Professional Documents
Culture Documents
Materials requirements planning (MRP) is the logic for determining the number of parts, components, and materials needed to produce a product. MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced. Dependent demand drives MRP. MRP is a software system.
First, the number of units of A are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of A in the 9th week to receive them in the 10th week.
9 50
10 50
LT = 1 day
Next, we need to start scheduling the components that make up A. In the case of component B we need 4 Bs for each A. Since we need 50 As, that means 200 Bs. And again, we back the schedule up for the necessary 2 days of lead time.
Day: A B R e q u ire d O rd e r P la c e m e n t R e q u ire d O rd e r P la c e m e n t 20 200 20 50 200 1 2 3 4 5 6 7 8 9 10 50
Spares
4x50=200
Finally, repeating the process for all components, we have the final materials requirements plan:
Day: A LT=1 B LT=2 C LT=1 D LT=3 E LT=4 F LT=1 Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement 1 2 3 4 5 6 7 8 9 50 200 100 55 55 20 200 200 200 400 300 20 200 400 100 300
10 50
20 20 200
A
Part D: Day 6
C(2) F(2)
40 + 15 spares
Based on a master production schedule, a material requirements planning system: Creates schedules identifying the specific parts and materials required to produce end items.
Determines the dates when orders for those materials should be released, based on lead times.
Inventory transactions
Component or Subassemblies BOM create an artificial parent to the BOM used for inexpensive items like washers or pins to group.
Coding
Item is coded at lowest level at which it occurs D (Level 2 or Level 3) This number identifies the part at the lowest level of usage.
Pegging
Identify each parent item that created demand. Parent= Items above the current level Child = Items below the current level
Planned orders to be released at a future time. Order release notices to execute the planned orders. Changes in due dates of open orders due to rescheduling. Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule. Inventory status data.
Gross Requirements: needed during each period. Scheduled Receipts: Existing orders that arrive at beginning of period. On-hand or available balance:
Net requirements: What is need to meet requirements and safety stock. Planned order receipt: arrives at beginning of period. Planned order release: Addresses lead time.
MRP Examples
No Feedback Realistic?
Feedback
Yes
Execute: Capacity Plans Material Plans
MRP Game