Project: NGHI SON 1 THERMAL POWER PLANT CONSTRUCTON PROJECT

Client: VIETNAM ELECTRICITY Daily C&I Commissioning Schedule and information


Result of 14TH August2013:

1. Unit-2 Main Piping System Logic Check- Continue. 2. Unit-1- DCS Logic modification for STG, Boiler and BOP- Continue. 3. Unit-2- HFO Supply Pump Pressure controller and Temperature Controllers Tuning- Continue. 4. Unit-1- HFO Supply Heater TCV Operation Check- Completed. 5. Unit- 1 Transformer Oily Pit Level Switch Calibration- Completed. 6. Unit-2 Monitoring the Steam Blow out Activities- Continue. 7. Unit-1 & 2 DCS Logic Modification for STG- Completed. 8. Unit-2 Boiler Blow down Pit Level Switch Calibration Check- Completed. 9. HFO Unloading Pump operation Commissioning Support- Postponed.
Plan of 15TH August2013:

1. Unit-2 Main Piping System Logic Check. 2. Unit-1 & 2- DCS Logic modification for STG, Boiler and BOP. 3. Unit-2- HFO Supply Pump Pressure controller and Temperature Controllers Tuning. 4. Unit-2 Monitoring the Steam Blow out Activities. 5. HFO Unloading Pump operation Commissioning Support. 6. Unit-1 Steam Coil Air Heater Drain Pump-01 Motor Trial Run Operation Support.

You might also like