Professional Documents
Culture Documents
Organization of Presentation
A. B. C. D.
Introduction to FIDIC Types of Dispute Boards Three Internationally-Accepted Options for Dispute Boards Dispute Boards Distinguished from Arbitration
A.
A.
A.
FIDIC stands for the Fdration Internationale des Ingnieurs-Conseils and is the French acronym for the international federation of national associations of independent consulting engineers. FIDIC was founded in Belgium in 1913. The objectives of forming the federation were (and I believe are today): to promote the professional interests of the member associations and to disseminate information of interest to members of its component national associations.
A.
In 1957 FIDIC published the first edition of its Conditions of Contract for Works of Civil Engineering Construction, which came to be known as the Red Book.
A.
In 1963, FIDIC published the first edition of its Conditions of Contract for Electrical and Mechanical Works suitable for use in contracts between an employer (owner) and contractor for the supply and erection of plant and machinery. As its covers were yellow, it came to be known as the Yellow Book.
A.
Engineer
cases
(2) Duty to act impartially between
Contractor
A.
1. 2. 3. 4. 5. 6. 7.
Suitable for all civil works projects where main responsibility for design lies with Employer (or his Engineer). Some design may, of course, be carried out by Contractor. Administration of Contract and supervision by Engineer. Approval of work, payment and claims certified by Engineer. Work done is measured, payment according to Bill of Quantities. Option for payment on lump sum basis. Balanced / fair risk-sharing.
WHITE & CASE LLP 8
A.
1.
2.
Suitable for all types of projects where main responsibility for design lies with Contractor.
Recommended for the provision of electrical and/or mechanical plant, and for the design and execution of building or engineering works. Some design may be carried out by Employer or his Engineer. Employer provides Employers Requirements to which Contractor designs. Administration of Contract and supervision by Engineer.
3. 4. 5.
A.
continued
6. Approval of work, payment and claims certified by Engineer. 7. Lump sum Contract Price with payment usually based on schedule of payments. 8. More extensive testing procedures than for New Red Book, including Tests after Completion. 9. Balanced / fair risk-sharing.
10
A.
Reasons for a New (1999) Contract for EPC Turnkey Projects (the Silver Book) 1. 2. Increased use of two-party approach, without Engineer. Increased sophistication, improved education and experience in developing countries hence reduced need for an intermediary like an Engineer.
3.
4.
Increase in privately-financed projects, like BOT, where customary for design and construction to be governed by an EPC Contract.
As a result of increase in privately-financed projects, increased emphasis on risk allocation.
5.
11
A.
1. 2.
Responsibility for design lies solely with Contractor. Employer provides Employers Requirements to which Contractor designs Employers Requirements usually performance specification-type. Contractor carries out all engineering, procurement, construction providing a fully-equipped facility, ready for operation at the turn of a key No Engineer instead it is the Employer who may appoint an Employers Representative.
3.
4.
12
A.
continued
5. 6. 7. 8.
Lump sum Contract Price with payment usually based on schedule of payments. Extensive testing Completion. procedures, including Tests after
Contractor takes majority of risks, Employer pays more to cover such risks. Final price and time of completion are intended to be more certain.
13
A.
1. 2.
General Conditions, comprising clauses that are believed will apply generally to most contracts (previously called Part I), Guidance for the Preparation of Particular Conditions, which will supplement or modify the General Conditions (they also include as annexes seven forms of security or guarantee) (previously called Part II), and Form of Letter of Tender, Contract Agreement and Dispute Adjudication Agreement (the Red and Yellow Books also contain an Appendix to Tender form to be attached to the Letter of Tender).
3.
14
A.
Sub-Clause 3.1 [Engineers Duties and Authority] and Sub-Clause 3.5 [Determinations] Of Red/Yellow Books
Except as otherwise stated in these Conditions:
(a)
whenever carrying out duties or exercising authority, specified in or implied by the Contract, the Engineer shall be deemed to act for the Employer; [Emphasis added] Whenever these Conditions provide that the Engineer shall proceed in accordance with this Sub-Clause 3.5 to agree or determine any matter, the Engineer shall consult with each Party in an endeavour to reach agreement. If agreement is not achieved, the Engineer shall make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances. [Emphasis added]
(b)
15
A.
Base Date
Delay attributable to the Contractor 28d 28d 11 Notifying of defects 9.1 Tests on2 Completion . . .
<21d
Remedying of defects
1. The Time for Completion is to be stated (in the Appendix to Tender) as a number of days, to which is added any extensions of time under Sub-Clause 8.4.
2. In order to indicate the sequence of events, the above diagram is based upon the example of the Contractor failing to comply with Sub-Clause 8.2.
3. The Defects Notification Period is to be stated (in the Appendix to Tender) as a number of days, to which is added any extensions under Sub-Clause 11.3.
16
B.
17
B.
The first DB was called a Dispute Review Board (DRB) and it made recommendations rather than decisions. Major developments regarding DRBs were as follows: 1975 1981 First Domestic DRB in U.S. (Eisenhower Tunnel). First international DRB (EL Cajon Dam, Honduras)
1995
1997
World Bank makes DRBs mandatory for all IBRD-financed projects over US$50m.
Asian Development Bank and EBRD adopt DRB approach.
18
B.
Subsequently, the Dispute Adjudication Board (DAB), which made decisions rather than recommendations, developed internationally, as follows:
1995
1998 1999 2000
19
B.
1.
A DRB issues Recommendations, a relatively consensual approach. If no party expresses dissatisfaction with a Recommendation within a stated time period, compliance is required.
If a party timely expresses dissatisfaction, that party may resort to arbitration, if so provided, or the courts. Pending a ruling by the arbitral tribunal or the court, the parties are not required to comply with the Recommendation.
20
B.
2.
3.
A DAB issues Decisions, a less consensual approach. The parties must comply with a Decision as soon as they receive it. If a party expresses dissatisfaction with a Decision within a stated time period, it may submit the dispute to final resolution by arbitration, or the courts, but the parties meanwhile remain contractually bound to comply with the Decision.
A CDB normally issues Recommendations but may issue a Decision if a party so requests and no other party objects.
21
C.
22
C.
FIDIC
I.
FIDIC Clause 20 (Claims, Disputes and Arbitration) provides for a combination of a Dispute Adjudication Board (20.4), amicable settlement (20.5), and ICC arbitration (20.6), in that order.*
See Conditions of Contract for Construction (1st ed. 1999) (CONS), Conditions of Contract for Plant and Design-Build (1st ed. 1999) (P&DB), and Conditions of Contract for EPC/Turnkey Projects (1st ed. 1999) (EPCT).
23
C.
1. Now recommended by World Bank.
FIDIC (contd)
2.
3.
Constitution: 1 or 3 members, usually engineers, independent of parties, but all accepted by parties.
Permanent (Red Book) or Ad Hoc (Silver and Yellow Books).* Permanent DAB: maintains familiarity with project, visits site periodically, decides disputes that arise by (provisional) binding decisions.
Ad Hoc DAB: constituted for and decides an individual dispute by a (provisional) binding decision.
4. Experience to date: successfully used on major projects in U.S. and internationally.
Conditions of Contract for Construction Works (for Building and Engineering Works Designed by the Employer) (1999) (Red book); Conditions of Contract for Plant and DesignBuild For Electrical and Mechanical Works and for Building and Engineering Works Designed by the Contractor) (1999) (Yellow Book); Contract for EPC Turnkey Projects (1999) (Silver Book).
24
C.
FIDIC (contd)
Amicable Settlement
< 28d
< 84d
< 28d
< 56d
Arbitrator(s) appointed
25
C.
FIDIC (contd)
The FIDIC Arbitration Clause provides for arbitration by 3 arbitrators according to the ICC Rules and (normally) in the language of the Contract.
Arbitrators may open up, review and revise any decisions of the DAB. Neither party is limited before the arbitrator(s) to the evidence or arguments previously put before the DAB.
26
C.
II. World Bank
World Bank
For projects financed by the World Bank, the World Banks Standard Bidding Documents for Procurement of Works (SBDW) are mandatory in major works contracts (estimated to cost more than $10 million, including contingency allowance) unless otherwise agreed. Clause 20 of the SBDW (May 2006) is based on a special edition version of FIDIC Clause 20. SBDW Clause 20 provides for a combination of a Dispute Board (20(4)), amicable settlement (20(5)), and ICC arbitration (20(6)).
27
C.
III.
a)
ICC
ICC
The ICC Dispute Board Documents, in force as from 1 September 2004, consist of:
b)
Standard ICC Dispute Board Clauses, which the parties can incorporate into their contracts and which provide for three types of Dispute Boards: a Dispute Review Board (DRB); a Dispute Adjudication Board (DAB); and a Combined Dispute Board (CDB);
ICC Dispute Board Rules, which govern the procedure before any Dispute Board (DRB, DAB or CDB); and ICC Model Dispute Board Member Agreement, which can be used as the model for the agreements to be entered into between each of the Dispute Board members and the parties.
ICC Dispute Boards can be established for any type of contract and are not limited to construction contracts.
28
C.
Experience of DRBs to date:
1.
Our Experience
Internationally, the immediately binding decision feature of the DAB procedure seems to make it more effective than the DRB procedure. But there is still a need for the DB procedures to gain the confidence of parties around the world.
2.
3.
The experience and expertise of the members of the DAB or DRB is often essential to its success.
29
C.
Internationally, DBs are still in their infancy and, inevitably, have given rise to some problems, including:
1.
Neglect of parties to put Permanent DAB/DRB in place at beginning of contract (lack of intimate knowledge of project, backlogs of disputes...)
2.
Difficulty or impossibility of enforcing internationally either binding or final and binding decisions of the DAB.
3.
30
C.
continued
4. Difficulty of finding qualified, experienced and independent members for DAB/DRB (and careful when limiting the class of candidates). 5. Difficulty to remove an unsatisfactory member of a Permanent DAB/DRB. 6. Because it is an expedited procedure, it may not be ideal for very large and/or very complex disputes. 7. Double-decker clauses having both Engineer and then DB decisions (or even vice versa) leading to delays.
31
D.
32
D.
Referral to a Dispute Board is similar to arbitration, but can be distinguished from arbitration in two principal ways:
While an arbitrator is chosen to exercise a judicial function and to resolve a dispute based upon submissions by the parties, a Dispute Board is chosen for its expertise in a certain subject matter and often does its own investigation or appreciation of the issue, with or without submissions by the parties. While arbitral awards can be judicially enforced, a Dispute Board determination, unless re-qualified as an arbitration, is in some jurisdictions not enforceable in court. The enforceability issue is governed by local law, and is unresolved in many jurisdictions.
33