You are on page 1of 2

Assume you have completed three months of the project.

The BAC was $200 000 for this six month project. Also assume the following: PV = $120,000 EV = $100,000 AC = $90,000 A. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? B. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? C. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

Optional Information: Level/Year: College Subject: IT Project Management A) Cost Variance CV = EV - AC =100,000 - 90,000 =$10,000 Schedule Variance SV = EV-PV =100,000 - 120,000 =-$20,000 Cost Performance Index CPI = EV / AC =100,000 / 90,000 =1.11 Schedule Performance Index SPI = EV / PV =100,000 / 120,000 =0.833 B) The project cost is $90,000 underbudget but $20,000 behind schedule C)Estimate at Completion (EAC)

Estimate To Complete (ETC) = (BAC - EV) / CPI =(200,000 - 100,000) / 1.11 =$90,090 EAC = AC + ETC = 90,000 + 90,090 =$180,090 From the calculation of EAC, we can expect that the project will be completed under budget of $19,910. As such, the project is performing better than planned * Budget variance = BAC - EAC = 200,000 - 180,000 = $19,910

You might also like