Professional Documents
Culture Documents
Progress Community Presentations of Concept Design Ideas February 15, 2014. Team of Martinez & Johnson with Mecanoo Architects selected. Programming phase underway Meet the Architect event March 26, 2014
Lynch Development Partners
Architect
Martinez + Johnson
DCPL PM Firm
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058
Progress
Architect
Ten Arquitectos
New ground floor library will be part of mixed use development. Library designs have been approved.
Erik Lang Project Manager Developer Kim Fuller 202.442.6069 EastBanc Gareth Eckmann 202.737.1000
Project has received preliminary PUD approval from DC Zoning Commission on February 13, 2012. Litigation against project was dismissed.
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058
Progress
Architect
DC Department of General Services (DGS) is in lease negotiations on a potential storefront space. Librarys design-build team has completed the design for the interim space. Lease has been executed. Asbestos abetment work is complete. Construction is underway.
Art Lohsen Project Manager Contractor Chris Wright 202.727.4792 GCS/Sigal Taryn Morgan 202-944-6634
Contacts
Councilmember Ward 5 Kenyen McDuffie (202) 724-8028
Progress
Architect
Wiencek + Assoc
Mentor-Protg Construction Manager selected: Coakley-Williams and Blue Skye. GMP pricing proposal received & negotiated. Contract package approved by City Council. Initial construction work began January 13, 2014. Major demolition work is schedule to begin week of March 24th or April 1st.
Bing Thom Arch Project Manager Contractor Kim Fuller 202.442.6069 Coakley-Williams Terrance Caulfield 301.693.5000
Progress
Contacts
Councilmember Ward 7 YvetteAlexander 202.724.8068 Davis, Brody, Bond &Aedas Peter Cook 202.449.1190 Project Manager Contractor Kim Fuller 202.442.6069 Forrester Jon McGee 301.255.1750
Progress
Architect
New State of the Art Library located at 3935 Benning Road NE is open.
DCPL PM Firm
A-1 Consulting
Contacts
Councilmember Ward 8 Marion Barry 202.724.8045 Architect Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Coakley-Williams
Progress
DCPL PM Firm
Contacts
Councilmember Ward 3 Mary Cheh 202.724.8062 Architect
N/A
Progress
Project Manager
Ed Hampton 202.442.6067
Project complete
Eagle Construction
Contacts
Councilmember Ward 7 YvetteAlexander 202.724.8068 Architect EEK Sean ODonnell
Progress
Project is a partnership with the Department of Parks and Recreation to co-locate a 10,000 square foot library within a 54,000 square foot aquatic center and community center. Library and Community Center would share such space as computer lab, senior rooms, tutor rooms and community meeting rooms. Project location is 49th and Quarles St. NE
Contacts
Councilmember Various
Progress
Architect
T.B.D
Project Manager Capitol View, Cleveland Park, Shepherd Park, Lamond Riggs, Palisades, Southwest, West End and Woodridge The Library has received Federal Stimulus Money for energy enhancements. Projects will take place at the above locations, focusing on window replacements, energy efficient lighting, and automated building heating and cooling controls Contractor
DCPL PM Firm
Contacts
Councilmember Ward 7 YvetteAlexander 202.724.8068 Architect Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Hess Construction
Progress
Design of the new Francis Gregory Library will include community input on planning and programming phase. Project is fully funded.
DCPL PM Firm
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
Martinez & Johnson
Progress
Tom Johnson 202.333.4480 Project Manager Contractor Chris Wright 202.272.4913 N/A
Renovation complete and Library open to the public. DCPL PM Firm Smoot Construction
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
The Freelon Group
Progress
Derek Jones 919-941-9790 Project Manager Contractor Kim Fuller 202-442-6069 MCN Build Joseph Kourney 202.333.3424
Contacts
Councilmember Ward 1 Jim Graham 202.724.8181
Progress
Architect
Core Architects
Dale Stewart 202.466.6116 Project Manager Contractor Chris Wright 202.727.4913 T.B.D
Smoot Construction
Contacts
Councilmember Ward 6 Tommy Wells 202.724.8072
Progress
Architect
Bell Architects
David Bell 202.548.7570 Project Manager Chris Wright 202.727.4913 Contractor Monarc Construction C. McDermott, Project consists of Exterior Improvements to windows, doors, security lighting, masonry restoration, landscaping and signage. 703.201.1747
Contacts
Councilmember Ward 6 Tommy Wells 202.724.8072
Bell/Vines Architects
Progress
Architect
David Bell Victor Vines Project Manager Design-Builder This project is a major interior renovation of the 1930s era library. Renovations will create a 21st Century library while maintaining the historic integrity of the buildings interior. Chris Wright 202.727.4913 Whiting-Turner Andrew Easter
Contacts
Councilmember Ward 6 Tommy Wells
Progress
Architect
HordCort Plan
Reagan Assoc
Forrester
Project consists of 6,500 SQ FT Library facility as part of Elementary School and RecreationCenter. This facility replaces the Sursum Corda kiosk.
Contacts
Councilmember Ward 8 Marion Barry 202.724.8045
Progress
Architect
Mood Nolan - DC
Patrick Williams 202.244. 199 Project Manager Contractor Project to fit out approximately 5,000 Sq Ft of storefront space to replace the existing Parklands-Turner kiosk. The storefront library is similar in size, scope, computers, and collections to the Georgetown Interim and Tenley-Friendship Interim Libraries. Dedric Boyd 202.727.1129 Lexx Group Ken Postell 202.393.30
Contacts
Councilmember Councilmember Ward 4 Architect MurielBowser 202.724.8052
Frank and Loshen
Progress
Fletcher Farr Anoyte Project Manager Contractor Project updates the interior of the Petworth Library to be a fully functional state of the art 21st Century Library, while still being respectful of the buildings historic character.
DCPL PM Firm
Contacts
Councilmember Ward 6 Tommy Wells 202.724.8072 Architect Core Architects Dale Stewart 202.466.6116 Project Manager Contractor Kim Fuller 202.442.6069 Coakley/BlueSkye Bill Simons 240.200.4060 DCPL PM Firm NA
Progress
Contacts
Councilmember Ward 3 Mary Cheh 202.724.8062 Architect Freelon Group Philip Freelon 919.941.9790 Project Manager Contractor Dedric Boyd 202.727.1113 Forrester. Joe Ockershausen 301.255.1794 DCPL PM Firm Hill International
Progress
Design of the new Tenley Branch Library will include community input on planning and programming phase. Design and construction is fully funded.
Contacts
Councilmember Ward 5 Kenyen McDuffie (202) 724-8028
Progress
Architect
GDG
Mokhless Alhariri 202.857.0060 Project Manager Contractor Chris Wright 202.727.4913 Modular Genius Gregg Bichell 410.676.3424
Martin Luther King Jr. Library New Teen Spot and CollegeInformationCenter
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
Sorg Associates
Progress
SumanSorg
Project complete
Project Manager New Teen Spot and CollegeInformationCenter is a destination for teens.It provides stimulating learning opportunities that support their success in life. Contractor Kim Fuller 202.442.6070 Bennett Group Kolar Bowen 202. 625.3330