VIA SALOMIA

PRESUPUESTO DE OBRA

SENA CENTRO DE LA CONSTRUCCION REGIONAL VALLE

Obra:

CONSTRUCCION DE UN TRAMO DE VIA EN EL COMPLEJO

FECHA

SALOMIA DEL SENA, REGIONAL VALLE

PLIEGO

ITEM

DESCRIPCION

UNIDAD CANT.

17/Jun/2011

VR. UNIT

VR TOTAL

OBRAS PRELIMINARES

1.1 EXCAVACION A MAQUINA SIN RETIRO

M3

340.8

$ 2,523.00

859,838

1.2 RETIRO DE SALDOS EN SITIO

M3

1366.2

3,052.10

4,169,779

1.3 EXCAVACION TIERRA A AMANO

M3

523.6

7,631.00

3,995,592

1.4 DEMOL. MURO LAD. TIZON E=25-40CM

M2

100

3,231.15

323,115

1.5 DEMOL. ANDEN CONCRETO

M2

80

2,001.50

160,120

1.6 DEMOL. ANDEN -SARDINEL

M2

180

2,770.85

498,753

1.7 DEMOL.PAVIMENTO CONCRETO E=20CM+RET

M2

45

18,929.10

851,810

1.8 DEMOL.CAMARA DE CONCRETO+RETIRO

UND

205,818.00

1,234,908

1.9 RELLENO MATERIAL SITIO COMPACTO

M3

9,351.71

4,691,381

2 CAMPAMENTO STELL DECK

501.66

UND

3,075,740.00

SUBTOTAL OBRAS PREELIMINARES


2
2.1

3,075,740
$ 19,861,035

BASES Y SUBBASES
SUB-BASE COMPACT.MAT.SELECC.(TIPO INVIAS)

M3

466

64281.83

$ 29,955,333

SUBTOTALES BASES Y SUBBASES


3

FILTROS Y TUBERIAS

3.1 GEOTEXTIL NO TEJIDO

M2

932

2362.95

2,202,269

3.2 TUB PVC NOVAFORT 6"

ML

48

29385.52664

1,410,505

3.3 TUB PVC NOVAFORT 10"

ML

84

61787.1992

5,190,125

3.4 TUB PVC NOVAFORT 12"

ML

18

83522.85216

1,503,411

3.5 SILLA YEE NOVAFORT DIAMETRO DE 6" A 10"

UND

159344.791

637,379

3.6 COLCHON ARENA-GRAVA TUBER.

M3

23.4

39752.4

930,206

3.7 TUB.PVC 4 DREN.NOVAF

ML

130

32755.8

SUBTOTAL FILTROS Y TUBERIAS

4,258,254
$ 16,132,150

4 PAVIMENTO
4.1 PAV.CONCR.MR=40,E=0,20,INC.HIER,JUNTA

M2

606.303

50238.67

4.2 ANDEN CONCRETO ESTAMPADO 10CM 3000 PSI

M2

1226.143

31379.62

4.3 DEMOL. LOSA CONCRETO E=20CMS

M2

48

28851.2

4.4 SARDINEL EN CONCRETO 15X15 MAS HIERRO

ML

533

11715.4

4.5 RECUBRIMIENTO CONCRETO TUBERIA

M3

14.4

223125

30,459,856
38,475,901
1,384,858
6,244,308
3,213,000

VIA SALOMIA

PRESUPUESTO DE OBRA

SENA CENTRO DE LA CONSTRUCCION REGIONAL VALLE

Obra:

CONSTRUCCION DE UN TRAMO DE VIA EN EL COMPLEJO

FECHA

SALOMIA DEL SENA, REGIONAL VALLE

PLIEGO

ITEM

DESCRIPCION

UNIDAD CANT.

17/Jun/2011

VR. UNIT

VR TOTAL

4.6 ACERO REFUERZO FLEJADO 60000 PSI 420Mpa

KLS

200

3124.14

4.7 ADOQUIN CONCRETO ECOLOGICO- GRAMOQUIN

M2

186.926

39239

SUBTOTAL PAVIMENTOS

624,828
7,334,789
$ 80,402,752

5 CAMARAS Y SUMIDEROS
5.1 SUMIDERO DOBLE

UND

5.2 CAMARA INSPECCION TIPO B H=0,00-1,50MTS

UND

5.3 CAJA ELECTRICA 0,08X0,08 X 1,0MT

UND

5.5 COLCHON ARENA - GRAVA TUBER.

M3

6
6.1
6.2
6.3
6.4

AMOBLAMIENTO URBANO
MURO CONCRETO CONTENCION 0 <H<=1,0 MTS
BANCA CONCRETO
REFLECTOR METAL HALIDE 250 WATIOS
SOPORTE PARA REFLECTOR

370824.75

2,966,598

717305

2,869,220

203005.75

1,624,046

16.2

38331.2

620,965

SUBTOTAL CAMARAS Y SUMIDEROS

$ 8,080,829

M3
4.55
309862.68
UND
5
119243.5
UND
10
766367.89
UND
10
57451.1
SUBTOTAL AMOBLAMIENTO URBANO

1,409,875
596,218
7,663,679
574,511
$ 10,244,283

VALOR TOTAL COSTOS DIRECTOS


COSTOS INDIRECTOS
TOTAL COSTOS DIRECTOS
ADMINISTRACION
IMPREVISTOS
UTILIDAD
TOTAL A.I.U.
VALOR TOTAL DE PRESUPUESTO

$ 164,676,382

SERVICIO NACIONAL DE APRENDIZAJE SENA - REGIONAL VALLE DEL CAUCA


CENTRO DE LA CONSTRUCCION - CALI
OBRA:

CONSTRUCCION DE UN TRAMO DE VIA EN EL COMPLEJO SALOMIA DEL SENA

ANALISIS DE PRECIOS UNITARIOS

1 OBRAS PREELIMINARES
ITEM:

1.1 EXCAVACION A MAQUINA SIN RETIRO

010203
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0205

RETROEXCAVADORA JD 510

HRA

0.030
SUBTOTAL EQUIPO Y HERRAMIENTA

ITEM:

1.2 RETIRO DE SALDOS EN SITIO

010812
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0103

CARRETA TIPO BUGUI

DIA

0.070

MQ0301

HERRAMIENTA MENOR

GLB

0.200
SUBTOTAL EQUIPO Y HERRAMIENTA

MANO DE OBRA
MOAG01

1 AYUDANTE

H-H

0.700
SUBTOTAL MANO DE OBRA

ITEM:

1.3 EXCAVACION TIERRA A MANO

080107
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0301

HERRAMIENTA MENOR

GLB

0.100
SUBTOTAL EQUIPO Y HERRAMIENTA

MANO DE OBRA
MOAG01

1 AYUDANTE

H-H

2.000
SUBTOTAL MANO DE OBRA

ITEM:

1.4 DEMOL. MURO LADRILLO TIZON E=25-40 CM.

100316
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0301

HERRAMIENTA MENOR

GLB

0.183
SUBTOTAL EQUIPO Y HERRAMIENTA

MANO DE OBRA
MOAG01

1 AYUDANTE

H-H

0.800

SUBTOTAL MANO DE OBRA

ITEM:

1.5 DEMOLICION ANDEN EN CONCRETO

100401
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0301

HERRAMIENTA MENOR

GLB

0.100
SUBTOTAL EQUIPO Y HERRAMIENTA

MANO DE OBRA
MOAG01

1 AYUDANTE

H-H

0.500
SUBTOTAL MANO DE OBRA

ITEM:

1.6 DEMOLICION ANDEN-SARDINEL

100402
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0301

HERRAMIENTA MENOR

GLB

0.115
SUBTOTAL EQUIPO Y HERRAMIENTA

MANO DE OBRA
MOAG01

1 AYUDANTE

H-H

0.700
SUBTOTAL MANO DE OBRA

ITEM:

1.7 DEMOL. PAVIMENTO CONCRETO E=20CM + RET.

081003
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0105

COMPRESOR DE DOS MARTILLOS

HRA

0.200

MQ0221

VOLQUETA (ACARREO)

M3K

0.240

MQ0301

HERRAMIENTA MENOR

GLB

0.050
SUBTOTAL EQUIPO Y HERRAMIENTA

MANO DE OBRA
MOAG01

1 AYUDANTE

H-H

0.200
SUBTOTAL MANO DE OBRA

ITEM:

01.08 DEMOLICION CAMARA DE CONCRETO + RETIRO

010103
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0105

COMPRESOR DE DOS MARTILLOS

HRA

2.000

MQ0207

VOLQUETA 5 M3

VJE

0.260

MQ0301

HERRAMIENTA MENOR

GLB

1.000
SUBTOTAL EQUIPO Y HERRAMIENTA

MANO DE OBRA

MOAG01

1 AYUDANTE

H-H

4.000
SUBTOTAL MANO DE OBRA

ITEM:

01.09 RELLENO MATERIAL SITIO COMPACTADO

010206
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

EQUIPO Y HERRAMIENTA
MQ0204

MOTONIVELADORA CAT-12-F

HRA

0.047

MQ0206

VIBROCOMPACTADOR CA-15

HRA

0.047

MQ0222

CARROTANQUE AGUA

HRA

0.060

MQ0301

HERRAMIENTA MENOR

GLB

0.030
SUBTOTAL EQUIPO Y HERRAMIENTA

MANO DE OBRA
MOAG03

3 AYUDANTE

H-C

0.046
SUBTOTAL MANO DE OBRA

2 BASES Y SUB-BASES
ITEM:

2,1 SUB-BASE COMPACT.MAT.SELEC.


80207

CODIGO

DESCRIPCION

UNIDAD

5608 SUB-BASE TRITURADA - COMPACTADA


MOAG03

MANO OBRA ALBANILERIA 3 AYUDANTE

MQ0204
MQ0206
MQ0221
MQ0222

MOTONIVELADORA CAT-12-F

CANTIDAD

M3

1.300

HC

0.046

HRS

VIBROCOMPACTADOR CA-15

HRS

VOLQUETA(ACARREO)

M3K

CARROTANQUE AGUA

DIA

0.046
0.09
13
0.001

TOTAL ANALISIS
3 FILTROS Y TUBERIA
ITEM:

3,1 GEOTEXTIL NO TEJIDO


110903

CODIGO

DESCRIPCION

UNIDAD

203 GEOTEXTIL NO TEJ. REF 1600 REF 1600

CANTIDAD

M2

MOAG01

MANO OBRA ALBANILERIA 1 AYUDANTE

HC

0.15

MQ0301

HERRAMIENTA MENOR

GLB

0.04
TOTAL ANALISIS

ITEM:

3,2 TUB.PVC NOVAFORT 6".


20705

CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

193 TUBO SAN 6" PVC-160MM NOVAFORT

ML

238 HIDROSELLO NOVAFORT 160MM PAVCO

UND

0.33

521 ADHESIVO NOVAFORT

GLN

0.002

GLN

0.002

PAVCO

522 ACONDICION SUPERF NOVAFORT PAVCO


MOAG02

MANO OBRA ALBANILERIA 2 AYUDANTE

MOIS01

MANO OBRA HIDROSANIT. 1 AYUDANTE-1 OFI


TOTAL ANALISIS

HC

0.2

HC

0.4

ITEM:

3,3 TUB PVC NOVAFORT 10"


20707

CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

192 TUBO SAN 10" PVC-250MM NOVAFORT

ML

241 HIDROSELLO NOVAFORT 250MM PAVCO

UND

0.33

521 ADHESIVO NOVAFORT

GLN

0.002

GLN

0.002

PAVCO

522 ACONDICION SUPERF NOVAFORT PAVCO

MOAG02

MANO OBRA ALBANILERIA 2 AYUDANTE

HC

0.2

MOIS01

MANO OBRA HIDROSANIT. 1 AYUDANTE-1 OFI

HC

0.4

TOTAL ANALISIS
ITEM:

3,4 TUB PVC NOVAFORT 12"


20708

CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

191 TUBO SAN 12" PVC-315MM NOVAFORT

ML

242 HIDROSELLO NOVAFORT 315MM PAVCO

UND

0.33

251 HIDROSELLO NOVAFORT 315MM PAVCO

GLN

0.003

522 ACONDICION SUPERF NOVAFORT PAVCO

GLN

0.003

MOAG02

MANO OBRA ALBANILERIA 2 AYUDANTE

HC

0.2

MOIS01

MANO OBRA HIDROSANIT. 1 AYUDANTE-1 OFI

HC

0.4

TOTAL ANALISIS
ITEM:

3,5 SILLA YEE NOVAFORT DIAMETRO DE 6" A 10"


110652

CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

220 SILLA YEE NOVAF 250x160MM PAVCO

UND

521 ADHESIVO NOVAFORT

GLN

0.002

GLN

0.002

PAVCO

522 ACONDICION SUPERF NOVAFORT PAVCO


MOIS01

MANO OBRA HIDROSANIT. 1 AYUDANTE-1 OFI

HC

0.5

TOTAL ANALISIS
ITEM:

3,6 COLCHON ARENA-GRAVA TUBER


110901

CODIGO

DESCRIPCION

UNIDAD

224 ARENA GRUESA

CANTIDAD

M3

0.6

.3/4 COLOR AZUL

M3

0.4

MOAG02

MANO OBRA ALBANILERIA 2 AYUDANTE

HC

0.4

MQ0227

VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS

M3

HERRAMIENTA MENOR

GLB

0.6

1350 GRAVA TRITURADA

MQ0301

TOTAL ANALISIS
ITEM:

3,7 TUB.PVC 4 DREN.NOVAFOT


110507

CODIGO

DESCRIPCION

UNIDAD

196
1352 GRAVILLA FINA

CANTIDAD

ML

M3

0.032

MOIS01

MANO OBRA HIDROSANIT. 1 AYUDANTE-1 OFI

HC

0.4

MQ0301

HERRAMIENTA MENOR

GLB

0.5

TOTAL ANALISIS
4 PAVIMENTO

ITEM:

4,1 PAV.CONCR.MR=40,E=0,INC,HIER,JUNTA

CODIGO

DESCRIPCION

UNIDAD

181 ANTISOL ROJO


2482 SIKA FLEX 1A SELLADOR

C=300CC ELASTICO POLIURETANO

5609 BAKE-ROD (ESPUMA DE POLIET TIRILLA DE RESPALDO (JUNTAS)

CANTIDAD

KLS

0.2

UND

0.15

UND

0.4

ME0101

MEZCLA CONCRETO 1:2:2 4000 PSI-28.0MPa

M3

0.15

MOAG01

MANO OBRA ALBANILERIA 1 AYUDANTE

HC

0.16

MOAG15

MANO OBRA ALBANILERIA 5 AYUDANTE-1 OFI

HC

0.17

MQ0117

REGLA VIBRATORIA DE 4MTS

DIA

0.02

MQ0127

CORTADORA DE PAVIMENTO

ML

0.4

MQ0140

EQUIPO DE ACABADO SUPERFICIAL

DIA

0.01

MQ0301

HERRAMIENTA MENOR

GLB

0.1

MQ0301

HERRAMIENTA MENOR

GLB

0.1

MQ0501

FORMALETA MET.PAVIMENTO 0.15X0.20X3MTS

DIA

0.5

TOTAL ANALISIS

ITEM:
200132
CODIGO
1617
2293
ME0105
MOAG11
MQ0227
MQ0301

4,2 ANDEN CONCRETO ESTAMPADO 10 CM 3000 PSI


DESCRIPCION
LISTON 1 x4x300 OTOBO
PUNTILLA 1.1/2
CC 363 UND/LB
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA
MANO OBRA ALBANILERIA 1 AYUDANTE-1 OFI
VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS
HERRAMIENTA MENOR
TOTAL ANALISIS

UNIDAD
UND
LBS
M3
HC
M3
GLB

4,3 DEMOL.LOSA CONCRETO E=20CMS


10105
CODIGO
DESCRIPCION
UNIDAD
MOAG01
MANO OBRA ALBANILERIA 1 AYUDANTE
HC
MQ0105
COMPRESOR DE DOS MARTILLOS
HRS
MQ0301
HERRAMIENTA MENOR
GLB
TOTAL ANALISIS

CANTIDAD
0.335
0.05
0.1
0.7
0.15
0.1

ITEM:

4,4 SARDINEL EN CONCRETO 15X15 MAS HIERRO


80522
CODIGO
DESCRIPCION
180 ANTISOL BLANCO UNX20 KG. CURADOR R:120002
4600 HIERR.DE 37000 PSI 259 MPA U
ME0105
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA
MOAG12
MANO OBRA ALBANILERIA 2 AYUDANTE-1 OFI
MQ0123
VIBRADOR A GASOLINA
MQ0301
HERRAMIENTA MENOR
FORMALETA MET.PAVIMENTO 0.15X0.20X3MTS
TOTAL ANALISIS

CANTIDAD
0.4
0.3
0.4

ITEM:

ITEM:
20421
CODIGO

UNIDAD
KLS
KLS
M3
HC
DIA
GLB
DIA

CANTIDAD
0.1
0.8
0.023
0.25
0.02
0.08
0.6

4,5RECUBRIMIENTO CONCRETO TUBERIA


DESCRIPCION

UNIDAD

CANTIDAD

ME0105
MOAG12

MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA


MANO OBRA ALBANILERIA 2 AYUDANTE-1 OFI
TOTAL ANALISIS

ITEM:

M3
HC

1
2.5

4,6 ACERO REFUERZO FLEJADO 60000 PSI 420Mpa

120101
CODIGO
111
2458
3999
MOAG01

DESCRIPCION
ALAMBRE NEGRO
# 18 R=50K MTS/KLS-1.24M
SEGUETA SIN MARCO
HIERR.DE 60000 PSI 420 MPA
MANO OBRA ALBANILERIA 1 AYUDANTE
TOTAL ANALISIS

UNIDAD
KLS
UND
KLS
HC

CANTIDAD
0.03
0.03
1.03
0.04

CAMARAS Y SUMIDEROS
ITEM:
20407 5. 1 SUMIDERO DOBLE
CODIGO

DESCRIPCION

UNIDAD

CANTIDAD

UND

HIERRO .1/2" 60.000 [6M] VARILLA CORRUGADA

KG.

33

PUNTILLA .1/2

LBS

UND

3
0.7

1046

CUARTON 2"x4"x300 OTOBO

1722
2322
2556

TABLA 1x10x300 OTOBO

AC
X

ME0105

MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA

M3

MOAG12

MANO OBRA ALBANILERIA 2 AYUDANTE-1 OFI

HC

MQ0124

VIBRADOR ELECTRICO

DIA

0.5

MQ0301

HERRAMIENTA MENOR

GLB

0.003

UNIDAD

CANTIDAD

TOTAL ANALISIS
ITEM:
20403 5.2 camara de inspeccion tipo b h=00.-1.50 mts
CODIGO

DESCRIPCION

2556 TABLA 1x10x300 OTOBO

UND

3890 FORMALETA CAMARA INSPECCIO METALICA

UND

3999 HIERR.DE 60000 PSI 420 MPA

KLS

52.5

4600 HIERR.DE 37000 PSI 259 MPA U

KLS

ME0105

MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA

M3

2.180

ME0203

MORTERO 1:2

M3

0.01

MOAG12

MANO OBRA ALBANILERIA 2 AYUDANTE-1 OFI

HC

10

TOTAL ANALISIS
ITEM:
60803 5.3 caja electrica 0.8X0.8X1.OMT
CODIGO

DESCRIPCION
# 18 R=50K MTS/KLS-1.24M

UNIDAD

CANTIDAD

111

ALAMBRE NEGRO

KLS

0.050

1720

HIERRO .3/8" 37.000 [CH] EN CHIPA

KLS

4.520

1761

ANGULO 1,1/2 x 3/16

UND

0.400

TIRA DE 6 METROS

2414

ROCA MUERTA

M3

0.180

2558

TABLA 1x05x300 OTOBO [1C]

SIN TRANSPORTE

UND

4.000

3569

SOLDADURA 6011 x 1/8"

KLS

0.150

4600

HIERR.DE 37000 PSI 259 MPA U

KLS

0.600

VARILLA - ELECTRICA

ME0105

MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA

M3

0.400

ME0203

MORTERO 1:2

M3

0.050

MOAG01

MANO OBRA ALBANILERIA 1 AYUDANTE

HC

0.300

MOAG11

MANO OBRA ALBANILERIA 1 AYUDANTE-1 OFI

MOME01

MANO OBRA METALISTERIA 1 AYUDANTE-1 OFI

MQ0301

HERRAMIENTA MENOR

HC

6.000

HC

0.500

GLB

1.000

TOTAL ANALISIS

ITEM
110901

5.5 COLCHONDE ARENA -GRAVA TUBER.

CODIGO

UNIDAD

CANTIDAD

224

ARENA GRUESA

DESCRIPCION

M3

0.6

1350

GRAVA TRITURADA .3/4

M3

0.4
0.4

M0AG11

MANO OBRA ALBANILERIA 2 AYUDANTE

HC

MQ0227

VOLQUETA TRANSPORTE MAT.PETREOS 1-10KMS

M3

MQ0301

HERRAMIENTA MENOR

GLB

0.6

TOTAL ANALISIS

6 AMOBLAMIENTO URBANO
ITEM:
80809
CODIGO
2294
2558
3584
3688
ME0105
MOAG13
MQ0124
MQ0301

6,1 MURO CONCRETO CONTENCION 0 <H<=1,0 MTS


DESCRIPCION
PUNTILLA 2 CC
TABLA 1x05x300 OTOBO [1C]
CUARTON 2"x4"x300
CINTA PVC JUNTA V-10
ROLLO 30 MTS
MEZCLA CONCRETO 1:2:3 3100 PSI 21 MPA
MANO OBRA ALBANILERIA 3 AYUDANTE-1 OIF
VIBRADOR ELECTRICO
HERRAMIENTA MENOR
TOTAL ANALISIS

6,2 BANCA CONCRETO


280408
CODIGO
DESCRIPCION
1164 BANCA CONCR.COMPLETA
L=110 H=90CM PREFABRICADA
MOAG11
MANO OBRA ALBANILERIA 1 AYUDANTE-1 OFI
MQ0301
HERRAMIENTA MENOR
TOTAL ANALISIS

UNIDAD
LBS
UND
ML
ML
M3
HC
DIA
GLB

CANTIDAD
0.1
0.2
0.1
3
1.03
5
0.04
0.02

UNIDAD
UNIDAD
HC
GLB

CANTIDAD

UNIDAD
ML
UND
UND
HC

CANTIDAD
10
1
1
0.31

ITEM:

ITEM:

6,3 REFLECTOR METAL HALIDE 250 WATIOS

60714
CODIGO
4041
4404
4498
MOIE03

DESCRIPCION
ALAMBRE COBRE THWN #12 CENTELSA
REFLECTOR MET-HALIDE 250 W ILUMINACION
BOMBILLO MET.HALIDE 250 W ILUMINACION (HOMOLOGADO
MANO OBRA ING.ELECTR 3 AYUD-1 OFI-1 PROF

1
0.5
0.1

MQ0301

HERRAMIENTA MENOR

GLB

2.332

TOTAL ANALISIS
ITEM:

ADOQUIN CONCRETO ECOLOGICO- GRAMOQUIN

200447
CODIGO
210
224
1844
MQ0301

DESCRIPCION
ARENA FINA
ARENA GRUESA
ADOQ CONCRETO ECOL- GRAMA 30.0x45.0x08 PREMOLDA
HERRAMIENTA MENOR

UNIDAD
M3
M3
UND
GLB

CANTIDAD
0.001
0.006
8
0.1

1 AYUDANTE

HC

1 OFICIAL

HC

MANO DE OBRA
MOAG01

1
SUBTOTAL MANO DE OBRA

ITEM:
60720
CODIGO
1761
4254
4277
MOIE03
MQ0301

6,4 SOPORTE PARA REFLECTOR


DESCRIPCION
UNIDAD
ANGULO 1,1/2 x 3/16 TIRA DE 6 METROS
UND
BANDA COPA DOBLE 6"
CONJUNTO PRIMARIO Y SECUNDARIO UND
TORN CARRUAJE 5/8X 1.1/2" CONJUNTO PRIMARIO Y SECUNDARIOUND
MANO OBRA ING.ELECTR 3 AYUD-1 OFI-1 PROF
HC
HERRAMIENTA MENOR
GLB
TOTAL ANALISIS

____________________________________________________________
VIA SALOMIA
SENA CENTRO DE LA CONSTRUCCION REGIONAL VALLE

CANTIDAD
0.25
1
3
0.3
0.88

ALLE DEL CAUCA

FECHA:

06-09-2011.

UNIDAD:

M3

PRECIO

VALOR

84,100.00

$ 2,523

SUBTOTAL EQUIPO Y HERRAMIENTA

2,523.00

TOTAL ANALISIS

$ 2,523.00

UNIDAD:
PRECIO

M3
VALOR

2,500.00

$ 175

1,250.00

250.00

SUBTOTAL EQUIPO Y HERRAMIENTA

425.00

3,753.00

2,627.10

SUBTOTAL MANO DE OBRA

2,627.10

TOTAL ANALISIS

$ 3,052.10

UNIDAD:
PRECIO

M3
VALOR

1,250.00

125.00

SUBTOTAL EQUIPO Y HERRAMIENTA

125.00

3,753.00

7,506.00

SUBTOTAL MANO DE OBRA

7,506.00

TOTAL ANALISIS

$ 7,631.00

UNIDAD:
PRECIO

M2
VALOR

1,250.00

228.75

SUBTOTAL EQUIPO Y HERRAMIENTA

228.75

3,753.00

3,002.40

0.56

SUBTOTAL MANO DE OBRA

3,002.40

TOTAL ANALISIS

$ 3,231.15

UNIDAD:
PRECIO

M2
VALOR

1,250.00

125.00

SUBTOTAL EQUIPO Y HERRAMIENTA

125.00

3,753.00

1,876.50

SUBTOTAL MANO DE OBRA

1,876.50

TOTAL ANALISIS

$ 2,001.50

UNIDAD:
PRECIO

M2
VALOR

1,250.00

143.75

SUBTOTAL EQUIPO Y HERRAMIENTA

143.75

3,753.00

2,627.10

SUBTOTAL MANO DE OBRA

2,627.10

TOTAL ANALISIS

$ 2,770.85

UNIDAD:
PRECIO

M2
VALOR

89,500.00

17,900.00

900.00

216.00

1,250.00

62.50

SUBTOTAL EQUIPO Y HERRAMIENTA

18,178.50

3,753.00

750.60

SUBTOTAL MANO DE OBRA

750.60

TOTAL ANALISIS

$ 18,929.10

UNIDAD:
PRECIO

UND
VALOR

89,500.00

179,000.00

40,600.00

10,556.00

1,250.00

1,250.00

SUBTOTAL EQUIPO Y HERRAMIENTA

190,806.00

3,753.00

15,012.00

SUBTOTAL MANO DE OBRA

15,012.00

TOTAL ANALISIS

$ 205,818.00

UNIDAD:

M3

PRECIO

VALOR

89,900.00

4,225.30

85,000.00

3,995.00

9,600.00

576.00

1,250.00

37.50

SUBTOTAL EQUIPO Y HERRAMIENTA

8,833.80

11,259.00

517.91

SUBTOTAL MANO DE OBRA

517.91

TOTAL ANALISIS

$ 9,351.71

UNIDAD:

M3

PRECIO

VALOR

30600

39780

11259

776.43

89900

4135.4

85000

7650

900

11700

240000

240
64281.83

UNIDAD:

M2

PRECIO

VALOR

1750

1750

3753

562.95

1250

50

TOTAL ANALISIS

2362.95

UNIDAD:

ML

PRECIO

VALOR

23324.12

23324.12

2641.32

871.6356

54098

108.196

74787.52

149.57504

7506

1501.2

8577

3430.8
29385.52664

9600

UNIDAD:

ML

PRECIO

VALOR

50156.08

50156.08

8339.24

2751.9492

54098

108.196

74787

149.574

11253

2250.6

15927

6370.8
61787.1992

UNIDAD:

ML

PRECIO

VALOR

72432.72

72432.72

17489.32

5771.4756

54098

162.294

74787.52

224.36256

7506

1501.2

8577

3430.8
83522.85216

UNIDAD:

UND

PRECIO

VALOR

154798.52

154798.52

54098

108.196

74787.52

149.57504

8577

4288.5
159344.791

UNIDAD:

M3

PRECIO

VALOR

30000

18000

30000

12000

7506

3002.4

6000

6000

1250

750
39752.4

UNIDAD:

ML

PRECIO
27724

VALOR
27724

30500

976

8577

3430.8

1250

625
32755.8

UNIDAD:

M2

PRECIO

VALOR

9900

1980

21808

3271.2

465

186

223280

33492

5627

900.32

37495

6374.15

33000

660

5800

2320

20500

205

1250

125

1250

125

1200

600
50238.67

PRECIO
1572
2100
192300
14990
6000
1250

VALOR
526.62
105
19230
10493
900
125
31379.62

PRECIO
3753
89500
1250

VALOR
1501.2
26850
500
28851.2

PRECIO
5980
2650
192300
12330
33600
1250
1200

VALOR
598
2120
4422.9
3082.5
672
100
720
11715.4

PRECIO

VALOR

192300
12330

PRECIO
3100
2552
2650
5627

192300
30825
223125

VALOR
93
76.56
2729.5
225.08
3124.14

OS
PRECIO

VALOR

8000

24,000

2650

88,245

3300

3,300

6000

18,000

192300

134,610

12330

86,310

32712

16,356

1250

4
$ 370,825

PRECIO

VALOR

7100

7100

15000

15000

2650

139125

2650

10600

192300

419214

296600

2966

12330

123300
717305

PRECIO

VALOR

3100

155

2300

10396

44900

17960

5500

990

4106

16424

6199

929.85

2615

1569

192300

76920

296600

14830

3753

1125.9

8577

51462

17988

8994

1250

1250
203005.75

PRECIO

VALOR

23000

13800

33200

13280

11253

4501.2

6000

6000

1250

750
38331.2

PRECIO
2000
4106
2240
9600
192300
16083
32712
1250

VALOR
200
821.2
224
28800
198069
80415
1308.48
25
309862.68

PRECIO
114840
8557
1250

VALOR
114840
4278.5
125
119243.5

PRECIO
2422.08
649600
65564
77639

VALOR
24220.8
649600
65564
24068.09

1250

UND

2915
766367.89
M2

PRECIO
VALOR
23000
23
23000
138
3900
31200
1250
125

3,753.00

3,753.00

4,000.00

4,000.00

SUBTOTAL MANO DE OBRA

7,753.00

TOTAL ANALISIS

$ 39,239.00

PRECIO
44900
17119
1571.8
77639
1250

VALOR
11225
17119
4715.4
23291.7
1100
57451.1

ANALIZIS BASICO
DEMANO DE OBRA
SUBSIDIO

OFICIAL
AYUDANTE

ITEM

VALOR-HORA
TRANSPORTE
SUELDO
APORTES /56,3%
TOTAL
/240 HORAS-MESREDONDEADO
700000
394100
63800
1157900 4824.583333
$ 4,824
535600
301542.8
63800
900942.8 3753.928333
$ 3,753

CODIGO
ME0101

ITEM
200132

ITEM
60803

CODIGO
ME0105

CODIGO
ME0203

CONCRETO
MEZCLA CONCRETO 1:2:2
3500 PSI-28.0MPa

ANALIZIS BASICO DE CONCRETOS


DESCRIPCION
UNIDAD
CANTIDAD
CEMENTO
ARENA
GRAVA
AGUA

DESCRIPCION
CEMENTO
MEZCLA CONCRETO 1:2:3 ARENA
3000 PSI 21 MPA
GRAVA
AGUA

sacos
m3
m3
agr seco

8.5
0.67
0.67
229

CONCRETO

UNIDAD
sacos
m3
m3
agr seco

CANTIDAD
7
0.555
0.835
180

MORTERO

DESCRIPCION
UNIDAD
CEMENTO
sacos
ARENA
m3
AGUA
agr seco

CANTIDAD
12.5
0.97
250

MORTERO 1:2

VALOR UNITARIO
21000
30000
30000
20
TOTAL
VALOR UNITARIO
21000
30000
30000
20
TOTAL
VALOR UNITARIO
21000
30000
20
TOTAL

VALOR TOTAL
178500
20100
20100
4580
$ 223,280
VALOR TOTAL
147000
16650
25050
$ 3,600
$ 192,300
VALOR TOTAL
262500
29100
5000
$ 296,600

A.P.U CAMPAMENTO STELL DECK

MATERIALES

UND

CANTIDAD

VLR UNITARIO

TOTAL

PERFIL ESTRUCTURAL 12 CM X 6M

UND

12

39,700.00

476,400.00

STELL DECK .95X6.1M

UND

14

139,900.00

1,958,600.00

ANGULO HIERRO 2X2 X1/8 X 6M

UND

34,300.00

68,600.00

TUBERIA CUADRADA 1 1/2 X 1 1/2

UND

19,900.00

39,800.00

PERNO GALVANIZADO 1/2 X 1/2

GLB

20,000.00

20,000.00

REMACHE 2 1/4" X 1/8

UND

200

160.00

32,000.00

BISAGRA

UND

730.00

5,840.00

CADENA

6,000.00

12,000.00

CANDADO

UND

50,000.00

100,000.00

PISO EN FORMALETA DE MADERA DE .70X1.40


TOTAL MATERIALES

UND

25

14,500.00

362,500.00
$ 3,075,740.00