Item of Work : Aluminum Cladding Qty, sq.m.: Item No. : Description : A.3.6 Aluminum Cladding
DESCRIPTION/COMPUTATION I. MATERIAL COST: Angular Frame, 50x50x6 Expansion Bolt, 12mmD Steel Plate, 6mmT Aluminum Cladding Misc 20% of Above
UNIT m pc m2 m2
Sub-total, Materials Output TOTAL OF MATERIALS II. LABOR: Foreman Skilled Laborer Unskillerd Laborer Sub-total, Labor III. EQUIPMENT: Minor Tools, 32% of Unskilled
hr hr hr P/hr hr
Sub-total, Equipment Sub-total, Labor+Equipment Output IV. TOTAL OF LABOR AND EQUIPMENT
ESTIMATED DIRECT COST, I+IV INDIRECT COST / MARK-UP Overhead, Conting. & Misc.,10%V Profit, 10% V Mob./Demob., 1% V VAT, 8% (V+VI.abc)
4,490.45 1,377.67
VII.
P/sq.m.