1. In ACC Layout - Coordinates has been fixed and the revised layout is submitted to M/s.

PCTL on 19th March 2013. 2. M/s. RPA, M/s AQUATHERM & M/s. CCE informed to M/s. PCTL that drain pot is not required since Turbine Exhaust device shall be used as drain pot supplied by Turbine supplier. Hence suction pipe of Drain pump shall be connected to the Turbine Exhaust device 3. M/s. CCE informed to M/s. PCTL that the Turbine exhaust device flange forces and moments shall be submitted on 22nd March 2013 by M/s. RPA. 4. M/s. CCE submitted the GA drawings of GSC, LP Heater & Deaerator and TG Building Plan & Elevation view on 19th March 2013 5. M/s. CCE informed to M/s. PCTL that the Process parameters & Pressure drop across GSC, LP Heater & Deaerator inlet required pressure shall be submitted by M/s. RPA on 22nd March 2013 6. M/s. PCTL confirmed that the Ejector Motive steam parameters as a. Pressure: 11 ata b. Temperature: 350 oC c. Steam Flow: 4 TPH M/s. PCTL has submitted the