Course Objectives
By the end of the course the participant should be able identify the following;
When PPAP submission is required The requirements for part approval Submission levels and the retention requirements Definition of requirements Part Submission status
Dana Quality Assurance Services 2

So what is PPAP?
PPAP
Production Part Approval Process PPAP defines the requirements for production part approval, including production and bulk materials

Dana Quality Assurance Services

Applicability
PPAP applies to all internal and external suppliers of;
bulk materials production materials production parts service parts

Dana Quality Assurance Services

Foreword to PPAP Third Edition


Inclusion of requirements for bulk material Bulk material-specific appendix Industry specific appendix Tire industry specific appendix Cpk/PpK = Initial process studies Clarification

Dana Quality Assurance Services

PPAP Third edition


Effective date

February 1, 2000
Dana Quality Assurance Services 6

Production Part Approval Process

PPAP is a mandatory requirement of QS 9000 Element 4.2.4


so is Subcontractor PPAP requirements 4.2.4.2
Dana Quality Assurance Services 7

PPAP - When Submission is required


A full Production Part Approval is always required before shipment of the first production in the following situations;
1. A new part or product - something not previously supplied before 2. Correction of discrepancy on a previously submitted product 3. Engineering change on part or product 4. Other
Dana Quality Assurance Services 8

Definition of Other
In any of these other situations the supplier is required to notify the customer who may subsequently elect to require a submission for PPAP approval.

Driven by design and/or process changes