POWER
ELECTRICAL NETWORK
RESERVOIR
GENERATOR
RUNNER
PRESSURE TANK
Alstom Hydro completely assembles, tests and pre-configures the electronic and oleo-hydraulic parts of the governing system at its ISO 9001:2000 manufacturing sites worldwide.
THE UNIT PROCESSING CONTROLLER MODULE (UPC) The uPC module performs the most complex turbine control functions including: Highly accurate rotation speed regulation for synchronisation with the grid, using a specific integrated electronic circuit capable of taking 3 measurements Power/load adjustment Frequency regulation Integration of 2D and 3D laws and numerous parameters to optimize turbine operating
Specific advanced functions for each type of turbine (such as jet dispatcher for Pelton, on-cam operation for Kaplan, individual wicket gate control for Pump turbine etc.) multi-level redundancy (SPC, uPC, sensors).
THE SERVO POSITIONING CONTROLLER MODULE (SPC) The SPC module carries out servo motor position control via a single or double loop position control. Equipped with a universal amplifier, it can control all types of actuators including third party equipment. The NEYRPIC T.SLG can handle up to 24 independent SPC modules, therefore permitting individual gate
control for Pump turbines. moreover, the SPC has both redundancy and hot swap capabilities.
THE TURBINE AUXILIARY DIGITAL TACHOMETER (T.ADT) In addition to the standard uPC and SPC modules, the NEYRPIC T.SLG can also have other modules easily added-on such as the T.ADT. The T.ADT is the ideal product for customers who require a standalone independent tachometer for measuring turbine output with speed thresholds. Designed on the same platform as the T.SLG, the T.ADT can easily work in combination with the NEYRPIC T.SLG governing system. It is a good choice of solution for both new plants and for upgrading outdated mechanical systems in old plants. The T.ADT functions cover: Speed measurement Speed signal redundancy with up to 3 sensors Speed threshold programming and control The T.ADT also offers advanced functions not included in the uPC module such as: Rotation direction detection Creep and stop detection 12 programmable speed thresholds
THE HUMAN MACHINE INTERFACE (HMI) The HMI is the interface used by the operator to manage and adjust the NEYRPIC T.SLG parameters. using a flat-panel touch screen, the operator can intuitively navigate through the menus using the graphical user interface. The HmI can be customized in the users language.
Based on Alstom Hydros experience and know-how, the HMI has all the features a plant operator requires including: Analogue and digital graphic indicators (speed, gate, power, etc.) Quick access to device parameters
THE T.SOFT DIAGNOSTIC TOOL Alstom Hydros T.SOFT maintenance software allows plant operators to monitor and troubleshoot problems autonomously. This user-friendly tool features clear mimics, easy access to parameters, and produces dif ferent t ypes of alarm and event messages with clear instructions for resolving the problem.
The main functions of T.SOFT are: uploading of application software Downloading and storing of parameters Reading and forcing of I/Os Diagnosing a large number of test points using an integrated real-time oscilloscope Tuning of parameters Data recording (Historian) Local and manual mode Fault recorder
The software runs on any standard Windows laptop. T.SOFT communicates with both the T.SLG and the T.ADT via an Ethernet connection.
ED Series
D Series
DF series
valve, the flanged actuator model can also include a manoeuvring time adjustment orifice, an emergency shutdown solenoid valve, an overspeed relay, a multi-slope closure law
valve and redundant sensors. Designed, manufactured and tested at the Alstom Hydro Global Technology Centre, these plug-and-play systems help to increase turbine performance
and reliability. They also eliminate the need for specific performance tests that are normally carried out on site for each project.
10
CANADA La Grande - new: 33 turbine/generator units, 8654 MW. US Shasta - refurbishment: 5 x 142 MW turbine/generator units. MEXICO Chicoasen - new turnkey supply : 3 x 310 MW turbine/ generator units, control system. BRAZIL Itaipu - new: 10 x 700 MW turbine/generator units, control systems. Tucurui - new: 11 x 370 MW turbine/generator units, control system. VENEZUELA Guri 1 - refurbishment Francis: 4 x 400 MW turbine/ generator units.
PORTUGAL Alqueva - new pumped storage: 2 x 130 MW turbine/ generator units, control system. NORWAY New Tyin - new: 2 x 220 MVA generators, BOP, control system. SWITZERLAND Chancy Pougny - refurbishment: 2 x 12 MW turbine/ generator units. TURKEY Uzundere - new: 2 x 30 MW turbine/generator units. FRANCE Grand Maison - new pumped storage: 12 x 157 MW turbine/generator units. MOROCCO Afourer - new pumped storage and irrigation: 2 x 175 + 2 x 60 MW turbine/generator units, BOP, control system. SUDAN Merowe - new turnkey supply: 10 x 125 MW turbine/ generator units, BOP, control system. ZAMBIA Victoria Falls - refurbishment of 2 small power stations: 108 MW turbine/generator units.
CHINA 3 Gorges - new: 14 x 700 MW turbine/generator units, 14 governors, control system. Huizhou, Bailianhe and Baoquan - new, 3 pumped storage plants: 16 x 306 MW turbine/generator units, BOP, control system. SOUTH KOREA Yang Yang - new pumped storage: 4 x 250 MW turbine/generator units with adjustable double-stage. INDIA Subansiri - new turnkey supply: 8 x 250 MW turbine/ generator units, control system. VIETNAM Se San 4 - new: 3 x 120 MW turbine/generator units. Dai Ninh - new: 2 x 150 MW turbines, control system. Dai Ninh - refurbishment: 4 x 40 MW control system. MALAYSIA Bakun - new: 4 x 315 MW turbine/generator units, BOP. AUSTRALIA Trevallyn - refurbishment: 4 x 30 MW turbine/generator units. NEW ZEALAND Manapouri - upgrade: 7 x 135 MVA generators.
11
PWS/BPROB/HTSGS09/eng/HYD/03.09/FR/6823 ALSTOM 2009. All rights reserved. Information contained in this document is provided without liability for information purposes only and is subject to change without notice. No representation or warranty is given or to be implied as to the completeness of information or fitness for any particular purpose. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. - Photo credits: Alstom 2009 - Design & Layout: www.kineka.com.