Floor Plan

Work Break down Structure

S.no
A B C D E F G H J K L M N P Q R S T

Activity
Leveling, clearing of site, layout marking and Excavation Preparation of all door and window frames Foundation Work up to DPC including plinth and toe wall Laying of sewerage pipes and water supply pipes Brick work up to ground floor slab Construction of Staircase Shuttering, laying reinforcement, electrical works in slab and casting of slab for Ground floor including cantilever Fixing of door and window frames Chiseling work for electrical and plumbing work for Ground floor Internal plastering for ground floor excluding Toilet Tiles flooring for ground floor Laying of floor and wall tiles in Toilet Brick work for parapet, mumty Fixing of doors and windows Construction of mumty slab Fixing of toilet fixtures and other electrical fixtures Internal finishes and paints Exterior finishes and paints

Duration
6 8 6 2 4 10 5 4 2 3 2 3 3 3 2 2 5 5

Interdependency of Activities
o Activity A is the start of the project.
o o o o o o o o o o o o o o o

Activity B & C begin simultaneously and depend on A Activity D depends on C Activity E depends on D Activity E & F begin simultaneously Activity G depends on E & F Activity H depends on B & G Activity J depends on G Activity L, M & K depend on H & J Activity N depends on G Activity P depends on K, L & M Activity Q depends on N Activity R depends on P Activity S depends on R Activity T depends on Q Project finishes when activity S & T are finished.

Critical Path Network

Float Table
Activity Tail Event Head Event Dura tion Days TEt TLt TEh TLh Early Late Float Rks

St.

Fin.

St.

Fin.

Total

Free

Ind.