KEGIATAN : APBD KABUPATEN BLORA PEKERJAAN : PENINGKATAN JALAN KAMOLAN- BANJAREJO LOKASI : KECAMATAN BLORA/KECAMATAN BANJAREJO

PERSYARATAN UMUM
Start: 13/06/13 Finish: 19/06/13 Comp: 0% ID: 1 Dur: 5 days

Direksi Keet
Start: 13/06/13 Finish: 19/06/13 Res: ID: 2 Dur: 5 days

PEKERJAAN TANAH PENYIAPAN BADAN JALAN


Start: 20/06/13 Finish: 02/10/13 Comp: 0% ID: 3 Dur: 75 days

Galian Tanah Keras (Bahu Jalan)


Start: 20/06/13 Finish: 11/09/13 Res: ID: 4 Dur: 60 days

Timbunan Bahu Jalan (Grosok Tahunan)


Start: 27/06/13 Finish: 02/10/13 Res: ID: 6 Dur: 70 days

Galian Tanah Keras (Badan Jalan)


Start: 20/06/13 Finish: 21/08/13 Res: ID: 5 Dur: 45 days

PEKERJAAN JALAN
Start: 27/06/13 Finish: 12/09/13 Comp: 0% ID: 7 Dur: 56 days

Lapis Pondasi Atas (LPA) Kelas A


Start: 27/06/13 Finish: 04/09/13 Res: ID: 8 Dur: 50 days

Lapis Resap Pengikat (Prime Coat)


Start: 22/08/13 Finish: 11/09/13 Res: ID: 9 Dur: 15 days

Lapis Aspal Beton Pondasi Atas Perata (ATBL)


Start: 23/08/13 Finish: 12/09/13 Res: ID: 10 Dur: 15 days

Memasang Aspal Beton (Laston)


Start: 23/08/13 Finish: 12/09/13 Res: ID: 11 Dur: 15 days

Page 1

KEGIATAN : APBD KABUPATEN BLORA PEKERJAAN : PENINGKATAN JALAN KAMOLAN- BANJAREJO LOKASI : KECAMATAN BLORA/KECAMATAN BANJAREJO

Project: 3A GEDUNG PREDECESSO Date: Mon 29/07/13

Critical Noncritical

Critical Milestone Milestone

Critical Summary Summary

Critical Inserted Inserted

Critical Marked Marked Page 2

Critical External External

Project Summary Highlighted Critical

Highlighted Noncritical

You might also like