EXAMPLE OF TASK SCHEDULE

TASK 1. Pretest MSS team BSC team Commercial team ITOC team 2. Firewall connection to OT IT 3. Inter-firewall connection 4. Connectivity test with OT IT 5.Inter-firewall connection test 6.Firewalls operational test Synchronization of configuration Status (Active and standby) 7.Firewall redundancy test Secondary standalone Primary standalone Primary and Secondary 8.Posttest / Rollback and Posttest DURATION 2300 to 0000

0000 to 0030

0030 to 0045 0045 to 0100

0100 to 0115 0115 to 0130

0130 t0 0200

0200 to 0300