Professional Documents
Culture Documents
In CJ20n project 7102028 has an activity #014 under WBS element 71020287600 with duration 44 days
3. Another activity under WBS element 71020287600 is 7600 with duration 24 days
5. Dates in CJ2b for WBS element 710202876 PIPING LAYOUT are matching with those in CJ20n dates
6. Similarly, dates in CJ2b for the Activities under PIPING LAYOUT WBS element also match with those present in CJ20n
7. Now, in CJ2b I modify the duration of the activity #014 from 44 days to 50 days by dragging the bar in Gantt Chart
8. Scheduling is carried out for the activities under the WBS element PIPING LAYOUT by selecting all the WBS elements
10. Now, I open the project in CJ20n and check the duration for the activity #014. It has changed from 44 days to 51 days
12. Duration for the next activity remains same and only dates get changed (as expected)
13. Dates for the WBS element PIPING LAYOUT are also changed accordingly