You are on page 1of 4

Operator Schedule

WEEK 1
Amirudin Ajid Fahrun Rizki Andita

Monday 19/08/2013
Ironmaking Steelmaking Cont. Casting

Tuesday 20/08/2013
Cont. Casting Ironmaking Steelmaking

Wednesday 21/08/2013
Steelmaking Cont. Casting Ironmaking

WEEK 2
Amirudin Ajid Fahrun Rizki Andita

Monday 26/08/2013
Cont. Casting Ironmaking Steelmaking

Tuesday 27/08/2013
Steelmaking Cont. Casting Ironmaking

Wednesday 28/08/2013
Ironmaking Steelmaking Cont. Casting

WEEK 3
Amirudin Ajid Fahrun Rizki Andita

Monday 02/09/2013
Steelmaking Cont. Casting Ironmaking

Tuesday 03/09/2013
Ironmaking Steelmaking Cont. Casting

Wednesday 04/09/2013
Cont. Casting Ironmaking Steelmaking

WEEK 4
Amirudin Ajid Fahrun Rizki Andita

Monday 09/09/2013
Ironmaking Steelmaking Cont. Casting

Tuesday 10/09/2013
Cont. Casting Ironmaking Steelmaking

Wednesday 11/09/2013
Steelmaking Cont. Casting Ironmaking

WEEK 5
Amirudin Ajid Fahrun Rizki Andita

Monday 16/09/2013
Cont. Casting Ironmaking Steelmaking

Tuesday 17/09/2013
Steelmaking Cont. Casting Ironmaking

Wednesday 18/09/2013
Ironmaking Steelmaking Cont. Casting

WEEK 6
Amirudin

Monday 23/09/2013
Steelmaking

Tuesday 24/09/2013
Ironmaking

Wednesday 25/09/2013
Cont. Casting

Ajid Fahrun Rizki Andita


Ironmaking Cont. Casting Steelmaking Cont. Casting Steelmaking Ironmaking

For the month of: August - september Team Name: Refractory Department: Steemaking

Thursday 22/08/2013

Friday 23/08/2013
Ironnaking Steelmaking Cont. Casting

Thursday 29/08/2013

Friday 30/08/2013
Cont. Casting Ironmaking Steelmaking

Thursday 05/08/2013

Friday 06/09/2013
Steelmaking Cont. Casting Ironmaking

Thursday 12/09/2013

Friday 13/09/2013
Ironmaking Steelmaking Cont. Casting

Thursday 19/09/2013

Friday 20/09/2013
Cont. Casting Ironmaking Steelmaking

Thursday 26/08/2013

Friday 27/09/2013
Steelmaking

Cont. Casting Ironmaking