REPORT OF JALAN BINTULU SIBU

TABLE OF CONTENT
1. OVERVIEW OF JALAN BINTULU SIBU
i. ROAD MAP
ii. BINTULU DIVISION TERRITORY
iii. ROAD CENSUS
iv. ACCIDENT STATISTIC
2. BINTULU DIVISION ROAD INVENTORY
i. CURRENT ROAD CONDITION
ii. IMPROVEMENT WORK 2011
iii. IMPROVEMENT WORK 2012
iv. IMPROVEMENT WORK 2013
v. ARAHAN KERJA 2014
3. PHOTOS

REPORT OF JALAN BINTULU SIBU


OVERVIEW OF JALAN BINTULU SIBU - ROAD MAP

BINTULU TERRITORY
68 KM (SEC 651.1 -719.1)
ROUTE 1/57 -1/62

REPORT OF JALAN BINTULU SIBU


OVERVIEW OF JALAN BINTULU SIBU

Location

Sept
2013

Btu
/Sibu

2,190

Sibu
Bintulu

2,313

Total

4,503

Mac
2014

Year

2012

2013

2014

Maut

Parah

Ringan

Rosak

177

208

25

Jumlah

184

214

25

2,246

2,650

4,896

CENSUS DATA

ACCIDENT STATISTIC

REPORT OF JALAN BINTULU SIBU


BINTULU DIVISION ROAD INVENTORY

Total Condition 4 : 2.7 km


Total Condition 3 : 8.1 km
Total Condition 4 approved: 9.0 km
* Priority list submitted to KKR by HCM

REPORT OF JALAN BINTULU SIBU


BINTULU DIVISION ROAD INVENTORY IMPROVEMENT WORK

YEAR

KM

RM

REMARKS

2011

7.93

CIPR

2012

10.44

23,620,094

CIPR

2013

5.42

5,940,000.00

CIPR

12,460,000.00

CIPR
(AK 01 -03)

2014

9.00

REPORT OF JALAN BINTULU SIBU


PHOTO CURRENT ROAD CONDITION (SEC 683 686)

REPORT OF JALAN BINTULU SIBU


PHOTO CURRENT ROAD CONDITION (SEC 698.2 698.9)

REPORT OF JALAN BINTULU SIBU


PHOTO CURRENT ROAD CONDITION (SEC 660.0 668.0)

REPORT OF JALAN BINTULU SIBU


PHOTO COMPLETED CIPR WORK

BEFORE

AFTER

REPORT OF JALAN BINTULU SIBU


PHOTO COMPLETED CIPR WORK

BEFORE

AFTER

REPORT OF JALAN BINTULU SIBU


PHOTO ROUTINE MAINTENANCE

BEFORE

AFTER

REPORT OF JALAN BINTULU SIBU


PHOTO ROUTINE MAINTENANCE

BEFORE

AFTER

REPORT OF JALAN BINTULU SIBU


BINTULU DIVISION ROAD INVENTORY IMPROVEMENT WORK AK 2011
ROUTE
NO

START

END

LENGTH
(KM)

1/57

668.08

668.45

0.36

1/58

668.45

673.3

4.85

1/60

700.9

702.4

1.50

1/60

702.4

703.62

1.22

RM

REMARKS

REPORT OF JALAN BINTULU SIBU


BINTULU DIVISION ROAD INVENTORY IMPROVEMENT WORK AK 2012
ROUTE
NO

START

END

LENGTH
(KM)

RM

REMARKS

1/58

673.30

674.00

0.70

990,000.00

AK(2A)/2012/25

1/58

664.00

675.14

1.14

1,605,308.00

AK(2A)/2012/18

1/58

679.00

679.83

0.83

1,150,000.00

AK(2A)/2012/26

1/58

682.30

683.00

0.70

990,000.00

AK(2A)/2012/27

1/58

686.00

687.07

1.07

1,505,698.00

AK(2A)/2012/19

1/59

687.00

688.90

1.90

2,640,000.00

AK(2A)/2012/28

1/59

691.80
695.80

692.90
696.80

2.10

3,000,000.00

AK(2A)/2012/29

1/60

698.90

700.90

2.00

2,829,088.00

AK(2A)/2012/20

10.44

23,620,094.00

TOTAL

REPORT OF JALAN BINTULU SIBU


BINTULU DIVISION ROAD INVENTORY IMPROVEMENT WORK AK 2013

ROUTE
NO

START

END

LENGTH
(KM)

RM

REMARKS

1/59

688.90
690.11

689.62
691.62

2.23

4,000,000.00

AK(2A)/2013/17

1/59

695.37
696.80

695.80
698.22

1.85

5,240,000.00

AK(2A)/2013/18

1/60

703.50

704.84

1.34

2,000,000.00

AK(2A)/2013/19

5.42

5,940,000.00

TOTAL

REPORT OF JALAN BINTULU SIBU


BINTULU DIVISION ROAD INVENTORY IMPROVEMENT WORK AK 2014

ROUTE
NO

START

END

LENGTH
(KM)

RM

REMARKS

1/59

651.10

654.00

2.90

4,060,000.00

AK(2A)/2014/01

1/59

654.00

657.00

3.00

4,200,000.00

AK(2A)/2014/02

1/60

657.00

660.00

3.00

4,200,000.00

AK(2A)/2014/03

8.90

12,460,000.00

TOTAL