Activity List for MIS project implementation at Sefam Pvt.

Ltd

Activity A B C D E F G H I J K L M N

Description Vendor selection Requirement analysis Design Construction Data collection/conversion Testing Hardware acquisition Other software acquisition Software installation Hardware Installation Implementation Training Conduct parallel runs Fix bugs

Duration(in months) 2 3 4 3 2 1 1 1 0.5 0.5 6 3 3 1

Precesding activity A,B C D D F E,F H G I, J K K M