WEEK 4

A weekly assembly at BNS dockyard at 8 ooclock. A short lecture given by Dr. Syafizza on workers healthy and aging of workers heart.

A brief explanation given by En.Daud, AANS safety officer after the assembly about AANS safety and daily working condition.

Reorganizing, testing and recording work at 4 different locations this week which were at KDSK, location 21 and 22 in BNS, and AANS workshop (office). Figure shows the testing work for fan blower to separate the malfunction and good one. The fan blowers then were sent to the KDSK for storage. We also tested the arc welding machine to separate the broken one and good one.

WEEK 5

En. Ahmad Fuaad, our faculty supervisor came to our company for visiting us.

AANS workers were installing the box at electronic equipment room at KD Kelantan.

En. Nizam was discussing with the foreman, En. Rafi on the job at KD Kasturi.

A pressure test was done after the copper pipe installed in the bus terminal in electronic equipment room at the KD Kelantan.

Mr. Rokman was holding the end of socket to prevent the water from spilling out to the floor.

Housekeeping done by the workers after the job the job at KD Kelantan was done successfully