ABATON-MAIDLANG BRIDGE II

Brgy. Parang, Calapan, Oriental Mindoro

Erection Procedure of Modular Steel Bridge for SPAN 1


USING

CABLE SYSTEM

Tools for Installation


1.1 4 pcs. 130 Meters Wire Cable 6x19x1 1/4 dia. 1.2 2 pcs. 20 Meters Wire Cable 6x37x1 1/4 dia. 1.3 86 pcs. 1 1/4 dia. Cable Clamp 1.4 4 unit Cable Trolley 1.5 2 unit 15 ton Chain Block 1.6 2 unit 5 ton Chain Block 1.7 1.8 1.9 2 unit 2 ton Chain Block 4 pcs. Tightening Roller 6 pcs. Shackle 2" dia.

1.10 6 pcs. Shackle 1 1/4 dia. 1.11 4 pcs. Erection Pin 1.12 Minor Tools and Wrenches

Installation of Tower and Cable


1.1 30 pcs. W8x35x6000 1.2 20 pcs. L 65x65x6x6000 1.3 3 pcs. B/U beams 300x301x11x8x6000 1.4 4 pcs Concrete Block .8x.8x1.0 meter for Dead Man 1.5 24 pcs Concrete Block .4x.4x.5 meter for support of Anchor Span

Concrete Blocks (Counter Weight) 10mtrs Height Tower (W-shape)

4sets Wire Cable 6x7-1 72 Tons Capacity/set

9mtrs Height Tower (W-shape)

ABUT. A Concrete Blocks (Counter Weight)

Step 1: INSTALLATION OF 4 TOWERS INSTALLATION OF 4SETS WIRE CABLES - 2SETS FOR SUPPORT/MAIN TRUSS SEGMENT - 2SETS FOR OTHER SUPPORT MEMBERS (GIRDER, TOP CHORD, ETC.)

PIER 1

NOTE: STRUCTURAL DESIGN OF TOWER, CABLES AND LINK SET WILL BE CERTIFIED, SIGNED AND SEALED BY STRUCTURAL ENGINEER

2 sets Link Set (BH 300x301x11)

Step 2: INSTALLATION OF 2PCS-LINK SET

Cable Trolley & Chain Block

2nd Truss Segment

1st Truss Segment

Tag Wire

Step 3: INSTALLATION OF 1ST SEGMENT(LEFT TRUSS) INSTALLATION OF 1ST SEGMENT(RIGHT TRUSS) CONNECTION OF 1ST GIRDER TO 1ST SEGMENT
NOTE: ASSEMBLED SPAN 1 TRUSS WILL BE DISMANTLE SEGMENT BY SEGMENT AND TO
TRANSFER TO CABLE SYSTEM USING 25T CRAWLER CRANE BE

1 Cable with cable shackle

Step 4: INSTALLATION OF 2ND SEGMENT(LEFT TRUSS) INSTALLATION OF 2ND SEGMENT(RIGHT TRUSS) CONNECTION OF 2ND GIRDER TO 1ST SEGMENT

Step 5: INSTALLATION OF REMAINING SEGMENTS INSTALLATION OF REMAINING WIND BRACINGS CONNECTION OF REMAING GIRDERS SETTING OF TRUSS/BRIDGE COMPONENT TO BEARING PAD

Step 6: INSTALLATION OF STRINGERS INSTALLATION OF TRAPEZOIDAL SHEETS CONNECTION OF STUD BOLTS

PREPARED BY: ENGR. CONRADO C. CUCIO Project Manager JDLegaspi Const. Abaton- Maidlang Bridge II

Step 7: DISMANTLING OF TOWERS & CABLES INSTALLATION OF SIDE WALK FORMS INSTALLATION OF SLAB REINFORCEMENTS SLAB CONCRETING (USING POURING SEQUENCE)