Asas: Ujian Beban 1. Maintaned Load Test i.

Contoh Pengiraan

Beban kerja= Beban ujian =

50 tan 2 x beban kerja = 2 x 50 = 100 ton

Increament untuk menaikkan beban = 100/8 = 12.5 ton Increament untuk menurunkan beban = 100/4 = 425 ton Berat pemberat (kentledge) = 100 + 20% = 120 ton

PROCEDURES

1st Cycle up to Working Load 25% of working load for each increment Maintained minimum 2 hours at each increment Maintained 24 hours at Working Load. Reading is taken at 15 minutes interval Reading of pile settlement is taken before and after increment Unloading at 4 equal stages @ 1 hour interval.

PROCEDURES

2nd Cycle up to Twice Working Load 25% of working load for each increment Up to 2 x working load (8 increments) Maintained minimum 2 hours at each increment ATAU rate of settlement 0.05mm in 15 minutes is reached. Maintained 24 hours at 2 times Working Load. Reading is taken at 15 minutes interval Reading of pile settlement is taken before and after increment Unloading at 4 equal stages @ 1 hour interval. Wait 1 hour after zero load to record residual settlement Plot load/time graph and load settlement graph.

Pile Testing-STATIC LOAD TEST (Cont.)


JKR STANDARD SPECIFICATION FOR BUILDING WORKS 2005 Acceptance Criteria for Static Load Test
1. 2. 3.

At design load s< 12.5mm or, At test load s < 38mm or 10% pile diameter (which is higher), or Residual settlement <6.5mm

LOA D Vs SET T LEM EN T C UR VE


LOA D ( T ON N E)
0 0 -5 25 50 75 100 125 150 175 200 225

-10 -15

-20 -25 -30

-35 -40

WHAT CAN GO WRONG?

Coaxial loading Bearing for the kentledge Spacing & rigidity of the reference beam supports Compliance with STD & Spec (layout & measurement devise)?

INSTRUMENTED BORE PILE