PRODUCTIVITY - CONCRETE PUMP (Mar'13)

SL.NO. 1 ASSET CODE 1335-028-H Include hired assets also All placers in the cluster to be shown irrespective of idle, Surplus or Breakdown NORMS DESCRIPTION Concrete pump - 30 cum/hr Concrete pump - 60 cum/hr MAKE & MODEL Putzmeister & 1405-D

PROJECT L&T Godrej Palm Grove

CONCRETE PUMPED FOR THE MONTH (CUM)

NORMS (CUM) 2500

2181

Total

2181

e, Surplus or Breakdown Norms (Cum/Month) 2,500 2,500

CONCRETE PUMP PRODUCTION DETAIL


Utility (%) 87% TOTAL CONCRETE PUMPED FOR THE PROJECT (CUM) 8385 NO OF MONTHS DEPLOYED 8

8385

ON DETAIL
AVERAGE CONCRETE PUMPED PER MONTH (CUM) 1048 BALANCE CONCRETE TO BE PUMPED IN THIS PROJECT WITH PUMP (CUM) NO OF MONTHS THIS PUMP FURTHER REQUIRED IN THIS PROJECT 11

46000

FURTHER PUMPING PLANNED WITH THIS PUMP PER MONTH (CUM) 4200

Month

Job Code

Cluster

Mar'13

LE100580

CNCL