• What is queueing ?
SERVICE:
• Drilling – to fill explosives in hole – takes
approx 10 minutes
• Packing - Controlled explosion
requirement- chemicals to be in fixed
ratio – takes approx 20 minutes
• Blasting – wiring done – electric method of
blasting
- takes approx 40 minutes
• Arrival of explosives – 1 hour 20
minutes
• Therefore we have λ= 60/90 = 0.67
explosives/hour
• Service rate is – 70 minutes
• Therefore we have µ=60/70=0.67
explosives/hour
Cindy Crawfard model……