Football Stadium Charter

Group 6
Kelsey Blair, Pedro Garcia, Swati Arora, Haley Tran, Jason Didier

Table of Contents
Introduction....................................................................................................................................3
High Level Project Purpose or Justification..........................................................................................................3
Project Scope.........................................................................................................................................................3
Project Requirements.............................................................................................................................................3
Key Stakeholders...................................................................................................................................................3
Project Budget.......................................................................................................................................................4
Project Timeline....................................................................................................................................................4
Key Deliverables and High Level Milestones.......................................................................................................4

Project Name: Football Stadium Building


Project Sponsor: Plano Independent School District
Project Manager: Shawn Alborz

Project Charter Document

Introduction
High Level Project Purpose or Justification
The purpose of the project is to build an updated football stadium for Plano High School.

Project Scope
The scope of the project is to design a capable football stadium in an appropriate location and
oversee the construction.

Project Requirements
The stadium must be large enough to hold a maximum of 20,000 people in the stands. The
location must also be able to hold a parking area that is sufficient for a large crowd. Most
importantly the stadium needs to be up to safety and health code standards. Other features
include:
Use of concrete material
Standard sized field
Equipped with electricity and lights
Commentator box
Two VIP boxes, one on each side
Concession areas
Two men and women restrooms
Bleachers
Artificial turf

Key Stakeholders
The main stakeholders are the city of Plano community. Other stakeholders include:
Architects
Finance team
Manufacturers
Suppliers
Engineers
3

Electricians
Plumbing Company
Artificial turf

Project Budget
The budget of this project is set at $15 million.

Project Timeline
The project has one year to complete the stadium.
Project Activity
Design
Test
Re-design
Site Preparation
Build
Opening Preparation

Maximum Time needed


2 Weeks
3 Weeks
1 Week
2 Months
7 Months 2 Weeks
1 Month

Key Deliverables and High Level Milestones


The building plan must be completed by July 15th 2014.
The site prep must be completed by September 15th 2014.
The build must be completed by April 30th 2015.
The stadium will be ready to open on May 30th 2014.
4

Approvals
PISD:

Shawn Alborz: