Pennsylvania Department of Environmental Protection
milo |
2 Public Square
Wilkes-Barre, PA 18711-0790
June 18, 2009
Northeast Regional Office 570-826-2511
Fax 570-830-3016
Lynn Township
7911 Kings Highway
New Tripoli, PA 18066
Attention: Ms. Tammy White, Secretary
Re: Official Sewage Facilities Plan Update Revision
Lynn Township, Lehigh County
Dear Ms. White:
‘The Department is in receipt of a letter from Mr. Kermit E. DeLong, Chairman of the Lynn
Township Board of Supervisors, dated May 6, 2009. Enclosed with the May 6, 2009 letter was a
technical memorandum dated April 15, 2009 prepared by Gannett Fleming containing an evaluation of
treatment processes, The memorandum was prepared at the request of the Township to consider
alternate processes other than the Virginia Initiative Plant (VIP) process mentioned in the
Department’s January 26, 2009 Act 537 Plan approval letter. Gannett Fleming pro\
Department with additional clarifications via email on June 3, 2009. The Township
substituting an alternate process that will not trigger an official revision to the Township's Act 537
plan,
‘The Township's plan considers Pennvest for financing. The Department's role as Pennvest’s
technical advisors is to ensure that those projects recammended for financing have selected the most
cost effective alternative. The technical memorandum indicates that proposals have been requested
fiom two MLE packaged plant vendors, presumably based upon the representation in Table 6 that
those processes are the most cost effective alternates. The Department views costs estimated using a
present worth analysis within 15% of one another to be equivalent; meaning that no particular favor
needs to be given fo any one alternative if they are within 15% of each other. Therefore, after a final
review of your proposals, if the difference is greater than 15% of each other the Township would have
to choose the most cost effective alternate.
‘The technical memorandum also mentions that additional tankage will be required for the new,
treatment process. If the additional tankage requires additional disturbances beyond those areas that
‘were considered as part of the environmental review for the Act 537 plan revision, then an updated
environmental report generated from the Uniform Environmental Review process would need to be
submitted to the Department for our review prior to the Pennvest application cut off date.
RECEIVED]
JUN 19 2009 |
tt ern ay Qy— : jrovdepstatapae Pied on Reyes Paper OP)Lynn Township June 18, 2009
If the Township follows these guidelines, the project should be able to move forward under the
January 26, 2009 Act 537 Plan approval. Should you have any questions, please call James Ridgik,
P.E,, Environmental Engineer at 370-826-2335.
Sincerely,
fee?
Joseph J, Buezynski, P.E.
Environmental Engineer Manager
Planning Section
Water Management Program
cc: Mr. Kermit B. Delong, Chairman/Lynn Township Board of Supervisors
Mr. Kevin Deppe, Township Manager/Lynn Township
Mr. Roger A. Phillips, P.E., Senior Project Manager/Gannett Fleming, Ine.