PRELIMINARIES Award of Contract Mobilization Preparation of Drawings and approval Material submittal and approval Procurement of long lead

item TYPICAL ONE UNIT VILLA CONSTRUCTION CYCLE SUB-STRUCTURE Lot Stake-out Excavation Plain Concrete below footing Formworks for Footing Fabrication and installation of rebars Pouring of Concrete on footing Formworks for stub column Pouring of Concrete on stub column Bitumin application, footing and stub column Backfilling up to bottom of grade beams Grade Beams; forms, reinforcement & pouring Bitumin application, side of beams Backfilling up to bottom of grade slabs Blinding concrete, 50mm thick Slab On Grade, reinforcement & pouring SUPER-STRUCTURE GROUND FLOOR Formworks for columns Fabrication/installation of rebars on columns Pouring of concrete - columns Formworks for beams, slabs and staircase Installation of rebars for beams, slabs and staircase Pouring of concrete - beams, slabs and staircase Curing of concrete - 1st phase Masonry Works - External (Insulated Blocks) Masonry Works - Internal Partitions Plumbing rough-in Electrical rough-in FIRST FLOOR LEVEL Formworks for columns Fabrication/installation of rebars on columns Pouring of concrete - columns Formworks for beams, slabs and staircase Installation of rebars for beams, slabs and staircase Pouring of concrete - beams, slabs and staircase Curing of concrete - 2nd phase Masonry Works - External (Insulated Blocks) Masonry Works - Internal Partitions Masonry Works - Parapet @ Elev. 5.65m Plumbing rough-in Electrical rough-in LOWER ROOF LEVEL Formworks for columns Fabrication/installation of rebars on columns Pouring of concrete - columns Formworks for beams and roof slabs Installation of rebars for beams and roof slabs

Pouring of concrete - beams and roof slabs Curing of concrete - 3rd phase Plumbing rough-in Electrical rough-in WATER PROOFING All Wet Areas Lower and Upper Roof FENCING WORKS Excavation Fence footing Grade Beam for fence Backfilling Column for fence Blockwork for fence Copping on top of masonry Plastering Works-Fence Installation of Gates FINISHES Plumbing Works - Ground, 1st and lower roof Electrical Conduitings Concrete Screed Installation of Doors and Windows Tiling works Metal Works and Handrails Plastering Works Plumbing Fixtures Electrical Fixtures Painting Works PER UNIT HAND OVER Site Clearing, broom finish Main Contractor Inspection Punchlists Correction/Rectification Hand-over PROJECT CLOSEOUT As Built Drawings Demobilzation

You might also like