Professional Documents
Culture Documents
Introduction
SAs power generation is still dominated by Eskom
Mostly coal. DoEs IRP 2 sets targets for introduction of renewable generation.
Contents
Technical Challenges Unfamiliarity of local industry with RE Ability to evacuate the required amount of power Grid code compliance Compliance with Eskom/ Utility standards Health and safety Civil/Infrastructure Commercial Challenges PPA Bureaucracy and inefficiencies in supply authorities Overseas developers lack of understanding of SA
Lack of understanding of SA
Difficult to quantify, but: The large amounts of copper used in the collector network and earthing would be very attractive to thieves
Commercial challenges
PPA may not be to the developers advantage
Rates not nearly as high as some European feed-in
tariff rates makes it more difficult to make a profit. Reliance on Eskom and munics for building infrastructure will probably introduce delays.
network.
Lack of understanding may lead to misinterpretation of grid code
Local suppliers may not have the correct cable and the ideal
lengths
MV cables only in rolls of 300 or 500 m (Wind). Local LV cables may not be suitable for solar applications need
may occur when several projects are being constructed Cable manufacturers may not be able to keep up with demand when a number of RE projects are under construction
authorities dont.
most countries codes many generators/inverters will probably not comply. WTG manufacturers wont supply models of their product When connecting using long lines (even short lines when using MV) Q and V requirements not met
required amount of power will need grid strengthening. In some cases it may mean long lines and large transformers, even though Eskoms TDP does take into account some RE project.
comply with Distribution Standard for the integration of Embedded Generators Has specific requirements about anti-islanding protection and other requirements for the PUC Cant therefore copy a design from another country without modifying, Other utilities probably dont have standards. NRS documents not finalised yet.
likely to be unlike projects contractors have worked on before. Increases the risk of H&S incidents Operationally, extra sources are introduced into the grid greater risk of electrocution of maintenance personnel if proper isolating/earthing procedures arent in place or arent followed.
corners
earthing and the collector network. Major risk of theft. Cultural/ language differences may pose challenges when working with overseas developers.