Professional Documents
Culture Documents
1999AM RISK01 Slides PDF
1999AM RISK01 Slides PDF
Monte Carlo is a tool to determine which level of Project Definition you have achieved.
ESTIMATE CLASS
END USAGE
Typical purpose of estimate
METHODOLOGY
Typical estimating method
PREPARATION EFFORT
Typical degree of effort relative to least costs index of 1 (b)
Class 5
0% to 2%
Concept Screening
Capacity Factored, Parametric Models, Judgment, or Analogy Equipment Factored or Parametric Models Semi-Detailed Unit Costs with Assembly Level Line Items Detailed Unit Cost with Forced Detailed Take-off Detailed Unit Cost with Detailed TakeOff
Class 4
1% to 15%
Study or Feasibility
2 to 4
Class 3
10% to 40%
3 to 10
Class 2
30% to 70%
4 to 20
Class 1
50% to 100%
5 to 100
Notes: [a] The state of process technology and availability of applicable reference cost data affect the range markedly. The +/- value represents typical percentage variation of actual costs from the cost estimate after application of contingency (typically at a 50% level of confidence) for given scope. [b] If the range index value of "1" represents 0.005% of project costs, then an index value of 100 represents 0.5%. Estimate preparation efforts is highly dependent upon the size of the project and the quality of estimating data and tools.
Composition Prod. rates Final over time reservoi & produ ct r Specs. engr. in put
Cont inued Reservoir Engr.
Oper. Input freeze Opera tions inpu ts to P&ID's, equip ment layou ts, & maj . equip. purchase specs.
Construction
Commissioning
+100%
T rending
Trending from coneptual est imate & schedule t o reflect dec isions made during prelimi nary engineer ing (Screeni ng +30% or bet ter quality estimates.)
+15%
Current Estimate
-20% -40% -50% Low end of accura cy range -13%
+8% -8%
RBL 12/97
Histogra m
35 30 25 20 15 10 5 0 Bin
M inu te s
60 50 40 30 20 10 0 1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96
Fr e q u e n cy
70
Frequenc y 35 30
Fr e q u e n c 120% 100% 80% 60% 40% 20% 0%
Cu m ula tive
25 20 15 10 5 0 40 45 50 55 60 65 70 75 80 85 90 More
70
75
65
60
40
45
50
55
80
85
90
Bin
or
90 Mo re
40
45
50
55
60
65
70
75
80
85
'
Probability
!
!&
#
+/ 1.28= 80 %
0.025
0.020
Probability
0.015
0.010
0.005
Skewness
0.0350 0.0300
0.0250
0.0200
0.0150
0.0100
0.0050
70%
Cumulative Probability
60%
50%
40%
30%
20%
10%
0% 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0
More Definitions
Standard Deviation
Measure of average variance from mean. Measure of how widely dispersed the values are in the distribution.
Skewness
Asymmetric distribution. Usually right skewed for cost estimates. Usually left skewed for revenue estimates.
Simulation Statistics Date: 5/19/93 at 21:11 Iterations: 1500 Simulations: 1 Worksheet: HA_ONSHR.XL Output Range: Total Hainan Is Cell: $M$29 72,128
84,864 13,892 192,990,082 0.451398462 3.2461517
Tabular
Frequency Chart
10 Outliers
65
51,160 63,816
10Perc=
15Perc= 20Perc= 25Perc= 30Perc= 35Perc= 40Perc= 45Perc=
67,844
70,343 72,820 75,174 76,653 78,550 80,017 82,028
.024
48.75
.016
32.5
.008
16.25
50Perc=
55Perc= 60Perc= 65Perc= 70Perc= 75Perc= 80Perc= 85Perc=
84,084
85,901 87,579 89,324 91,381 93,759 95,977 99,174
90Perc=
95Perc= Maximum=
102,964
109,962 144,382
Contingency
General Definition: An Assessment, made by a team of professionals, of the amount of funds which, when added to the line item estimate will reflect an equal chance of underrun or overrun given relative stability of the scope and assumptions upon which the estimate is based. DOE, AACE, & PMI discuss uncertainty and statistical analysis in their definitions in addition to experience. DOE adds: Contingency is not to be used to avoid making an accurate assessment of expected costs. AACE adds: Usually excludes changes in scope or unforeseeable major events such as strike, earthquakes, etc. PMI adds: Contingency reserves are normally included in the projects cost and schedule baselines.
Contingency Analysis
Median - 50/50 point
Equal Chance of overrun / underrun Target
Contingency Amount
% -23.7% -8.3%
10Perc=
15Perc= 20Perc= 25Perc= 30Perc= 35Perc= 40Perc= 45Perc=
72,189
74,229 75,923 77,547 78,744 80,131 81,401 82,638
-2,963
-923 771 2,395 3,592 4,979 6,249 7,486
-3.9%
-1.2% 1.0% 3.2% 4.8% 6.6% 8.3% 10.0%
86.2%
-13.8%
50Perc=
55Perc= 60Perc= 65Perc= 70Perc= 75Perc= 80Perc= 85Perc=
83,726
85,142 86,723 88,111 89,664 91,139 93,247 95,528
8,574
9,990 11,571 12,959 14,512 15,987 18,095 20,376
11.4%
13.3% 15.4% 17.2% 19.3% 21.3% 24.1% 27.1%
100.0%
90Perc=
95Perc= Maximum=
98,433
102,352 121,119
23,281
27,200 45,967
31.0%
36.2% 61.2%
117.6%
17.6%
248.7
10.40% -7.50%
225.3 Contingency 6%
208.4
Sensitive Analysis
Which inputs are most significant How do you reduce the risk (Improve Accuracy Range) Quantification of Subjective Impressions
Sensitivity Graphics
Conclusions
Monte Carlo uses:
Establish contingency Establish overrun/underrun limits Determine if estimate accuracy meets expectations
Graphical presentation
Cumulative showing Probability of Overrun