Beban mati
1. Lantai
= BJ . t . p
= 2,4 . 0,20 . 1= 0,48 t/m
2. Perkerasan
= BJ . t . p
= 2,2 . 0,05 . 1= 0,11 t/m
3. Air hujan
= BJ . t . p
= 1 . 0,05 . 1= 0,05 t/m +
Total berat pada lantai kendaraan
= 0,64 t/m
4. Trotoar
= BJ . t . p
= 2,4 . 0,45 . 1= 1,03 t/m
Beban Hidup
1. Beban orang = 0,5 . p
= 0,5 . 1
= 0,5 t/m
2. Beban tekanan roda=11 t +(30% x 11)
= 14,3 t/m
DEAD LOAD
LIVE LOAD
MOMENT DIAGRAM
PENULANGAN
DAERAH LAPANGAN fc=30 MPa , Fy=240 MPa
Didapat output SAP
Mu+ = 7,52 tm = 75,2 KNm
Dari Tabel diambil: Tebal Bondek 1mm
Slab depth (D)
A = 1650 mm2 / m
d = 94,4 mm
p = As/ b.d = 0,017
As = p.b.d = 0,017 . 1000 mm. 94,4 mm = 1604,8 mm2
Penentuan banyak tulangan
Dicoba dengan tulangan D 32
Astulangan = 1/4D2 = 1/4322 = 804,24 mm2
Jumlah tulangan =
= 1,99 2 tulangan
. b=
. 1000 = 501,14 mm
= 0,017
=
= 0,0035
1 = 0,85 *(
b =
)+ = 0,85 *(
)+ = 0,814
b =
b =
.
= 0,0376
d - = 200
= 18,58 mm
= 190,71 mm
Mn = As . Fy . ( d - )
Mn = 1417,65 . 390 . 190,71
Mn = 105440412,3 Nmm = 105,441 KNm
Mn = 0,8 . 105,441 = 84,35 KNm
Mu = 65,4 KNm < Mn = 84,35 KNm
Penampang kuat
Lantai tidak komposit dengan pelat bondek, pelat bondek hanya berfungsi sebagai
perancah
Tulangan susut / tulangan bagi
Asbagi = 0,002 . b . h
.b=
. 1000 = 226,18 mm
250 mm
= 81,625 KNm
= 1107,38 mm2
= 3,9 4 tulangan
. b=
= 0,0054
=
= 0,0036
1 = 0,85 *(
b =
)+ = 0,85 *(
)+ = 0,814
b =
b =
.
= 0,0376
d - = 210
= 14,87 mm
= 202,565 mm
Mn = As . Fy . ( d - )
Mn = 1134,12 . 390 . 202,565
Mn = 89595876,94 Nmm = 89,60 KNm
Mn = 0,8 . 89,60 = 71,68 KNm
Mu = 65,3 KNm < Mn = 71,68 KNm
Penampang kuat
Lantai tidak komposit dengan pelat bondek, pelat bondek hanya berfungsi sebagai
perancah
Tulangan susut / tulangan bagi
Asbagi = 0,002 . b . h
Asbagi = 0,002 . 1000 . 250
.b=
. 1000 = 226,18 mm
250 mm