NO
Jumlah Harga
( Rp )
PEKERJAAN PENDAHULUAN
366,680.000
II
1,776,867.800
III
5,465,344.000
IV
6,372,407.200
15,414,624.400
VI
27,614,382.470
VII
PEKERJAAN FINISHING
4,833,895.000
VIII
745,920.000
IX
15,521,000.000
3,757,500.000
5,518,088.500
Jumlah Total
87,386,709.370
No
Uraian Pekerjaan
Volume
Satuan
Harga
( Rp )
PEKERJAAN PENDAHULUAN
1 Uniset dan bouwplank
2 Pembersihan lokasi
4
60
m'
m2
39,920.00
3,450.00
Sub Jumlah
II
III
38.84
24.05
7.89
m3
m3
m3
19,170.00
m3
369,280.00
Sub Jumlah
m3
m
2,701,360.00
2,041,540.00
Sub Jumlah
m
m
m1
395,710.00
15,040.00
7,000.00
109,500.00
Sub Jumlah
IV
14.8
Catatan :
Mutu beton : fc' = 22,5 Mpa (camp. 1: 2: 3)
1 Betom sloof 15x20cm & ring balk
2 Beton kolom praktis 15x15cm
V
1.18
1.56
24.06
343.08
217.78
3,370.00
Sub Jumlah
VI
VII
41.9
44.99
57.41
63.44
14.86
64.08
64.08
25.8
m
m
m
m1
m
m'
m'
m
m
m'
75,730.00
65,230.00
73,480.00
25,243.33
72,500.00
17,500.00
28,870.00
142,940.00
90,750.00
70,590.00
Sub Jumlah
343.08
57.41
m
m
12,500.00
2.25
9
PEKERJAAN FINISHING
1 Cat dinding tembok dalam catylac
2 Cat langit-langit
9,500.00
Sub Jumlah
VIII
m'
124,320.00
Sub Jumlah
Harga
Jumlah Harga
( Rp )
159,680.00
207,000.00
366,680.00
744,562.80
168,350.00
863,955.00
1,776,867.80
5,465,344.00
5,465,344.00
3,187,604.80
3,184,802.40
6,372,407.20
9,520,782.60
5,159,923.20
733,918.60
15,414,624.40
3,173,087.00
146,767.50
661,320.00
1,135,697.57
4,162,225.00
1,110,200.00
429,008.20
9,159,595.20
5,815,260.00
1,821,222.00
27,614,382.47
4,288,500.00
545,395.00
4,833,895.00
745,920.00
745,920.00
No
Uraian Pekerjaan
Volume
Satuan
Harga
( Rp )
IX
3
1
1
5
9
unit
unit
unit
unit
m
1,749,000.00
1,749,000.00
225,000.00
895,000.00
425,000.00
Sub Jumlah
Pekerjaan elektrikal
1
2
2
3
3
4
4
5
6
4
2
1
26
4
4
5
unit
unit
unit
unit
ttk
bh
bh
bh
55,000.00
85,000.00
145,000.00
220,000.00
90,000.00
17,500.00
20,000.00
17,500.00
Sub Jumlah
m1
m1
m1
m1
m1
m1
m1
m1
unit
26,700.00
21,550.00
38,500.00
57,500.00
125,000.00
850,000.00
356,000.00
1,325,000.00
1,100,000.00
Sub Jumlah
B Pekerjaan Mekanikal
a. Pemipaan & sanitary
- Pipa air bersih 3/4" wavin AW
- Pipa air bersih 1/2" wavin AW
- Pipa air bekas 3" wavin AW
- Pipa air kotor 4" wavin AW
- Kran air bersih merk TOTO
- Washtafel merk TOTO
- Shower tray merk TOTO
- Closet jongkok merk TOTO
b. Septik tank kapasitas 1,5m3
14.93
7.05
10.93
7.23
4
1
1
1
1
Harga
Jumlah Harga
( Rp )
5,247,000.00
1,749,000.00
225,000.00
4,475,000.00
3,825,000.00
15,521,000.00
330,000.00
340,000.00
290,000.00
220,000.00
2,340,000.00
70,000.00
80,000.00
87,500.00
3,757,500.00
398,631.00
151,927.50
420,805.00
415,725.00
500,000.00
850,000.00
356,000.00
1,325,000.00
1,100,000.00
5,518,088.50