Requester /Dept.

: Ahmad Zulfian Tojib /NET OPTIM EAST NOC OPTIMIZATION Network Element: (HLR,MSC,IN,VoMS,IVR,VMS,SMS,BSC,BTS etc) BTS Element/Parameter to be changed: Cell Parameters: Change Parameter

(Refer to Need Change Parameter)

Please see other sheet attachments.

Present Measurement: Based on CDD Reason of Change: Improve quality Expected Result: Good Performance At These Cells

Implementation: NCCR No.

Comments & Evaluations: Status of Change after Evaluation:

NETWORK CONFIGURATION CHANGE REQUEST


NOP Division, Jl. Mega Kuningan Lot E4-7 No.1 Jakarta 12950, Ph.57959555,Fax.57959558

c)

Supporting Documents: (PleaseAttached) NCCR Order Others : Network Element ID. /Location No.: Jember/BJBR2 Present Value/Size:

Date & Time

Executor in Charged

Permanent

Fallback to Original value

GURATION

No 1

PIC Engineer A. Zulfian .T

UEST
Date: Thursday, October 24, 2013

ta 12950, Ph.57959555,Fax.57959558

Signature

Checked by : ..

Area LUMAJANG

CR Log Name/tile NCCR (EJ-REGULAR-2G) 20130913_NCCR2G_BJBR2_Power.xlsx

Propose NCCR

Parameter Name

Category Activity Networks BSC Involved Total Cell Implement Week Regular 2G BJBR2 1 cell 37

Reduce Power BSPWRT & BSPWRB

Date Released Date Execute 13/09/2013

BSC BJBR2 BJBR2

Cell

Parameter 17393 BSPWRT 17393 BSPWRB

Old 47 47

New 45 45