTUK PENAHAN SILAU
5 DRAINASE, DLL
3
KENYAMANAN
1 2 KONDISI PERMUKAAN STRUKTUR PERKERASAN
3 4
KELANCARAN
1 KAPASITAS JALAN
GEOMETRIK JALAN
3 4
1. GEOMETRIK JALAN
1. KAPASITAS JALAN 2. DIMENSI / LEBAR JALAN 3. ALINYEMEN VERTIKAL & HORIZONTAL 4. SIMPANG / PERTEMUAN JALAN
2. STRUKTUR JALAN
1. KONDISI PERKERASAN 2. TEBAL, TIPE DAN SUSUNAN PERKERASAN 3. DAYA DUKUNG TANAH DASAR
3. DRAINASE JALAN
1. SISTEM DRAINASE/SISTEM PENGALIRAN
2. KAPASITAS DRAINASE
3. KONDISI DRAINASE
4. BANGUNAN PELENGKAP
1. GORONG - GORONG 2. JEMBATAN 3. DINDING PENAHAN TANAH
D IA G R A MA L IR PR O S E SD IS A IN
MUL AI
PE RSIAPAN Mobilisasi
PE NGUKURAN TOPOGRAFI
PE NE L ITIAN L APANGAN
PE NE L ITIAN L ABORATORIUM
PE NE L ITIAN QUARRY
KO NSE P PE RE NC ANAAN
D iskusi
S E L E S AI
1. PERSIAPAN
1. MOBILISASI PERSONIL DAN PERALATAN 2. KOORDINASI DENGAN PEMBERI TUGAS
1. Menyamakan presepsi pengertian isi Dokumen Kontrak 2. Pemeriksaan Rencana Kerja, Jadwal Ekspose, dan jadwal koordinasi rutin
4. PENYUSUNAN RMK Ini adalah Laporan untuk menunjukkan kepada pemberi tugas langkah langkah apa yang akan dilakukan agar pelaksanaan pekerjaan perencanaan sesuai atau memenuhi ketentuan dalam K.A.K dan dokumen kontrak lainnya.
10
2. SURVEY PENDAHULUAN
Maksud dan Tujuan :
Untuk mengetahu gambaran umum lokasi pekerjaan secara lebih detail, yang akan dipakai sebagai masukan bagi penyusunan rencana kerja dan penetapan langkah kegiatan perencanaan berikutnya.
1. Latar belakang, maksud, tujuan dan sasaran yang ingin dicapai, 2. Diskripsi lokasi kegiatan secara lebih detail yang memuat lokasi, diskripsi awal dan akhir kegiatan, kondisi eksisting jalan dan perlengkapan jalan, terrain, jenis tanah secara umum dan indikasi permasalahan menyangkut geometrik, struktur, drainase, bangunan pelengkap, serta rencana solusi yang akan diterapkan. 3. Metode dan Pendekatan Pelaksanaan pekerjaan yang akan diaplikasikan yang sudah mengakomodir fakta fakta yang didapat selama pelaksanaan survey pendahuluan yang datanya sudah disajikan pada penjelasan mengenai diskripsi lokasi kegiatan. 4. Organisasi dan Rencana Kerja detail.
12
2. STRUKTUR JALAN
1. KONDISI PERKERASAN 2. TEBAL, TIPE DAN SUSUNAN PERKERASAN 3. DAYA DUKUNG TANAH DASAR SURVEY KONDISI JALAN : IRI/RCI, BB, SKJ
TEST PIT
DATA
3. DATA IRI/RCI, BB, KONDISI JALAN 4. DATA SUSUNAN DAN TEBAL PERKERASAN DAN SUSUNAN TANAH DASAR
5. DATA CBR LAPANGAN
14
3. DRAINASE JALAN
1. SISTEM DRAINASE/SISTEM PENGALIRAN 2. KAPASITAS DRAINASE 3. KONDISI DRAINASE SURVEY
TOPOGRAFI,
KONDISI HIDROLOGI DAN
DATA
6. DATA HIDROLOGI
15
4. BANGUNAN PELENGKAP
1. GORONG - GORONG 2. JEMBATAN 3. DINDING PENAHAN TANAH 4. TROTOAR, MEDIAN, PULAU PULAU, 5. PENERANGAN JALAN UMUM (PJU)
SURVEY TOPOGRAFI , KONDISI DAN HIDROLOGI, GEOTEKNIK DAN SURVEY PEKERJAAN PELENGKAP JALAN
DATA SEKUNDER
DATA GEOTEKNIK
DATA HIDROLOGI
PERUMUSAN KEBUTUHAN MENYANGKUT BIAYA KONSTRUKSI, KAPASITAS, DIMENSI, STRUKTUR JALAN DAN BANGUNAN PELENGKAP JALAN
DATA TOPOGRAFI
17
18
% Tambalan
Susunan Permukaan
Kondisi Permukaan
% Penurunan
Jenis Retakan
Lebar Retakan
% Luas Retakan
Jumlah Lubang
Ukuran Lubang
PJG BAGIAN KE
3
m
4
Kiri
16
TOTAL SKOR
17
KONDISI
RCI
KET.
10
11
12
13
14
18
19
20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
0+000 0+100 0+200 0+300 0+400 0+500 0+600 0+700 0+800 0+900 1+000 1+100 1+200 1+300 1+400 1+500 1+600 1+700 1+800 1+900 2+000 2+100 2+200
0+100 0+200 0+300 0+400 0+500 0+600 0+700 0+800 0+900 1+000 1+100 1+200 1+300 1+400 1+500 1+600 1+700 1+800 1+900 2+000 2+100 2+200 2+300
100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100
2 2 2 2 1 1 2 1 2 2 2 2 1 1 2 1 1 1 1 1 2 2 2
1 1 3 3 1 3 1 1 3 3 3 3 1 1 3 1 1 1 1 1 1 1 3
2 2 3 3 4 3 2 3 2 2 1 2 1 1 1 1 1 1 1 1 1 1 2
3 2 4 4 3 3 3 3 4 3 2 2 1 2 2 2 2 3 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 2 2 2 4 4 2 4 2 2 1 1 1
4 3 4 3 3 4 3 3 4 3 3 2 2 2 2 2 2 2 2 2 1 1 1
3 3 4 4 4 3 3 3 4 3 2 2 2 2 2 2 2 2 2 2 1 1 1
1 2 2 1 1 2 2 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 2
1 2 4 1 1 2 2 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 4
1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1
2 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1
23 23 31 27 24 28 24 22 27 26 21 20 15 16 21 18 16 19 15 15 13 12 19
SEDANG SEDANG SEDANG SEDANG SEDANG SEDANG SEDANG SEDANG SEDANG SEDANG SEDANG SEDANG BAIK BAIK SEDANG SEDANG BAIK SEDANG BAIK BAIK BAIK BAIK SEDANG
6 6 5 5 6 5 6 6 5 5 6 6 7 7 6 6 7 6 7 7 7 7 6
19
TANAH DARI HASIL TEST PIT ATAU BORING DILAKUKAN PENGUJIAN : 1. 2. ATTERBERG LIMITS (LL, PL dan PI) KADAR AIR, BERAT JENIS
3.
4. 5. 6.
KEPADATAN LABORATORIUM
CBR LABORATORIUM (RENDAMAN) ANALISA SARINGAN KUAT GESER
20
1. TANAH DASAR
SEBAGAI SUB GRADE TANAH DASAR BERFUNGSI : SEBAGAI TEMPAT PERLETAKAN STRUKTUR PERKERASAN AGAR STRUKTUR PERKERASAN STABIL, SEBAGAI LAPISAN UNTUK MELINDUNGI STRUKTUR PERKERASAN DARI PENGARUH AIR KAPILER ATAU PENGARUH LAIN DARI LAPISAN DI BAWAHNYA, OLEH KARENA ITU SEBAGAI SUB GRADE TANAH DASAR HARUS : KUAT (NILAI KEPADATAN 100%) STABIL NILAI CBR MINIMUM 5 % (RENDAMAN 6 %)
21
22
PERSYARATAN TERSEBUT DI ATAS HARUS TERPENUHI DARI DATA/PARAMETER TANAH YG DIDAPAT DARI PENYELIDIKAN LAPANGAN DAN LABORATORIUM
23
24
A 4 : KELOMPOK TANAH LANAU DENGAN SIFAT PLASTISITAS RENDAH A 5 : KELOMPOK TANAH LANAU DENGAN SIFAT PLASTISITAS LEBIH TINGGI A 6 : KELOMPOK TANAH LEMPUNG DENGAN SIFAT PLASTISITAS TINGGI A 7 : KELOMPOK TANAH LEMPUNG DENGAN SIFAT PLASTISITAS SANGAT TINGGI
25
26
27
STA
2
NILAI CBR %
3
CBR DESIGN
6
KET.
7
1 2 3 4 5 6 7 8 9 10 11
0.000 0.500 1.000 1.500 2.000 2.500 3.000 3.500 4.000 4.500 5.000
100.00 90.91 81.82 72.73 63.64 54.55 45.45 36.36 27.27 18.18 9.09
14.15
PROSENTASE
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
14,15
28
Demak Ijo = 4 % 70 50 30 10
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 32
CBR
JIKA NILAI CBR LAP < 5 %, MAKA TANAH DASAR YG ADA HARUS DIGANTI DENGAN TANAH PILIHAN
29
30
31
KETERANGAN
10
10
15
15
15
15
15
15
20
25
25
25
25
25
25
30
35
Disain khusus
50
50
50
50
50
55
60
60
Sumber : REPORT-TECH-VAB652\as.171291
HASIL PENGUJIAN LABORATORIUM DARI PROYEK JALAN BODO-MELIAU, SANGAU, KALIMANTAN BARAT LOKASI JENIS TANAH INDEX PLASTIS (%) Km 3+800 Km16+500 Pasir halus berlumpur Pasir berlempung dan berlumpur 8 11 TIDAK DIRENDAM W (%) 17,8 15,5 CBR (%) 15 20 W (%) 20.9 22 DIRENDAM CBR (%) 9 6
32
LL 51.61 32.58
PL 25.1 12.29
PI 26.51 20.29
37.03
30.06 28.93
27.27
17.34 20.33
9.76
12.72 8.6
CBR
(70 - PI)/10
6.024 14.15
2. GEOMETRIK JALAN
PERENCANAAN / ANALISIS GEOMETRIK JALAN MELIPUTI :
1. LEBAR JALAN CUKUP TIDAK DAN BANDINGKAN DG KETENTUAN LEBAR MENURUT KELAS JALANNYA. 2. PERBAIKAN ALINYEMEN HORIZONTAL DAN VERTIKAL UNTUK MENYESUAIKAN DIMENSI DAN PARAMETER PARAMETER TIKUNGAN DENGAN KETENTUAN MINIMUM SESUAI DENGAN KELAS JALANNYA. 3. PERBAIKAN BIDANG BIDANG PERTEMUAN JALAN SEPERTI PEREMPATAN ATAU PERTEMUAN DENGAN JALAN LAIN (SIMPANG) UNTUK MENINGKATKAN FAKTOR KEAMANAN, KENYAMANAN DAN KELANCARAN LALU LINTAS. BAGIAN GEOMETRIK JALAN INI TERKAIT DENGAN KEBIJAKAN YG DITENTUKAN OLEH DANA TERSEDIA. MESKIPUN DEMIKIAN DALAM SUATU PERENCANAAN JALAN TETAP HARUS DILAKUKAN ANALISIS MENGENAI ASPEK GEOMETRIK INI.
34
3. STRUKTUR PERKERSAN
1. PERENCANAAN FULL DEPTH BETTERMENT
ATAU PERENCANAAN TEBAL PERKERASAN LENGKAP YG
TERDIRI
DARI
LPB,
LPA
DAN
LAPIS
PERMUKAAN.
PERENCANAAN PERKERASAN PADA JALAN BARU ATAU PADA BAGIAN PELEBARAN. 2. PERENCANAAN LAPIS PERKERASAN TAMBAHAN / OVERLAY ATAU PERENCANAAN TEBAL LAPIS PERKERASAN TAMBAHAN (OVERLAY) PADA JALAN EKSISTING YANG TELAH MENGALAMI PENURUNAN KONDISI
35
36
START
Faktor Regional (FR) : - intensitas hujan - kelandaian jalan - % kendaraan Berat - Pertimbangan Teknis Beban Lalu - Lintas (LER) Indek Permukaan Awal (Ipo) Indek Permukaan Akhir (Ipt) Tentukan Nilai ITP Tahap 1 dan 2 Tentukan Nilai ITP Tahap 1 Tentukan Nilai ITP Selama umur rencana Ya Konstruksi Bertahap? Tidak
FINISH
37
CBR Rencana
DDT
4,3 log CBR + 1,7
LER
ITP
Faktor Regional
ITP
38
Perhitungan Tebal Perkerasan Pada Bagian Pelebaran dengan Metode Analisa Komponen Bina Marga. Metode analisa komponen Bina Marga merupakan modifikasi dari metode AASHTO 1972 revisi 1981. Modifikasi ini dilakukan untuk menyesuaikan dengan kondisi alam, lingkungan, sifat tanah dasar, dan jenis lapis perkerasan yang umum dipakai di Indonesia. Penyesuaian tersebut antara lain : Lapis permukaan di Indonesia terdiri dari berbagai jenis yang berbeda mutunya satu dengan yang lain. Oleh karena itu Ipo (Indek Permukaan Awal) tidak dapat dipergunakan hanya satu nilai seperti AASHTO. Ipt (Indek Permukaan Akhir) menurut metode AASHTO hanya mempergunakan dua nilai yaitu 2 dan 2,5. Sedangkan di Indonesia dipakai 4 nilai Ipt yaitu : 1; 1,5; 2 dan 2,5. Faktor Regional (FR) menurut AASHTO dibedakan menjadi 4 (empat) musim, sedangkan di Indonesia didasarkan atas kondisi curah hujan. Di Indonesia dipakai nilai FR antara 0,5 s/d 4. Nomogram AASHTO untuk umur rencana 20 tahun. Sedangkan di Indonesia umumnya dipakai umur rencana 10 tahun. Oleh karena itu diperlukan adanya faktor penyesuaian.
39
2. PERENCANAAN OVERLAY
Perhitungan tebal lapis perkerasan tambahan (Overlay) dilakukan dengan metode HRODI (Hot Rolled Overlay Design of Indonesia). Metode ini dikembangkan oleh C.Come, dan merupakan modifikasi dari metode ACODI (Asphaltic Concrete Overlay Design Indoensia). Metode ini khusus untuk menghitung tebal lapisan tambahan. Menurut metode HRODI tebal lapis tambahan adalah tebal lapisan yang dibutuhkan untuk mengurangi lendutan yang terjadi selama umur rencana sampai batas yang di-ijinkan (t), dan tebal lapisan yang dibutuhkan untuk membentuk kembali permukaan perkerasan ke bentuk yang dikehendaki (T). Penjelasan lebih lengkap dapat dilihat pada Gambar 3-2
40
41
DATA YG DIBUTUHKAN :
42
STA
2
NILAI CBR %
3
CBR DESIGN
6
KET.
7
1 2 3 4 5 6 7 8 9 10 11
0.000 0.500 1.000 1.500 2.000 2.500 3.000 3.500 4.000 4.500 5.000
100.00 90.91 81.82 72.73 63.64 54.55 45.45 36.36 27.27 18.18 9.09
14.15
PROSENTASE
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
14,15
43
9
BUS BUS KECIL SEPEDA MOTOR TRUCK 3 AS TRUCK 2 AS KENDARAAN RINGAN TRUCK GANDENGAN TRAILLER KENDARAAN TDK BERMOTOR
KONVERSI DALAM SATUAN MOBIL PENUMPANG (SMP) UNTUK ANALISIS KAPASITAS / LEBAR JALUR PELAYANAN LALU - LINTAS (PERKERASAN).
8
KONVERSI DALAM LINTAS EKIVALEN RENCANA (LER) ATAU CESA UNTUK PERHITUNGAN TEBAL PERKERASAN.
44
ANALISA KAPASITAS
CESA
LER
V/C?
V/C 0,65
45
11000 10000 9000 8000 7000 6000 5000 4000 3000 2000 1000 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41
46
ANALISIS LALU LINTAS UNTUK JALAN BARU ATAU JALAN YG TIDAK MUNGKIN DILEBARKAN
MULAI
HITUNG LER
BANDING KAN
HITUNG LER
Kapasitas
LER/CESA
SELESAI
47
d .( n 1)
2
n.( n 1)
dimana :
d
S d2 n
= Lendutan balik rata rata dalam satu segment = Faktor distribusi statistik = Kuadrat dari nilai lendutan tiap titik dalam satu segment = Jumlah titik pemeriksaan dalam satu segment.
48
Lendutan (mm)
0.000
0.500
1.000
1.500
2.000
2.500
3.000
3.500
4.000
4.500
Kilometer
LENDUTAN
CONTOH DISAIN
5.000
49