Professional Documents
Culture Documents
1.2AUTHORITY OF TEST:-
Subject to the provisions of the contract, both parties shall have equal rights
in determining the test methods and procedures and in selecting all test
personnel. The test may be entrusted to experts who hold independent
positions with respect to both parties. If so, they and chief of test together
with contracting parties shall have final authority in selecting all other test
personnel.
1.3 PERSONNEL:-
1.5CHOICE OF PERSONNEL:-
The testing team shall have the necessary competence and experience for the
correct installation & utilization of the measuring equipment.
1.6PRESENCE AT TEST:-
All drawings of importance for the test and all relevant data, documents,
Specifications, certificates and reports on operating conditions shall be
placed at the disposal of the chief of test.
2.2INSPECTION ON SITE:-
Shortly before the start of the test, the unit and all test equipment shall be
subjected to thorough inspection by representatives of both parties and the
chief of the test to ensure that conditions are such that the performance of
the machine may be judged equitably. It shall be verified that:
A main bench mark for levels shall be established. All secondary bench
marks (Levelling reference points) in the specific hydraulic energy
measuring system shall be referred to it. All bench marks shall be
retained undisturbed until the final
report has been accepted.
When the indirect method of power measurement is used, the results of the
generator/motor efficiency test should preferably be available prior to the
hydraulic machine performance test. In case such information is missing the
guaranteed values of generator/motor for losses may be used for preliminary
computation of the results.
The test programme and procedure shall be prepared by the chief of test,
taking into consideration the plans previously prepared. All arrangements &
plans shall be submitted to both purchaser and supplier in ample time for
consideration and agreement. approval or objection shall be given in
writing.
The acceptance test shall not take place until the commissioning tests,
including speed and pressure variation trials, have been conducted.
It is for the purchaser to decide, with respect to plant operation and flow
conditions, on the date of the acceptance test. This shall be within the
contract guarantee period and preferably within six months after the
machine has been handed over to the purchaser, unless otherwise agreed by
both parties in writing.
The general programme shall be drafted by the chief of test and shall include
particulars concerning the following items:-
3.4 SPECIFIC HYDRAULIC ENERGY FOR ACCEPTANCE TEST:-
In those cases where guarantees are given for more than one specific
hydraulic energy the general programme shall state at which value or values
of specific hydraulic energy the acceptance test shall be carried out, on the
basis of the purchaser’s instructions.
If requested by either party or the chief of test, the unit and all test
equipment shall be available for inspection within two days after completion
of the test. A request for this inspection should be made as early as possible,
in any case, before the completion of testing.
The actual average head (speed) for each individual test run during the
whole acceptance test may deviate from its specified value by not more
than +3%(+1.5%) if the speed (head) is kept at its specified value.
The head may deviate by not more than +10% if the actual speed nn is
adjusted to Satisfy the relation:
nn √Hn
― = ―
nr √Hr
For reaction turbines, the tailwater level must not fall below the level which
corresponds to the maximum suction head stated in the contract. If the actual
head deviates from the guaranteed head, the cavitation conditions computed
for this head must not be worse than for the guaranteed head.
For impulse turbines, the highest tailwater level must not exceed the
maximum level stated in the contract.
6. TEST PROCEDURE:-
6.1 PERSONNEL:-
Unless otherwise provided in the contract, both parties to the contract shall
have equal rights in determining the test methods and procedures & in
selecting the test personnel. It is preferable, however, that the test be
entrusted to experts who hold an independent position toward both parties.
The purchaser and the supplier of the turbine shall be entitled to have
present members of their staff.
All drawings of importance for the test and all relevant data, documents,
specifications and certificates and reports on operating conditions, shall be
placed at the disposal of the chief of test.
Within two days before the start of the tests, the turbine shall be subjected
to inspection.
That the scales of guide vane or nozzle openings and blade angles
correspond with actual measurements taken.
That water passages are not obstructed or restricted by any foreign material.
That all pressure tappings, tubes and connections are clear of obstruction,
properly formed and located.
The procedure to be followed in the test shall be outlined by the chief of test
under consideration of plans. All arrangements and plans are to be submitted
to the purchaser and supplier in ample time for consideration and agreement.
Consent or objection is to be given in writing.
The acceptance test shall not place until after the turbine, following due test
running, has been handed over to the purchaser for commercial operation. It
is for the purchaser to decide, with respect to plant operation and flow
conditions, on the date of the acceptance test. This should be as soon as
possible after the turbine is handed over to the purchaser, but within the
specified guarantee period unless otherwise agreed by both parties in
writing. The general programme shall be drafted by the chief of test and
shall include particulars concerning the following items:-
This shall include a statement of the runs and the load points at which these
are to be made.
This shall state whether several or only one of a group of similar units are to
be tested with regard to efficiency.
The methods to be used for measurement of discharge, output and head shall
be stated.
8.6 KAPLAN TURBINE, WITH OR WITHOUT CAM:-
Tests for efficiency and output of Kaplan turbines shall be carried out, if
possible with cam control between guide vane opening and blade angle
disconnected, as this offers a means of checking the correct relationship
between these settings. A series of not less than five efficiency tests for
each fixed blade angle shall be run at different guide vane openings near
the presumed correct opening for the selected blade angle. A graph of
these tests reveals the best combination. These may, in order to save
time, be carried out as “index tests ” with only relative values of the
efficiency, if they are amended by suitable accepted methods, at the
determined correct guide vane opening. If the best blade angle
relationship has previously been determined by index test, the five test
points required herein above may be reduced to a minimum of three
points. By agreement, the tests may be run with the cam connected.
9. INSTRUMENTS:-
All momentary readings shall extend over the same interval of time at
each measuring point. The arithmetical mean of the momentary
readings will be used for the test computations.
Before carrying out a test, the openings of the needle nozzle or the
guide vanes and, in the case of Kaplan turbines, the positions of the
movable runner blades, for various positions of the operating
mechanisms, shall be accurately measured and suitable scales
provided. These scales must be accessible in operation and recorded of
each run. The test results can be referred to such recorded positions.
Before carrying out the test, the necessary correction and calibration
curves of all instruments employed shall be available, so that within a
short time following a test run, a sufficient number of representative
calculations can be made. All errors hereby determined shall be
eliminated where possible or taken into account. Only on this basis
may the tests be terminated and the test instruments removed.
This code covers the arrangements for acceptance tests at the plant to
determine the attainment of turbine guarantees. It determines the rules
as to their conduct & prescribes the measures to be taken if the
conduct of the tests is disputed. It deals with the way in which the
results are to be computed & the range,content & style.
In all cases the deviations must lie within the limits defined under a) &
b) below:-
10.1.1 GENERAL:
For non- regulated machines & for regulated machines with shut-off
devices which have long closing times, steady state runaway speed
will normally be exceeded during load rejection which is performed
during commissioning. Therefore a separate steady state runaway
test is not necessary.
11.3 PRESSURE VARIATIONS:-
The maximum momentary pressure on the high pressure side & the
minimum momentary pressure on the low pressure side of a turbine
normally occur during the shut-down operation when a specified
load is reduced to zero. The minimum momentary pressure on the
high pressure side & the maximum momentary pressure on the low
pressure side normally occur during the opening movement of the
shut-off valves beginning from zero or from no-load opening.
The basis of the limiting frequency for the filter is given by the
specific frequency characteristics of the hydraulic system.
The maximum permissible value of measurement total uncertainty
shall be +100 ×p-0,25% (Where p is in pascals).
0,9<E<1,1 Esp
c) The closing time is greater than 1,5 times the period of the pressure
waves in the penstock.
If before measurement,
The variations ΔPsp & Δnsp, which are to be expected under specified
conditions, can be calculated from the measured values of the pressure
variation Δp = pm – pi & speed variation Δn = nm – ni . as follows: