Professional Documents
Culture Documents
Piles
2013
HTTP://WWW.ARAB-ENG.ORG/VB/F5/
.
, .
.
{ " } { }
"
( )
.
: : : : Piles :
.
" : .
" /( ) Cast in situ bored Piles
," .
:
.
.
.
.
Replacement piles
:
( ) cast in situ
, Pre-cast .... " "
.Cast in situ bored Piles .
.
... .. .. .
( ( )Pile Cap Raft foundation )
:
End-bearing -1
.
Friction pile -2
.
-3 " .
* :
-1 ( ) shear wall
.
-2 .
-3 ( )Pile Cap
( 2 3
)
..
-4 ( )
.
-5 ( ( ) Fcu , Fy"
. N/m240
-6 :
- 80
. " " BS8004 , cm100
, ,
. 60
" 130 ( .
)
-7
( " ) .
-1 .
-2 (
).
-3 (
).
-4 .
: Cut off level -5 "
( - )
( .
)sec.X-X
" / (
)Trimming
:
-1 :
.
-2 :
+ (
" "
)
( 13 ) +
( PCC )pile head
" ( cut off level "
) - - :
(
)
.
10 ( ) pile cap ( )
pcc 10
PCC .
.
:
" .
" .
: 2 + 1
Cut off level
.
Trimming of pile 3 .
:
:
-1 ( ) bench mark
.
-2 ( )
30- (
30 ) .
-4 16 = 80 .
(
) -
= + = 60 100 +
= (.)160-
10 " = 10 + = (+ )160-
10 = ( . ) 150-
= 80 " = +
= ( 80 + )150- = ( . ) 70-
-
= ( ) 30-
= 40 .
" 40
( . )
"
( 40 ) "
= 40 +
80 = 120 .
.