LAPORAN

TESTING & COMMISSIONING



PERIODE 15 DESEMBER 2011 16 JANUARI 2012
TANGCITY MALL - TANGERANG

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


ii | P a g e



DAFTAR ISI

I. RINGKASAN UTAMA ............................................................................................................ 1
II. PROGRES PEKERJAAN .................................................................................................. 4
A. ELEKTRIKAL ....................................................................................................................... 4
A.1. STATUS PEKERJAAN ELEKTRIKAL......................................................................... 4
A.2. PROGRES TESCOM ELEKTRIKAL ............................................................................ 5
A.3. PROGRES RATIFIKASI DEFECT ELEKTRIKAL ...................................................... 6
A.3.1. DEFECT TESCOM SYSTEM GROUNDING (25 OKTOBER 2011) ................ 7
A.3.2. DEFECT CHECKLIST PENYALUR PETIR (25 OKTOBER 2011) ................ 10
A.3.3. DEFECT TESCOM GENSET (21 NOPEMBER 2012) ..................................... 11
A.3.4. DEFECT TESCOM PANEL KONTROL GENSET (21 NOPEMBER 2012) . 16
A.3.5. DEFECT TESCOM TRANSFORMATOR (18 OKTOBER 2011) ................... 19
A.3.6. DEFECT TESCOM PANEL (2 NOPEMBER 2011) .......................................... 20
A.3.7. DEFECT TESCOM PANEL (3 NOPEMBER 2011) .......................................... 23
A.3.8. DEFECT TESCOM PANEL (4 NOPEMBER 2011) .......................................... 24
A.3.9. DEFECT TESCOM PANEL (7 NOPEMBER 2011) - 1 .................................... 27
A.3.10. DEFECT TESCOM PANEL (7 NOPEMBER 2011) 2 ............................... 29
A.3.11. DEFECT TESCOM PANEL (10 NOPEMBER 2011) -1 ............................... 30
A.3.12. DEFECT TESCOM PANEL (10 NOPEMBER 2011) -2 ............................... 33
A.3.13. DEFECT TESCOM PANEL (11 NOPEMBER 2011).................................... 35
A.3.14. DEFECT TESCOM PANEL (14 NOPEMBER 2011).................................... 38
A.3.15. DEFECT TESCOM PANEL (5 NOPEMBER 2011) ...................................... 40
A.3.16. DEFECT TESCOM PANEL (17 NOPEMBER 2011).................................... 42
A.3.17. DEFECT TESCOM PANEL (28 NOPEMBER 2011).................................... 44
A.3.18. DEFECT TESCOM PANEL (30 NOPEMBER 2011).................................... 47
A.3.19. DEFECT TESCOM PANEL (1 DESEMBER 2011) ..................................... 51
A.3.20. DEFECT TESCOM PANEL (2 DESEMBER 2011) ...................................... 52
A.3.21. DEFECT TESCOM PANEL (5 DESEMBER 2011) ...................................... 54
A.3.22. DEFECT TESCOM PANEL (6 DESEMBER 2011) ...................................... 56

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


iii | P a g e


A.3.23. DEFECT TESCOM PANEL (9 DESEMBER 2011) ...................................... 59
A.3.24. DEFECT TESCOM PANEL (12 DESEMBER 2011) .................................... 63
A.3.25. DEFECT TESCOM PANEL (13 DESEMBER 2011) .................................... 64
A.3.26. DEFECT TESCOM PANEL (15 DESEMBER 2011) .................................... 66
A.3.27. DEFECT TESCOM PANEL (19 DESEMBER 2011) .................................... 67
A.3.28. DEFECT TESCOM PANEL (20 DESEMBER 2011) .................................... 69
A.3.29. DEFECT TESCOM PANEL (21 DESEMBER 2011) .................................... 71
A.3.30. DEFECT TESCOM PANEL (21 DESEMBER 2011) .................................... 72
A.3.31. DEFECT TESCOM PANEL (22 DESEMBER 2011) .................................... 74
A.3.32. DEFECT TESCOM PANEL (23 DESEMBER 2011) .................................... 75
A.3.33. DEFECT TESCOM PANEL (27 DESEMBER 2011) .................................... 77
B. ELEKTRONIK ..................................................................................................................... 78
B.1. STATUS PEKERJAAN ELEKTRONIK ...................................................................... 78
B.2. PROGRES TESCOM ELEKTRONIK ......................................................................... 79
B.3. PROGRES RATIFIKASI DEFECT ELEKTRONIK ................................................... 80
B.3.1. DEFECT CHECKLIST PANEL BAS (8 NOPEMBER 2011) .......................... 81
B.3.2. DEFECT CHECKLIST CCTV (9 NOPEMBER 2011) ....................................... 89
B.3.3. DEFECT CHECKLIST FIRE ALARM (2 NOPEMBER 2011) ......................... 92
B.3.4. DEFECT CHECKLIST SOUND SYSTEM (2 NOPEMBER 2011) ................ 101
B.3.5. DEFECT TESCOM SOUND SYSTEM (25 NOPEMBER 2011) ................... 108
B.3.6. DEFECT TESCOM BAS (16 DESEMBER 2011) ........................................... 111
C. MVAC ................................................................................................................................. 112
C.1. STATUS PEKERJAAN MVAC .................................................................................. 112
C.2. PROGRES TESCOM MVAC ...................................................................................... 113
C.3. PROGRES RATIFIKASI MVAC ................................................................................ 114
C.3.1. DEFECT TESCOM FAN ..................................................................................... 115
C.3.2. DEFECT CHECKLIST FAN (22 DESEMBER 2011) ..................................... 127
C.3.3. DEFECT CHECKLIST AHU & FCU B2 & B1 .............................................. 128
C.3.4. DEFECT CHECKLIST AHU LG ..................................................................... 135
C.3.5. DEFECT CHECKLIST AHU GF ..................................................................... 141
C.3.6. DEFECT CHECKLIST AHU (22 & 23 DESEMBER 2011) ............................ 145
C.3.7. DEFECT CHECKLIST & TEST POMPA CHWP (16 DESEMBER 2011)... 151

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


iv | P a g e


C.3.8. DEFECT CHECKLIST DAN TEST POMPA CWP (15 DESEMBER 2011) 155
C.3.9. DEFECT CHECKLIST COOLING TOWER (15 DESEMBER 2011) ........... 160
C.3.10. DEFECT CHECKLIST CHILLER (16 DESEMBER 2011) ........................ 162
D. PLUMBING ....................................................................................................................... 165
D.1. STATUS PEKERJAAN PLUMBING......................................................................... 165
D.2. PROGRES TESCOM PLUMBING ............................................................................ 166
D.3. PROGRES RATIFIKASI PLUMBING ....................................................................... 167
D.3.1. DEFECT CHECKLIST INSTALASI GAS (8 NOPEMBER 2011) ................. 168
D.3.2. DEFECT CHECKLIST STP ................................................................................ 171
D.3.3. DEFECT CHECKLIST STP ................................................................................ 172
D.3.4. DEFECT CHECKLIST GROUND TANK .......................................................... 172
D.3.5. DEFECT RUANG POMPA ................................................................................. 172
D.3.6. DEFECT POMPA TRANSFER .......................................................................... 173
D.3.7. DEFECT WATER HAMMER .............................................................................. 173
D.3.8. DEFECT ROOF TANK ........................................................................................ 174
D.3.9. DEFECT POMPA BOOSTER ............................................................................ 174
D.3.10. DEFECT TOILET ............................................................................................. 175
D.3.11. DEFECT SUMPIT ............................................................................................ 175
E. FIRE FIGHTING ................................................................................................................... 176
E.1. STATUS PEKERJAAN FIRE FIGHTING ................................................................. 176
E.2. PROGRES TESCOM FIRE FIGHTING .................................................................... 176
E.3. PROGRES RATIFIKASI FIRE FIGHTING ............................................................... 177
D.3.1. DEFECT CHECKLIST FIRE FIGHTING .............................................................. 178
F. TRANSPORTASI GEDUNG .............................................................................................. 179
F.1. STATUS PEKERJAAN TRANSPORTASI GEDUNG ............................................ 179
F.2. PROGRES TESCOM TRANSPORTASI GEDUNG ............................................... 180
F.3. PROGRES RATIFIKASI TRANSPORTASI GEDUNG .......................................... 181
F.3.1. DEFECT TESCOM ESCALATOR & TRAVELATOR .................................... 182
F.3.2. DEFECT CHECKLIST ELEVATOR .................................................................. 185
F.4. LIST BERITA ACARA TRANSPORTASI GEDUNG ............................................. 187



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


v | P a g e


PENDAHULUAN
Laporan ini dibuat untuk PT. Pancakarya Griyatama selaku Konstruksi Managemen
dan juga selaku pemilik dari bangunan Tangerang City Mall, yaitu sebagai
monitoring mengenai pekerjaan Testing & Commissioning.
Laporan yang kami kirimkan saat ini adalah kegiatan Testing & Commissioning
periode 15 Desember 2011 s/d 16 Januari 2012. Isi laporan meliputi Progress
Tescomm, List defect dan progress penyelesaian defect oleh kontraktor.
Kami harapkan dengan adanya laporan ini dapat menjadikan sebagai indicator
dalam mengambil langkah selanjudnya guna suksesnya Testing & Commissioning di
Tangcity Mall.

Hormat kami


Richie Jo
Associate Director






MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


1 | P a g e


I. RINGKASAN UTAMA
A. STATUS UMUM PEKERJAAN
Sesuai dengan kesanggupan pihak PT. Pembanguanan
Perumahan bahwa ratifikasi akan selesai pada tgl. 15 Januari
2012, sehingga untuk bulan ini ter-fokus kepada
ratifikasi/penyelesaian defect.
Peralatan Fire Fighting belum dapat dilakukan pengetesan,
dikarenakan setingan PRV belum fix.
Pengetesan Pompa Sumpit & Pengecekan ground tank.
Penerbitan B.A Tescom Escalator (46 unit), Travelator (8 unit), Lift
(8 unit), STP dan Trafo (5 unit).
Mempersiapkan BAST-1 untuk peralatan Eskalator & Travelator.
B. PROGRES TESCOM


C. PROGRES RATIFIKASI DEFECT












SISTEM
CHECKLIST
(%)
TESTCOM
(%)
KETERANGAN
Elektrikal 100% 100%
Elektronik 100% 31.5%
MVAC 88.9% 73.5%
Plumbing 100% 100%
Fire Fighting 100% 0%
Trans. Gedung 95.5% 75%
SISTEM DEFECT RATIFIKASI
SISA
DEFECT
RATIFIKASI
(%)
Elektrikal 762 685 77 89.9%
Elektronik 402 212 190 52.7%
MVAC 545 306 239 56.1%
Plumbing 45 14 31 31%
Fire Fighting 6 4 3 66.7%
Trans. Gedung 88 73 15 83%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


2 | P a g e


No UNIT JML
CHECKLIST TESKOM
KETERANGAN
SUDAH BELUM (%) SUDAH BELUM (%)
1
ELEKTRIKAL
GENSET 5 5 0 100% 5 0 100%
PKG 10 10 0 100% 10 0 100%
TRAFO 5 5 0 100% 5 0 100%
PANEL-PANEL 182 182 0 100% 182 0 100%
GROUNDING 18 18 0 100% 18 0 100% Proses B.A Tescomm
PENYALUR PETIR 1 1 0 100% 1 0 100% Proses B.A Tescomm
100% 100%
2
ELEKTRONIK
BAS (PANEL) 27 27 0 100% 17 10 63%
- POIN LIST 2177 2177 0 100% 280 1897 13%
SOUND SYSTEM (PANEL) 27 27 0 100% 27 0 100%
- CEILING SPEAKER 706 706 0 100% 700 6 99% 153 buah tidak hidup
- HORN SPEAKER 112 112 0 100% 0 112 0%
- WALL SPEAKER 25 25 0 100% 0 25 0%
- CAR CALL 4 4 0 100% 0 4 0%
MCFA 2108 2108 0 100% 813 1295 39%
FIRE ALARM (PANEL) 15 15 0 100% 2 13 13%
- SMOKE DETECTOR 943 943 0 100% 287 656 30%
- ROR 1115 1115 0 100% 526 589 47%
- SMOKE DUCT 48 48 0 100% 0 48 0%
- BEAM DETECTOR 2 2 0 100% 0 2 0%
- ANOUNCIATOR 1 1 0 100% 1 0 100%
CCTV (PANEL) 10 10 0 100% 0 10 0%
- CAMERA 216 216 0 100% 0 216 0%
100% 31.5%
3
MVAC
CHILLER 4 4 0 100% 0 4 0%
AHU 61 61 0 100% 49 12 80%
FCU 9 9 0 100% 9 0 100%
FAN 106 106 0 100% 90 16 85%
COOLING TOWER 4 4 0 100% 4 0 100%
POMPA TRANSFER 2 2 0 100% 2 0 100%
MAKE UP WATER 2 0 2 0% 0 2 0%
POMPA CHWP 5 5 0 100% 5 0 100%
POMPA CWP 5 5 0 100% 5 0 100%
88.9% 73.9%
4
PLUMBING
GAS 1 1 0 100% 1 0 100%
SEWAGE 4 4 0 100% 4 0 100%
SUMPIT 17 17 0 100% 17 0 100%
DEEPWELL 4 4 0 100% 4 0 100%
STP 1 1 0 100% 1 0 100%
TOILET 14 14 0 100% 14 0 100%
100% 100%
5
FIRE FIGHTING
Belum bisa di test, setingan
PRV belum fix
POMPA FIRE 3 3 0 100% 0 3 0%
IHB 75 75 0 100% 0 75 0%
OHB 4 4 0 100% 0 4 0%
SEAMESE 2 2 0 100% 0 2 0%
Pillar Hydrant 4 4 0 100% 0 4 0%
BCV 28 28 0 100% 0 28 0%
100% 0%
6
TRANS. GEDUNG
ESCALATOR 46 46 0 100% 46 0 100% Proses BAST-1
TRAVELATOR 8 8 0 100% 8 0 100% Proses BAST-1
ELEVATOR (LIFT) 10 10 0 100% 10 0 100% Proses B.A Tescomm
GONDOLA 3 0 3 0% 0 3 0%
75.0% 75%
GRAND TOTAL 8179 8174 5 95.5% 3143 5036 63.4%






MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


3 | P a g e


No Sistem
Jumlah
Defect
Ratifikasi Sisa
Ratifikasi
(%)
KETERANGAN
1 ELECTRICAL 762 685 77 89.9%
Panel 620 572 48 92.3%
Trafo 10 10 0 100% Closed
Grounding 40 36 4 90%
Penangkal Petir 2 2 0 100% Closed
PKG 36 34 2 94.4%
Genset 54 31 23 57.4%
2 ELECTRONIC 402 212 190 52.7%
SOUND SYSTEM 139 61 78 43.9%
FIRE ALARM 140 76 64 54.3%
CCTV 30 0 30 0%
BAS 93 75 18 80.6%
3 MVAC 545 306 239 56.1%
FAN 175 91 84 55.8%
AHU 236 138 98 58%
FCU 31 22 9 71%
CHILLER 21 0 21 0%
CHWP 28 21 7 75%
COOLING TOWER 20 5 15 25%
CWP 34 29 5 85%
4
PLUMBING
45 14 31 31.1%
STP 7 5 2 71.4%
DEEPWELL 3 2 1 66.7%
GROUND TANK 4 4 0 100.0%
R. POMPA 2 0 2 0%
POMPA TRANSFER 6 5 1 83.3%
WATER HAMER 1 1 0 100% Closed
ROOF TANK 9 7 2 77.8%
R. BOOSTER PUMP 3 2 1 67%
POMPA BOOSTER 2 0 2 0%
TOILET 1 0 1 0%
SUMPIT 7 5 2 71.4%
5 FIRE FIGHTING 6 4 2 66.7%



6 TRANS. DALAM GEDUNG 88 73 15 83.0%
ESCALATOR 33 33 0 100% Closed
TRAVELATOR 10 10 0 100% Closed
ELEVATOR 45 30 15 66.7%
GONDOLA 0 0 0 - Peralatan belum siap
TOTAL DEFECT 1848 1294 554 63.3%



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


4 | P a g e


II. PROGRES PEKERJAAN
A. ELEKTRIKAL
A.1. STATUS PEKERJAAN ELEKTRIKAL
Peralatan elektrikal yang sudah dilakukan testing adalah Genset
berikut PKG, Panel-panel, Grounding dan penyalur petir.
Status defect untuk peralatan Trafo, grounding dan penyalur petir
sudah closed.
Peralatan Trafo sudah diterbitkan Berita Acara Testing
Commissioning.
Peralatan grounding dan penyalur petir dalam proses pembuatan
Berita Acara Testing Commissioning, terdapat kekurangan
dokumen yaitu As build drawing belum ada.
Melakukan pengecekan terhadap lampu-lampu yang terpasang
di area mall dan sekitarnya.
Melakukan pengecekan ratifikasi defect bersama antara NAI,
PAKAR, PP dan Pengelola.
Permasalahan panel kontrol yang pintu akses sulit dibuka
dengan leluasa, dan akan dilakukan pengecekan bersama untuk
mengetahui sejauh mana kesulitan akses untuk dapat melakukan
maintenance panel.




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


5 | P a g e


A.2. PROGRES TESCOM ELEKTRIKAL









0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
GENSET PKG TRAFO PANEL-
PANEL
GROUND
ING
PENYALU
R PETIR
Checklist 100% 100% 100% 100% 100% 100%
Test 100% 100% 100% 100% 100% 100%
A
x
i
s

T
i
t
l
e

PROGRESS TESCOM ELEKTRIKAL
SISTEM
CHECKLIST
(%)
TESTCOM
(%)
KETERANGAN
Genset 100% 100%
PKG 100% 100%
Trafo 100% 100% Sudah BA Tescom
Panel 100% 100%
Grounding 100% 100% Sudah BA Tescom
Penyalur Petir 100% 100% Sudah BA Tescom

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


6 | P a g e


A.3. PROGRES RATIFIKASI DEFECT ELEKTRIKAL









0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
GENSET PKG TRAFO PANEL-
PANEL
GROUND
ING
PENYALU
R PETIR
Ratifikasi 57.4% 94.4% 100% 84.2% 90% 100%
57.4%
94.4%
100%
84.2%
90%
100%
A
x
i
s

T
i
t
l
e

PROGRESS RATIFIKASI DEFECT ELEKTRIKAL
SISTEM
JML.
DEFECT
RATIFIKASI SISA %
Genset 54 31 23 57.4%
PKG 36 34 2 94.4%
Trafo 10 10 0 100%
Panel 620 572 48 92.3%
Grounding 40 36 4 90%
Penyalur Petir 2 2 0 100%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


7 | P a g e


A.3.1. DEFECT TESCOM SYSTEM GROUNDING (25 OKTOBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. GTB 9 PUTR.MALL 4 & 3 Bak control tertutup aspal 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


2. GTB BODY TRAFO 1,3 & 4 Peraphian bak control 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


3. GTB 11 BODY PUTR MALL
1 & 2
Label belum tersedia 10 Jan 12
Selesai Belum


4. GTB 12 START POINT TR
NO 1
Rapikan bak control 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


5. GTB 13 START POINT TR
NO 3
Label belum tersedia 10 Jan 12
Selesai Belum


6. GTB 14 START POINT
GENSET NO 2
Rapikan bak control 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum

7. GTB 14 A. START POINT
GENSET NO 5
Label belum tersedia 10 Jan 12
Selesai Belum


8. GTB 15 START POINT
GENSET TRAFO NO 4
Label belum tersedia 10 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


8 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
9. GTB 16 START POINT
GENSET NO 4
Label belum tersedia 10 Jan 12
Selesai Belum


10. GTB 8 BODY PANEL TM Bak control tertutup aspal 10 Jan 12
Selesai Belum

Label belum ada 10 Jan 12
Selesai Belum


11. GTB 17 CHILLER Bak control belum tersedia 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


12. GTB 18 CHILLER P. PETIR Bak control belum tersedia 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


13. GTB 1 BODY GENSET
1,2,3,4,5 & PKG
Bak control belum tersedia 10 Jan 12
Selesai Belum

Wiring diagram belum ada 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


14. GTB 2 START POINT
GENSET NO 3
Wiring diagram belum ada 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


15. START POINT GENSET NO 3 Perapihan pintu bak kontrol 10 Jan 12
Selesai Belum

Wiring diagram belum ada 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


9 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
16. GTB 4 START POINT
TRAFO CR
Bak control belum tersedia 10 Jan 12
Selesai Belum

Wiring diagram belum ada 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


17. GTB 5 BODY TRAFO CR Wiring diagram belum ada 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


18. GTB 6 START POINT
GENSET NO 1
Wiring diagram belum ada 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


19. GTB 7 BODY TR 2 & BODY
TRAFO CR
Wiring diagram belum ada 10 Jan 12
Selesai Belum

Label belum tersedia 10 Jan 12
Selesai Belum


20. GTB ELC. SOUND SYSTEM Kabel grounding belum terkoneksi ke
Busbar
10 Jan 12
Selesai Belum


21. GTB ELC. SOUND FIRE
ALARAM
Kabel grounding belum terkoneksi ke
Busbar
10 Jan 12
Selesai Belum


22. GTB ELC - BAS Kabel grounding belum terkoneksi ke
Busbar
10 Jan 12
Selesai Belum


23. GTB ELC - CCTV Kabel grounding belum terkoneksi ke
Busbar
10 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


10 | P a g e


A.3.2. DEFECT CHECKLIST PENYALUR PETIR (25 OKTOBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
24. PENYALUR PETIR Kawat sling kurang kencang 5 Jan 12
Selesai Belum

Tiang kurang kokoh 5 Jan 12
Selesai Belum





MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


11 | P a g e


A.3.3. DEFECT TESCOM GENSET (21 NOPEMBER 2012)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. GENSET NO. 1 Flexible silencer terlalu rapat 27 Des 11
Selesai Belum

Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning unit 5 Jan 12
Selesai Belum

Grounding untuk tangki harian belum
tersedia
5 Jan 12
Selesai Belum

Instalasi pipa panel control PLC tidak di
clamp
5 Jan 12
Selesai Belum

Selang di output pompa injection belum
tersedia
27 Des 11
Selesai Belum

Instalasi air bersih belum tersedia 27 Des 11
Selesai Belum

Bolt Valve belum tersedia name tag
Normaly Open/Close
5 Jan 12
Selesai Belum

Lube oil drain belum tersedia Nepel valve
1
27 Des 11
Selesai Belum

Pipa bahan bakar belum ada arah aliran 27 Des 11
Selesai Belum

Label belum tersedia 5 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


12 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
2. GENSET NO. 2 Flexible silencer terlalu rapat 27 Des 11
Selesai Belum

Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning unit 5 Jan 12
Selesai Belum

Grounding untuk tangki harian belum
tersedia
5 Jan 12
Selesai Belum

Instalasi pipa panel control PLC tidak di
clamp
5 Jan 12
Selesai Belum

Selang di output pompa injection belum
tersedia
27 Des 11
Selesai Belum

Instalasi air bersih belum tersedia 27 Des 11
Selesai Belum

Bolt Valve belum tersedia name tag
Normaly Open/Close
5 Jan 12
Selesai Belum

Lube oil drain belum tersedia Nepel valve
1
27 Des 11
Selesai Belum

Pipa bahan bakar belum ada arah aliran 27 Des 11
Selesai Belum

Label belum tersedia 5 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


13 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. GENSET NO. 3 Flexible silencer terlalu rapat 27 Des 11
Selesai Belum

Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning unit 5 Jan 12
Selesai Belum

Grounding untuk tangki harian belum
tersedia
5 Jan 12
Selesai Belum

Instalasi pipa panel control PLC tidak di
clamp
5 Jan 12
Selesai Belum

Selang di output pompa injection belum
tersedia
27 Des 11
Selesai Belum

Instalasi air bersih belum tersedia 27 Des 11
Selesai Belum

Bolt Valve belum tersedia name tag
Normaly Open/Close
5 Jan 12
Selesai Belum

Lube oil drain belum tersedia Nepel valve
1
27 Des 11
Selesai Belum

Pipa bahan bakar belum ada arah aliran 27 Des 11
Selesai Belum

Label belum tersedia 5 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


14 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
4. GENSET NO. 4 Flexible silencer terlalu rapat 27 Des 11
Selesai Belum

Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning unit 5 Jan 12
Selesai Belum

Grounding untuk tangki harian belum
tersedia
5 Jan 12
Selesai Belum

Instalasi pipa panel control PLC tidak di
clamp
5 Jan 12
Selesai Belum

Selang di output pompa injection belum
tersedia
27 Des 11
Selesai Belum

Instalasi air bersih belum tersedia 27 Des 11
Selesai Belum

Bolt Valve belum tersedia name tag
Normaly Open/Close
5 Jan 12
Selesai Belum

Lube oil drain belum tersedia Nepel valve
1
27 Des 11
Selesai Belum

Pipa bahan bakar belum ada arah aliran 27 Des 11
Selesai Belum

Label belum tersedia 5 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


15 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. GENSET NO. 5 Dudukan rack battery belum tersedia 27 Des 11
Selesai Belum

Bolt Valve belum tersedia name tag
Normaly Open/Close
5 Jan 12
Selesai Belum

Grounding untuk tangki harian belum
tersedia
5 Jan 12
Selesai Belum

Instalasi kabel control sebagian tidak
tersedia flexible
27 Des 11
Selesai Belum

Pipa bahan bakar belum ada arah aliran 27 Des 11
Selesai Belum

Labeling belum tersedia 5 Jan 12
Selesai Belum





MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


16 | P a g e


A.3.4. DEFECT TESCOM PANEL KONTROL GENSET (21 NOPEMBER 2012)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PANEL NO. 1 Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum

Wiring diagram 27 Des 11
Selesai Belum
Berada di PAKAR

2. PANEL NO. 2 Wiring diagram 27 Des 11
Selesai Belum
Berada di PAKAR
Cleaning panel 27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum


3. PANEL NO. 3 Wiring diagram 27 Des 11
Selesai Belum
Berada di PAKAR
Cleaning panel 27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum

CT.4000/5 A terbalik 5 Jan 12
Selesai Belum


4. PANEL NO. 4 Wiring diagram 27 Des 11
Selesai Belum
Berada di PAKAR
Cleaning panel 27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum

Jarak Bus bar dan body panel agar
supaya 3CM kecuali Bus Bar grounding
27 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


17 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. PANEL NO. 5 Wiring diagram 27 Des 11
Selesai Belum
Berada di PAKAR
Cleaning panel 27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum


6. PANEL NO. 6 Wiring diagram 27 Des 11
Selesai Belum
Berada di PAKAR
Cleaning panel 27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum

Jarak Bus bar dan body panel agar
supaya 3CM kecuali Bus Bar grounding
(Kecuali Bus Bar Grounding)
27 Des 11
Selesai Belum


7. PANEL NO. 7 Wiring diagram 27 Des 11
Selesai Belum
Berada di PAKAR
Cleaning panel 27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


18 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
8. PANEL NO. 8 Wiring diagram 27 Des 11
Selesai Belum
Berada di PAKAR
Cleaning panel 27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum

Jarak Bus bar dan body panel agar
supaya 3CM kecuali Bus Bar grounding
(Kecuali Bus Bar Grounding)
27 Des 11
Selesai Belum


9. PANEL NO. 9 Wiring diagram 27 Des 11
Selesai Belum

Label cubicle belum tersedia 5 Jan 12
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum


10. PANEL NO. 10 Wiring diagram 27 Des 11
Selesai Belum

Label cubicle belum tersedia
Selesai Belum

Jarak Bus bar dan body panel agar
supaya 3CM kecuali Bus Bar grounding
(Kecuali Bus Bar Grounding)
27 Des 11
Selesai Belum

Sebagian instalasi kabel control tidak
menggunakan flexible
27 Des 11
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


19 | P a g e


A.3.5. DEFECT TESCOM TRANSFORMATOR (18 OKTOBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
25. TRAFO No. 1 Roller stopper belum ada 29 Des 11
Selesai Belum

Thermometer belum tersedia 29 Des 11
Selesai Belum


26. TRAFO No. 2 Roller stopper belum ada 29 Des 11
Selesai Belum

Thermometer belum tersedia 29 Des 11
Selesai Belum


27. TRAFO No. 3 Roller stopper belum ada 29 Des 11
Selesai Belum

Thermometer belum tersedia 29 Des 11
Selesai Belum


28. TRAFO No. 4 Roller stopper belum ada 29 Des 11
Selesai Belum

Thermometer belum tersedia 29 Des 11
Selesai Belum


29. TRAFO No. 5 Roller stopper belum ada 29 Des 11
Selesai Belum

Thermometer belum tersedia 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


20 | P a g e


A.3.6. DEFECT TESCOM PANEL (2 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PUTR CR Cleaning cubicle dan ruangan 18 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 18 Des 11
Selesai Belum


2. P CAPACITOR BANK
1000KVAR (PUTR CR)
Cleaning cubicle dan ruangan 18 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 18 Des 11
Selesai Belum


3. PUTR MALL 1 Name tag belum permanent 29 Des 11
Selesai Belum

Lubang kabel belum ditutup 5 Jan 11
Selesai Belum

Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Instalasi kabel control FRC belum rapi 18 Des 11
Selesai Belum

Grounding pintu panel belum terkonek 29 Des 11
Selesai Belum


4. P CAPACITOR BANK
1000KVAR (PUTR MALL 1
)
Wiring diagram belum tersedia di panel 29 Des 11
Selesai Belum


5. PUTR MALL 2 Wiring diagram belum tersedia di panel 18 Des 11
Selesai Belum

Name tag belum permanent 18 Des 11
Selesai Belum

Instalasi kabel Bas tidak rapi
Selesai Belum
Linkup elektronik
Cleaning panel dan ruangan 18 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


21 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
6. P CAPACITOR BANK
1000KVAR (PUTR MALL 2)
Cleaning panel dan ruangan 20 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum


7. PANEL CUB.ARRESTER
(CUB 1) 630A/16KA 24KV
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel dan ruangan 20 Des 11
Selesai Belum


8. PANEL OUTGOING ALBS
BF 6
630A/16KA 24KV
(CUB No. 4)
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel dan ruangan 20 Des 11
Selesai Belum


9. PANEL OUTGOING ALBS
BF 6
630A/16KA 24KV (CUB No.
3)
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel dan ruangan 20 Des 11
Selesai Belum


10. PANEL OUTGOING ALBS
BF 6
630A/16KA 24KV (CUB No.
5)
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel dan ruangan 20 Des 11
Selesai Belum


11. PANEL OUTGOING ALBS
BF 6
630A/16KA 24KV (CUB No.
2)
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel dan ruangan 20 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


22 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
12. PANEL OUTGOING ALBS
BF 6
630A/16KA 24KV (CUB No.
6)
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel dan ruangan 20 Des 11
Selesai Belum


13. PANEL OUTGOING ALBS
BF 6
630A/16KA 24KV (CUB No.
7)
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel dan ruangan 20 Des 11
Selesai Belum


14. PANEL OUTGOING ALBS
BF 6
630A/16KA 24KV (CUB No.
7)
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel dan ruangan 20 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


23 | P a g e


A.3.7. DEFECT TESCOM PANEL (3 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P.CAP BANK 1100KVAR
PUTR MALL 3
Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum


2. PUTR MALL 3 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Lubang masuk kabel belum ditutup 29 Des 11
Selesai Belum

Label belum permanen 29 Des 11
Selesai Belum

Cleaning panel dan ruangan 18 Des 11
Selesai Belum


3. P.CAP BANK 1100KVAR
PUTR MALL 4
Wiring diagram belum tersedia di panel 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


24 | P a g e


A.3.8. DEFECT TESCOM PANEL (4 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P CWP M.05 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum


2. P CWP M.04 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum


3. P CWP M.03 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum


4. P CWP M.02 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum


5. P CWP M.01 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


25 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
6. P CHWP M.01 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum

Opening panel sisi atas belum ditutup 20 Des 11
Selesai Belum


7. P CHWP M.04 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum

Opening panel sisi atas belum ditutup 20 Des 11
Selesai Belum


8. P CHWP M.03 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum

Opening panel sisi atas belum ditutup 20 Des 11
Selesai Belum


9. P CHWP M.02 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum

Opening panel sisi atas belum ditutup 20 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


26 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
10. P CHWP M.01 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum

Opening panel sisi atas belum ditutup 20 Des 11
Selesai Belum


11. P CHILLER MALL 4 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum


12. P CHILLER MALL 3 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum


13. P CHILLER MALL 2 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum


14. P CHILLER MALL 1 Wiring diagram belum tersedia di panel 20 Des 11
Selesai Belum

Cleaning panel & ruangan 20 Des 11
Selesai Belum

Sebagian lampu indicator redup 20 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


27 | P a g e


A.3.9. DEFECT TESCOM PANEL (7 NOPEMBER 2011) - 1
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PL B1B Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


2. P KIOS B1C Wiring diagram belum tersedia 20 Des 11
Selesai Belum


3. P ESC.B1C Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


4. PL ESC.B1D Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


5. PL ESC.B1A Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


6. PL B1C Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


7. PL B1A Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


8. P KIOS B2D Cleaning panel 20 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


28 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Wiring diagram belum tersedia 20 Des 11
Selesai Belum


9. P.KIOS B1D Cleaning Panel 5 Jan 12
Selesai Belum

Wiring diagram 5 Jan 12
Selesai Belum


10. PL B2A Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


11. PL B2B Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


12. PL B2D Cleaning panel 5 Jan 12
Selesai Belum

Wiring diagram 5 Jan 12
Selesai Belum

Perapihan instalasi 5 Jan 12
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


29 | P a g e


A.3.10. DEFECT TESCOM PANEL (7 NOPEMBER 2011) 2
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PL B2C Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum


2. PL B2D Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum


3. P-KIOS.B2C Cleaning panel 3 Jan 2012
Selesai Belum

Wiring belum tersedia 3 Jan 2012
Selesai Belum






MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


30 | P a g e


A.3.11. DEFECT TESCOM PANEL (10 NOPEMBER 2011) -1
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P.KIOS LG-B Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 25 Des 11
Selesai Belum

Opening panel perlu ditutup rapat 25 Des 11
Selesai Belum


2. PL.EXT - LGB Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum

Opening panel perlu ditutup rapat 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 16 Des 11
Selesai Belum


3. ESC - LGB Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum


4. PL-EXT LGA Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 25 Des 11
Selesai Belum


5. P.KIOS LG C Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


31 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Opening panel perlu ditutup rapat 25 Des 11
Selesai Belum

6. P-KIOS LGC Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum

Opening panel perlu ditutup rapat 25 Des 11
Selesai Belum


7. P ESC.LGB Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum


8. P KIOS LGA Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum


9. P KIOS LGB Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum


10. PL LGA Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum


11. PL TRAV.LGA Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


32 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
12. P EXT.LGA Sebagian MCB Trip 25 Des 11
Selesai Belum

Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


33 | P a g e


A.3.12. DEFECT TESCOM PANEL (10 NOPEMBER 2011) -2
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P-ESC.GFA Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum

Outgoing grounding belum disambung ke
panel
29 Des 11
Selesai Belum


2. P-EXT GFA Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum

Sebagian Lampu indicator redup 29 Des 11
Selesai Belum


3. P KIOS GFA Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Opening cubicle belum ditutup 29 Des 11
Selesai Belum

Sebagian Lampu indicator redup 29 Des 11
Selesai Belum


4. PL GFA Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Instalasi piping kurang rapih 29 Des 11
Selesai Belum

Sebagian Lampu indicator redup 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


34 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. PL EXT.S.ELEV Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian kabel belum selesai 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Perapihan instalasi kabel 29 Des 11
Selesai Belum

Sebagian Lampu indicator redup 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


35 | P a g e


A.3.13. DEFECT TESCOM PANEL (11 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P.SMF LG Cleaning dan wiring 25 Des 11
Selesai Belum


2. P.ESC LGD Cleaning panel 25 Des 11
Selesai Belum


3. PL.EXT LGD Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 25 Des 11
Selesai Belum


4. P.KIOS LGD Cleaning panel
Selesai Belum


5. PL LGD Wiring diagram 25 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 25 Des 11
Selesai Belum


6. P.ESC LGC Cleaning panel 25 Des 11
Selesai Belum


7. PL.EXT LGC Clenaning panel 25 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 25 Des 11
Selesai Belum


8. PL LGC Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 25 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


36 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
9. P.TRAV LGA Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 16 Des 11
Selesai Belum

Opening cubicle perlu ditutup 27 Des 11
Selesai Belum


10. P LGA Sebagian lampu indicator redup 27 Des 11
Selesai Belum


11. P.KIOS - LGA Dudukan panel belum permanen 25 Des 11
Selesai Belum


12. P.KIOS - LGA Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum

Cleaning 25 Des 11
Selesai Belum


13. PL.EXT. LGD Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 25 Des 11
Selesai Belum

Cleaning 25 Des 11
Selesai Belum


14. PL LGD Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 25 Des 11
Selesai Belum

Cleaning 25 Des 11
Selesai Belum

Handle cubicle rusak 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


37 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
15. P.ESC LGD Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning Panel 25 Des 11
Selesai Belum


16. P.ESC LGC Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Cleaning Panel 25 Des 11
Selesai Belum


17. PL .EXT LGC Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Sebagian lampu indicator redup
Selesai Belum

Sebagian cubicle selector rusak 25 Des 11
Selesai Belum

Cleaning panel 25 Des 11
Selesai Belum


18. PUTR MALL 4 Wiring diagram belum tersedia 25 Des 11
Selesai Belum

Nameplate belum terpasang 25 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


38 | P a g e


A.3.14. DEFECT TESCOM PANEL (14 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PL - GFC Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


2. PL GFB Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


3. P KIOS GFB Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


4. P ESC.GFB Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


5. PL EXT.EAST ELEV Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


6. PL EXT.GFB Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


39 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
7. PL EXT.GFB Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum

Sebagian indicator redup 20 Des 11
Selesai Belum

Opening panel perlu ditutup 20 Des 11
Selesai Belum


8. PL - GFB Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


9. PL .EXT GFB Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum


10. PL.EXT E ELEV Cleaning panel 20 Des 11
Selesai Belum

Wiring diagram belum tersedia 20 Des 11
Selesai Belum

Opening panel perlu ditutup 20 Des 11
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


40 | P a g e


A.3.15. DEFECT TESCOM PANEL (5 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PL ESC.GFC Sebagian Lampu indicator redup 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram agar dilengkapi 29 Des 11
Selesai Belum


2. PL GFD 1 Set contactor rusak 5 Jan 12
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Lampu indicator sebagian redup 29 Des 11
Selesai Belum

Sebagian contactor belum terpasang 29 Des 11
Selesai Belum

Switch selector tidak lengkap 29 Des 11
Selesai Belum


3. PL EXT.GFC Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum


4. PL EXT N ELV Cleaning panel 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


41 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. P KIOS GFC Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


42 | P a g e


A.3.16. DEFECT TESCOM PANEL (17 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P ESC.GFD Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum


2. PL EXT.WEST ELEV Grounding penerangan belum disambung 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum


3. P EXT.GFD Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum

Sebagian sambungan kabel tidak
menggunakan terminal
29 Des 11
Selesai Belum


4. P KIOS.GFD Access bukaan pintu panel terhalang
dinding

Selesai Belum
Lingkup Sipil
Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


43 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. P ESC.GFD Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum


6. PL EXT.GFD Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Sebagian sambungan kabel tidak
menggunakan terminal
29 Des 11
Selesai Belum


7. P KIOS.GFD Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Pintu cubicle terhalang dinding 29 Des 11
Selesai Belum


8. PL EX.W.ELEV Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum






MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


44 | P a g e


A.3.17. DEFECT TESCOM PANEL (28 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P ESC.UGA Perapihan kabel ties 27 Des 11
Selesai Belum

Panel cleaning 27 Des 11
Selesai Belum

Wiring diagram belum ada di panel 27 Des 11
Selesai Belum


2. PL EXT.UGA Sebagian lampu indicator redup 27 Des 11
Selesai Belum

Panel cleaning 27 Des 11
Selesai Belum

Wiring diagram belum ada di panel 27 Des 11
Selesai Belum

Fire stop belum ada 5 Jan 12
Selesai Belum

Labeling belum ada 27 Des 11
Selesai Belum


3. P KIOS UGA Sebagian instalasi belum dikerjakan (stop
kontak lantai)
5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum

Panel cleaning 27 Des 11
Selesai Belum

Wiring diagram belum ada di panel 27 Des 11
Selesai Belum


4. PL UGA Sebagian lampu indicator redup 27 Des 11
Selesai Belum

Panel cleaning 27 Des 11
Selesai Belum

Wiring diagram belum ada di panel 27 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


45 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. P KIOS UGC Panel cleaning 27 Des 11
Selesai Belum

Wiring diagram belum ada di panel 27 Des 11
Selesai Belum

Fire stop belum ada
Selesai Belum
LINGKUP SIPIL

6. P KIOS UGD Panel cleaning 27 Des 11
Selesai Belum

Wiring diagram belum ada di panel 27 Des 11
Selesai Belum

Fire stop belum memadai 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum


7. PL - UGC MCCB 60A over load (Tem. 62oC) 27 Des 11
Selesai Belum

Contactor di naikin 1 tingkat 27 Des 11
Selesai Belum

Wiring diagram belum ada di panel 27 Des 11
Selesai Belum

Panel cleaning 27 Des 11
Selesai Belum


8. PL UGD Wiring diagram belum ada di panel 27 Des 11
Selesai Belum

Panel cleaning 27 Des 11
Selesai Belum

Kabel grounding pintu kurang panjang 27 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum

Ruangan elektrikal dilalui pipa AC 5 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


46 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
9. P ESC.UGD Panel cleaning 27 Des 11
Selesai Belum


10. PNL CTRL C.TOWER
MALL 4
Panel cleaning 5 Jan 12
Selesai Belum

Wiring diagram belum ada di panel 5 Jan 12
Selesai Belum

Opening panel sisi atas belum ditutup 5 Jan 12
Selesai Belum

Pemasangan protector belum rapih 5 Jan 12
Selesai Belum


11. PNL CTRL C.TOWER
MALL 3
Panel cleaning 5 Jan 12
Selesai Belum

Wiring diagram belum ada di panel 5 Jan 12
Selesai Belum

Opening panel sisi atas belum ditutup 5 Jan 12
Selesai Belum

Pemasangan protector belum rapih 5 Jan 12
Selesai Belum


12. PNL CTRL C.TOWER
MALL 2
Terminasi grounding kurang sempurna 5 Jan 12
Selesai Belum

Panel cleaning 5 Jan 12
Selesai Belum

Wiring diagram belum ada di panel 5 Jan 12
Selesai Belum


13. PNL CTRL C.TOWER
MALL 1
Terminasi grounding kurang sempurna 5 Jan 12
Selesai Belum

Panel cleaning 5 Jan 12
Selesai Belum

Wiring diagram belum ada di panel 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


47 | P a g e


A.3.18. DEFECT TESCOM PANEL (30 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. SDP B Grounding pintu panel tidak ada 5 Jan 12
Selesai Belum

Fire stop belum terpasang 5 Jan 12
Selesai Belum
LINGKUP SIPIL
Label belum tersedia 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum


2. PL P3 Incoming grounding belum ada 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 29 Des 11
Selesai Belum


3. PL UGB Perapihan installasi 29 Des 11
Selesai Belum

Incoming grounding belum ada 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


48 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
4. PL P1 Pintu cubicle panel belum ada grounding 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 29 Des 11
Selesai Belum


5. P KIOS UGB Incoming grounding belum terpasang 29 Des 11
Selesai Belum

Pintu cubicle panel belum ada grounding 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 29 Des 11
Selesai Belum


6. PL P2 Incoming grounding belum terpasang 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Wiring diagram belum tersedia di panel 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


49 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
7. PL 1A Kabel incoming 16mm
2
perlu ditambah
karena beban yang dipikul 88.9A
29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum

Sebagian lampu indicator redup
Selesai Belum


8. P KIOS 1A Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum


9. SDP A Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum

Label belum permanen 27 Des 11
Selesai Belum


10. SDP KIOS A Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum

Label belum permanen 27 Des 11
Selesai Belum

Cover temper meter pecah
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


50 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
11. SDP ESC.A Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


51 | P a g e


A.3.19. DEFECT TESCOM PANEL (1 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P KIOS 1C Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum


2. PL 1D Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum


3. PL 1C Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Cleaning panel 27 Des 11
Selesai Belum

Terminasi penerangan perlu diperbaiki 27 Des 11
Selesai Belum

Perbaikan kontaktor 27 Des 11
Selesai Belum





MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


52 | P a g e


A.3.20. DEFECT TESCOM PANEL (2 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P KIOS 1D Cleaning panel dan ruangan 27 Des 11
Selesai Belum

Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum


2. SDP KIOS B Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum


3. PL P4 Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Perapihan instalasi kabel 29 Des 11
Selesai Belum


4. SDP KIOS 1B Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Cover sisi atas cubicle tidak ada 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


53 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. P ESC.1D Cleaning panel dan ruangan 27 Des 11
Selesai Belum

Wiring diagram belum tersedia 27 Des 11
Selesai Belum

Sebagian lampu indicator redup 27 Des 11
Selesai Belum


6. PL 1B Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Grounding pintu cubicle belum disambung 29 Des 11
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


54 | P a g e


A.3.21. DEFECT TESCOM PANEL (5 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. SDP KIOS C Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Label belum permanen 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum


2. SDP KIOS D Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum


3. PL P5 Penyambungan grounding tidak
mengguna gigi macan
29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Cleaning panel dan ruangan 29 Des 11
Selesai Belum


4. SDP 01 Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Label belum permanen 29 Des 11
Selesai Belum

Grounding pintu lepas 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


55 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. SDP AC.C Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum


6. SDP D2 Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Label belum permanen 29 Des 11
Selesai Belum


7. SDP C Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Body panel cacat 29 Des 11
Selesai Belum


8. SDP ESC.C Cleaning panel dan ruangan 29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Sebagian lampu indicator redup 29 Des 11
Selesai Belum

Label belum permanen 29 Des 11
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


56 | P a g e


A.3.22. DEFECT TESCOM PANEL (6 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PL TK.1 Cleaning panel dan ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum


2. PL TK.4 Cleaning panel dan ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum


3. SDP ESC.D Cleaning panel dan ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum

Label belum permanen 5 Jan 12
Selesai Belum


4. PL TK.6 Cleaning panel dan ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum

Kerapihan instalasi kabel 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


57 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. PL LIFT PEN 05 Cleaning panel dan ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum

Kerapihan instalasi kabel + protector 5 Jan 12
Selesai Belum


6. PL TK.5 Cleaning panel dan ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum


7. PL TK.3 Cleaning panel dan ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum


8. P.CTRL-SMF.PO.01 Cleaning panel dan ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Perubahan instalasi dari 7.5kW ke 18.5kW 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


58 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
9. PL.TK.2 Cleaning 5 Jan 12
Selesai Belum

Wiring 5 Jan 12
Selesai Belum

Lubang masuk akbel belum ditutup 5 Jan 12
Selesai Belum

Protector 5 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


59 | P a g e


A.3.23. DEFECT TESCOM PANEL (9 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P.FAN R.M&E
CUB.1
Opening panel sisi atas tidak rapat 25 Des 11
Selesai Belum

Cleaning panel & cubicle 25 Des 11
Selesai Belum


2. P.FAN R.M&E
CUB.2
Opening panel sisi atas tidak rapat 25 Des 11
Selesai Belum

MCB trip 5 Jan 11
Selesai Belum

Cleaning panel & cubicle 25 Des 11
Selesai Belum

Motor short 25 Des 11
Selesai Belum


3. P.FAN R.M&E
CUB.3
Cleaning panel & cubicle 25 Des 11
Selesai Belum


4. P.FAN R.M&E
CUB.4
Cleaning panel & cubicle 25 Des 11
Selesai Belum


5. P.FAN R.M&E
CUB.5
Cleaning panel & cubicle 25 Des 11
Selesai Belum


6. P.FAN R.M&E
CUB.6
Cleaning panel & cubicle 25 Des 11
Selesai Belum


7. P.FAN R.M&E
CUB.7
Cleaning panel & cubicle 25 Des 11
Selesai Belum


8. P.FAN R.M&E Cleaning panel & cubicle 25 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


60 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
CUB.8

9. P.FAN R.M&E
CUB.9
Cleaning panel & cubicle 25 Des 11
Selesai Belum


10. P.FAN R.M&E
CUB.10
Cleaning panel & cubicle 25 Des 11
Selesai Belum


11. P.FAN R.M&E
CUB.11
Cleaning panel & cubicle 25 Des 11
Selesai Belum


12. P.FAN R.M&E
CUB.12
Cleaning panel & cubicle 25 Des 11
Selesai Belum


13. P.FAN R.M&E
CUB.13
Cleaning panel & cubicle
Selesai Belum

Motor belum tersambung 5 Jan 11
Selesai Belum


14. P.FAN R.M&E
CUB.14
Cleaning panel & cubicle 25 Des 11
Selesai Belum


15. P.FAN R.M&E
CUB.15
Cleaning panel & cubicle 25 Des 11
Selesai Belum


16. P.FAN R.M&E
CUB.16
Cleaning panel & cubicle 25 Des 11
Selesai Belum


17. P.FAN R.M&E Cleaning panel & cubicle 25 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


61 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
CUB.18

18. P.FAN R.M&E
CUB.19
Cleaning panel & cubicle 25 Des 11
Selesai Belum


19. P.FAN R.M&E
CUB.20
Cleaning panel & cubicle 25 Des 11
Selesai Belum


20. P.FAN R.M&E
CUB.21
Cleaning panel & cubicle 25 Des 11
Selesai Belum


21. SDP R.M&E Perapihan instalasi 25 Des 11
Selesai Belum

Cleaning 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 25 Des 11
Selesai Belum

Wiring diagram belum ada 25 Des 11
Selesai Belum


22. PLR.M&E Perapihan instalasi 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 25 Des 11
Selesai Belum

Wiring diagram belum ada 25 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


62 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
23. SDP - EMERGENCY MCB untuk keperluan SMF.P-01 dengan
motor 18.5 kW belum tersedia
29 Des 11
Selesai Belum

Opening cubicle tidak rapat 25 Des 11
Selesai Belum

Sebagian lampu indicator redup 25 Des 11
Selesai Belum

Perbaikan instalasi kabel dari NYY ke
FRC
29 Des 11
Selesai Belum

Wiring diagram belum ada 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


63 | P a g e


A.3.24. DEFECT TESCOM PANEL (12 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P OUTSOURCING Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Cleaning panel 5 Jan 12
Selesai Belum

Perapihan instalasi kabel 5 Jan 12
Selesai Belum


2. P. MANAGEMENT Perapihan instalasi 5 Jan 12
Selesai Belum

Cleaning panel 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum

Wiring diagram belum ada 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


64 | P a g e


A.3.25. DEFECT TESCOM PANEL (13 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. SDP - POMPA Cleaning panel & ruangan 5 Jan 12
Selesai Belum

Perapihan instalasi kabel & kabel tray 5 Jan 12
Selesai Belum

Penyambungan grounding tidak
menggunakan clamp
5 Jan 12
Selesai Belum

Label belum permanent 5 Jan 12
Selesai Belum

Cover panel sisi belakang belum ditutup 5 Jan 12
Selesai Belum


2. P RUANG CONTROL Perapihan instalasi grounding 5 Jan 12
Selesai Belum

Cleaning panel 5 Jan 12
Selesai Belum

Wiring diagram belum ada 5 Jan 12
Selesai Belum


3. P MDF TELKOM Cleaning panel 5 Jan 12
Selesai Belum

Wiring diagram belum ada 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum

Opening cubicle sisi atas tidak rapat 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


65 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
4. SDP - PARKIR Cleaning panel 5 Jan 12
Selesai Belum

Wiring diagram belum ada 5 Jan 12
Selesai Belum

Opening cubicle sisi atas tidak rapat 5 Jan 12
Selesai Belum


5. PL P6/P6A Cover protector belum lengkap 5 Jan 12
Selesai Belum

Opening panel sisi atas tidak rapat 5 Jan 12
Selesai Belum





MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


66 | P a g e


A.3.26. DEFECT TESCOM PANEL (15 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PAC B2A Opening panel sisi atas belum rapat 5 Jan 11
Selesai Belum

Sebagian lampu indicator redup 5 Jan 11
Selesai Belum

Wiring diagram belum tersedia 5 Jan 11
Selesai Belum


2. PAC B2B Opening panel sisi atas belum rapat 5 Jan 11
Selesai Belum

Wiring diagram belum tersedia 5 Jan 11
Selesai Belum


3. PAC B2C Opening panel sisi atas belum rapat 5 Jan 11
Selesai Belum

Wiring diagram belum tersedia 5 Jan 11
Selesai Belum


4. PAC B2D Opening panel sisi atas belum rapat 5 Jan 11
Selesai Belum

Wiring diagram belum tersedia 5 Jan 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


67 | P a g e


A.3.27. DEFECT TESCOM PANEL (19 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PAC B1A Opening panel sisi atas belum ditutup
rapat
5 Jan 12
Selesai Belum

Exhaust Fan ruangan tidak berfungsi 5 Jan 12
Selesai Belum

Cleaning ruangan 5 Jan 12
Selesai Belum

Wiring diagram belum terpasang 5 Jan 12
Selesai Belum


2. PAC B1D 1-1 Instalasi EAF B1.20 (2.2kW) belum
tersedia switch selector push button,
lampu indicator dan DOL
5 Jan 12
Selesai Belum

Exhaust Fan ruangan tidak berfungsi 5 Jan 12
Selesai Belum

Cleaning panel 5 Jan 12
Selesai Belum

R. Panel B1D tersedia head sprinkler
agar di Dop
5 Jan 12
Selesai Belum

TOR EAF B1.04 terlalu besar, agar
diganti dengan TOR yang sesuai
dengan kapasitas motor
5 Jan 12
Selesai Belum

Opening panel sisi atas belum ditutup 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


68 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. PAC B1D 1-2 Temperatur overload relay terlalu
besar, agar diganti dengan TOR yang
sesuai dengan kapasitas motor
5 Jan 12
Selesai Belum

Panel cleaning 5 Jan 12
Selesai Belum

Wiring diagram belum terpasang 5 Jan 12
Selesai Belum


4. PAC B1D 1-3 Contactor GMC 22 agar di
seragamkan dengan
sampingnyamenjadi GMC 32 untuk
keperluan hubungan Star Delta
5 Jan 12
Selesai Belum

Panel cleaning 5 Jan 12
Selesai Belum

Wiring diagram belum terpasang 5 Jan 12
Selesai Belum


5. PAC B1B Wiring diagram belum terpasang 5 Jan 12
Selesai Belum

Switch Selector sebagian rusak 5 Jan 12
Selesai Belum

Cleaning ruangan + panel 5 Jan 12
Selesai Belum

Labeling belum lengkap 5 Jan 12
Selesai Belum

TOR EAF B1.02 terlalu besar agar
diganti sesuai kapasitas motor
5 Jan 12
Selesai Belum


6. PAC B1C Wiring diagram belum terpasang 5 Jan 12
Selesai Belum

Cleaning ruangan + panel 5 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


69 | P a g e


A.3.28. DEFECT TESCOM PANEL (20 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PAC LGC Wiring diagram belum terpasang 5 Jan 11
Selesai Belum

Incoming grounding kurang besar
yang terpasang 10 mm
2
dirubah
menjadi 25mm
2

5 Jan 11
Selesai Belum

Grounding 5 Jan 11
Selesai Belum


2. PAC LGD Instalasi Star Delta EAF LG.FC 03
11kw belum tersedia.
5 Jan 11
Selesai Belum

Opening panel sisi atas belum rapat. 5 Jan 11
Selesai Belum

Component tidak complete 5 Jan 11
Selesai Belum

Wiring diagram belum terpasang 5 Jan 11
Selesai Belum


3. PAC LGA Cover protector belum tidak lengkap 5 Jan 11
Selesai Belum

Sebagian lampu indicator redup 5 Jan 11
Selesai Belum

TOR IAF LG.FC.4 terlalu besar,
ganti dengan disesuaikan kapasitas
motor
5 Jan 11
Selesai Belum

Wiring diagram 5 Jan 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


70 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
4. P. SMF LG Incoming grounding terpasang 4 mm
2
perlu penambahan diameneter kabel
grounding
5 Jan 11
Selesai Belum

Wiring diagram belum terpasang 5 Jan 11
Selesai Belum


5. PAC - LGB Wiring diagram belum terpasang 5 Jan 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


71 | P a g e


A.3.29. DEFECT TESCOM PANEL (21 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PAC GF.C TOR agar disesuaikan dengan
kapasitas motor, karena yang
terpasang sekarang terlalu besar
5 Jan 11
Selesai Belum

Grounding perlu ditambah karena
yang terpasang kurang besar
29 Des 11
Selesai Belum

Wiring diagram belum tersedia 29 Des 11
Selesai Belum


2. PAC GF.A Wiring diagram belum tersedia 29 Des 11
Selesai Belum


3. PAC GF.B Wiring diagram belum tersedia 29 Des 11
Selesai Belum

Untuk instalasi EAF GFC.1A termal
over load relay terlalu besar sehingga
perlu penggantian TOR di sesuaikan
dengan kapasitas motor
5 Jan 11
Selesai Belum



4. PAC GFD .1-1 Kapasitas TOR-IAF.GF.C.03 dan
EAF GF.C.01 terlalu besar
kapasitasnya agar disesuaikan
dengan kapasitas motor
5 Jan 11
Selesai Belum


5. PAC GFD .1-3 Kapasitas TOR agar disesuaikan
dengan kapasitas motor
5 Jan 11
Selesai Belum


6. PAC GFD .1-2
Service IAF-GFC.01
Kapasitas OL terlalu besar perlu
perubahan TOR sesuai kapasitas
motor
5 Jan 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


72 | P a g e


A.3.30. DEFECT TESCOM PANEL (21 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PAC UG.A (1-1) Penambahan grounding incoming 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 27 Des 11
Selesai Belum

TOR IAF UG.FC.01 terlalu
besaragar dipasang Overload rating
sesuai dengan kapasitas motor
5 Jan 12
Selesai Belum


2. PAC UG.A (1-5) TOR terlalu besar perlu penyesuaian
kapasitas motor
5 Jan 12
Selesai Belum


3. PAC UG.D (1-1) Incoming grounding perlu ditambah
5 Jan 12
Selesai Belum

Wiring diagram belum tersedia
5 Jan 12
Selesai Belum


4. PAC UG.D (1-4) Kapasitas TOR agar diselesaikan
dengan motor terpasang
5 Jan 12
Selesai Belum


5. PAC UG.D (1-5) Kapasitas TOR agar diselesaikan
dengan motor terpasang
5 Jan 12
Selesai Belum


6. PAC 1A Cleaning panel 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum


7. SDP AC.A Kabel temporary agar dilepas 5 Jan 12
Selesai Belum

Cleaning panel 5 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


73 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
8. PAC 1D TOR Rusak 5 Jan 12
Selesai Belum


9. All Ruang shaft Pemasangan Fire Stop
Selesai Belum
PP. konfirmasi
dengan bag. sipil

10. PUTR-Mall No 3
Incoming Genset mall 3 Cell No. 4
Phase pada ACB hanya ada 2 phase
yang 1 phase tidak ada.

Selesai Belum
PP. konfirmasi
dengan pengelola



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


74 | P a g e


A.3.31. DEFECT TESCOM PANEL (22 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. SDP PEN. A Fire stop belum tersedia
Selesai Belum
Lingkup sipil

2. SDP PEN. B Volt Meter rusak 29 Des 11
Selesai Belum

Cleaning panel 29 Des 11
Selesai Belum


3. P.SMF-GF Incoming grounding belum dipasang 29 Des 11
Selesai Belum

Wiring diagram belum terpasang 29 Des 11
Selesai Belum


4. SDP.AC-D Labeling belum tersedia 29 Des 11
Selesai Belum

Wiring diagram belum terpasang 29 Des 11
Selesai Belum

Cover samping melengkung (tidak
rapih)
5 Jan 12
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


75 | P a g e


A.3.32. DEFECT TESCOM PANEL (23 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. SDP.LIFT Wiring diagram belum tersedia 5 Jan 12
Selesai Belum


2. PP LIFT SERV 06 Panel Cleaning 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum

Opening panel belum ditutup 5 Jan 12
Selesai Belum

Perapihan kabel 5 Jan 12
Selesai Belum


3. PP LIFT FIRE 06 Sebagian lampu indicator redup 5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum


4. PP LIFT PEN 07 Perapihan panel 5 Jan 12
Selesai Belum

Labeling 5 Jan 12
Selesai Belum

Opening panel belum ditutup 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum

Wiring diagram 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


76 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. PP LIFT SERV 02 Instalasi electronic di panel tidak
rapih
5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum


6. PP LIFT FIRE 02 Opening panel sisi bawah belum
ditutup
5 Jan 12
Selesai Belum

Wiring diagram belum tersedia 5 Jan 12
Selesai Belum

Sebagian lampu indicator redup 5 Jan 12
Selesai Belum


7. SDP ESC.B Wiring diagram belum tersedia 5 Jan 12
Selesai Belum


8. SDP AC.B Opening panel sisi atas belum rapat 5 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


77 | P a g e


A.3.33. DEFECT TESCOM PANEL (27 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. P HYDRANT Grounding pintu lepas 5 Jan 11
Selesai Belum

Cleaning instalasi kabel tray 5 Jan 11
Selesai Belum

Sebagian lampu indicator redup 5 Jan 11
Selesai Belum


2. P ESC 2D Perapihan Instalasi Kabel 5 Jan 11
Selesai Belum


3. SDP PEN.D Handle pintu panel rusak 5 Jan 11
Selesai Belum

Perapihan instalasi kabel 5 Jan 11
Selesai Belum

PL.1D (R=90, S=80, T=60)
Perlu balancing beban
5 Jan 11
Selesai Belum

PL.LGD (R=79, S=101, T=93)
Perlu balancing beban
5 Jan 11
Selesai Belum

PL.B2D (R=5.2, S=12, T=6.7)
Perlu balancing beban
5 Jan 11
Selesai Belum


4. SDP PEN.C PL.GFC Q3 (R=34, S=44, T=30.6)
Perlu balancing beban
5 Jan 11
Selesai Belum

PL.1C Q4 (R=22, S=30, T=15)
Perlu balancing beban
5 Jan 11
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


78 | P a g e


B. ELEKTRONIK
B.1. STATUS PEKERJAAN ELEKTRONIK
Peralatan elektronik untuk Sound System, CCTV, BAS,
Fire Alarm sudah selesai checklist.
Interface peralatan sound system antara BOSE dan
BOSCH.
Emergency Call System sudah di fungsikan namun masih
terkendala pada Back Up power.
Ratifikasi bersama defect elektronik antara NAI, PAKAR,
Pengelola dan PP.
Dokumen-dokumen masih belum lengkap, seperti single
line diagram system, test impedance sound system, test
internal. Dan terus kami dorong kontraktor untuk
melengkapinya.
CCTV belum sluruhnya terpasang dan akan dipasang oleh
pihak Azbil.
Defect peralatan CCTV belum dikerjakan (By Azbil).
Speaker belum seluruhnya terpasang.
Kabel header MCFA yang melalui R. Pengelola sedang
dalam perapihan.
Equalizer sound system yang rusak masih dalam garansi
dan akan diganti baru oleh PT. Tetra.
Kabel speaker putus sehingga speaker sound system
tidak aktif (hidup) dan saat ini dalam perbaikan oleh pihak
Tetra.
Permasalahan dengung atau bergaung sedang diperbaiki
oleh pihak Tetra.

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


79 | P a g e


B.2. PROGRES TESCOM ELEKTRONIK
















0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
BAS SOUND
SYSTEM
FIRE ALARM CCTV
Checklist 100% 100% 100% 100%
Test 32% 40% 32% 0%
100% 100% 100% 100%
32%
40%
32%
0%
PROGRESS TESCOM ELEKTRONIK
SISTEM
CHECKLIST
(%)
TESTCOM
(%)
KETERANGAN
BAS
Panel BAS 100% 63%
Poin List 100% 13%

SOUND SYSTEM
Panel SS 100% 100%
Ceiling Speaker 100% 99%
Horn Speaker 100% 0%
Wall Speaker 100% 0%
Car Call 100% 0%

FIRE ALARM
Panel FA 100% 13%
Smoke Detector 100% 30%
ROR 100% 47%
Smoke Duct 100% 0%
Beam Detector 100% 0%
Anounciator 100% 100%

CCTV
Panel CCTV 100% 0%
Camera 100% 0%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


80 | P a g e


B.3. PROGRES RATIFIKASI DEFECT ELEKTRONIK








0%
20%
40%
60%
80%
100%
Sound
System
Fire Alarm CCTV BAS
Ratifikasi 43.9% 54.3% 0% 80.6%
43.9%
54.3%
0%
80.6%
PROGRESS RATIFIKASI DEFECT ELEKTRONIK
SISTEM
JML.
DEFECT
RATIFIKASI SISA %
Sound System 139 61 78 43.9%
Fire Alarm 140 76 64 54.3%
CCTV 30 0 30 0%
BAS 93 75 23 80.6%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


81 | P a g e


B.3.1. DEFECT CHECKLIST PANEL BAS (8 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PANEL BAS CR
B2 s/d Lt. ROOF
Singlw line diagram belum tersedia 17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat 14/12/11
Selesai Belum

Grounding belum tersambung ke pit box CLOSED
Selesai Belum

Cover penutup kabel try belum terpasang 17/12/11
Selesai Belum

Terminasi kabel tidak memkai sepatu
kabel
14/12/11
Selesai Belum


2. PANEL BAS / DOC
B2 ZONA B
Kabel grounding panel tidak tersedia 14/12/11
Selesai Belum

Name tage belum terpasang 14/12/11
Selesai Belum

Single line diagram panel belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat CLOSED
Selesai Belum

EAF belum tersambung 20/12/11
Selesai Belum

SP. 16 tidak ada fasilitas BAS 20/12/11
Selesai Belum

Kabel belum masuk ke electric
pum/jockey pump
19/12/11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


82 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. PANEL BAS/DDC
B2 ZONA A
Single line diagram panel belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat 14/12/11
Selesai Belum

Kabel grounding panel tidak tersedia 14/12/11
Selesai Belum

Name tage belum terpasang 14/12/11
Selesai Belum

Perapihan kabel di panel AC, panel lampu 14/12/11
Selesai Belum

Terminasi kabel di panel AC. Panel
lampu, P lift, tidak memakai kabel skun
CLOSED
Selesai Belum

FA (Filter Alarm belum terpasang 20/12/11
Selesai Belum

Perapihan terminasikabel di panel sumpit CLOSED
Selesai Belum

Panel sumpit No. 3 tidak dilengkapi
dengan ON-OF-TRIP
20/12/11
Selesai Belum


4. PANEL BAS / DDC
UG ZONE B
Kabel grounding panel belum tersedia CLOSED
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel
CLOSED
Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel
CLOSED
Selesai Belum

Name tag/labeling kabel belum terpasang CLOSED
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


83 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Lubang masuk kabel belum tertutup rapat CLOSED
Selesai Belum


5. PANEL BAS / DDC
LT.1 ZONA D
Kabel grounding panel belum tersedia CLOSED
Selesai Belum

Name tag/labeling kabel belum terpasang CLOSED
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat CLOSED
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel
CLOSED
Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel
CLOSED
Selesai Belum


6. PANEL BAS/DDC
LT.3 ZONE B
Kabel grounding panel belum tersedia CLOSED
Selesai Belum

Name tag/labeling kabel belum terpasang CLOSED
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat CLOSED
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel
CLOSED
Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel
CLOSED
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


84 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
7. PANEL BAS/DDC
PANEL LT.
CARREFOUR
Kabel grounding panel belum tersedia
Selesai Belum

Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel

Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum


8. PANEL BAS/DDC
LT. ATAP 1.1
Kabel grounding panel belum tersedia
Selesai Belum

Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line iagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel

Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum


9. PANEL BAS/DDC Kabel grounding panel belum tersedia
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


85 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
LT. ATAP 1.2
Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel

Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum


10. PANEL BAS/DDC
LT. UG ZONA D
Kabel grounding panel belum tersedia
Selesai Belum

Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line diagram belum
terpasang

Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel
17/12/11
Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


86 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
11. PANEL BAS/DDC
LT. GF ZONA D
Kabel grounding panel belum tersedia
Selesai Belum

Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel
17/12/11
Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum


12. PANEL BAS/DDC
LT. GF ZONA A
Kabel grounding panel belum tersedia
Selesai Belum

Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel

Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


87 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
13. PANEL BAS/DDC
LT. UG ZONA A
Kabel grounding panel belum tersedia
Selesai Belum

Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel

Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum


14. PANEL BAS/DDC
LT. GFZONA C
Kabel grounding panel belum tersedia
Selesai Belum

Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line diagram belum
terpasang

Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel

Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


88 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
15. PANEL BAS/DDC
LT. GFZONA B
Kabel grounding panel belum tersedia
Selesai Belum

Name tag/labeling kabel belum terpasang
Selesai Belum

Gambar single line diagram belum
terpasang
17/12/11
Selesai Belum

Lubang masuk kabel belum tertutup rapat
Selesai Belum

Terminasi sebagian tidak memakai sepatu
kabel

Selesai Belum

Install kabel & panel AC tidak memakai
flexible conduit dan kabel tidak memakai
sepatu kabel

Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


89 | P a g e


B.3.2. DEFECT CHECKLIST CCTV (9 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PERALATAN UTAMA
CCTV
B2 S/D LT. ROOF
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Cover penutup kabel belum terpasang 22 Des 11
Selesai Belum


2. PANEL ACCESS
SWITCH
B1 ZONE D
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Perapihan kabel tembus dinding & try 21 Des 11
Selesai Belum


3. PANEL ACCESS
SWITCH
B2 ZONE B
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Perapihan kabel instalasi & try 22 Des 11
Selesai Belum


4. PANEL ACCESS
SWITCH
LG ZONE C
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Perapihan kabel instalasi 21 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


90 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. PANEL ACCESS
SWITCH
LG ZONE D
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Perapihan kabel instalasi & try 22 Des 11
Selesai Belum


6. PANEL ACCESS
SWITCH
LG ZONE A
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Perapihan kabel instalasi & try 22 Des 11
Selesai Belum


7. PANEL ACCESS
SWITCH
GF ZONE B
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Perapihan kabel instalasi & try 22 Des 11
Selesai Belum

Pembuatan posisi camera di Steak 21
Selesai Belum


8. PANEL ACCESS
SWITCH
LT.1 ZONE D
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Perapihan kabel instalasi & try 22 Des 11
Selesai Belum

Lubang masuk kabel belum tertutup rapat 21 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


91 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
9. PANEL ACCESS
SWITCH
LT.1 ZONE A
Kabel grounding belum terpasang 23 Des 11
Selesai Belum

Name plate panel belum ada 21 Des 11
Selesai Belum

Perapihan kabel instalasi & try 22 Des 11
Selesai Belum

Lubang masuk kabel belum tertutup rapat 21 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


92 | P a g e


B.3.3. DEFECT CHECKLIST FIRE ALARM (2 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PANEL MCPFA
B2 S?D LT. ROOF
Grounding MCPFA belum terpasang 14 Des 11
Selesai Belum

Name plate belum tersedia
Selesai Belum

Perapihan panel riser
Selesai Belum

Single line diagram tidak tersedia 17 Des 11
Selesai Belum

Terminasi kabel tidak memakai skun 14 Des 11
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum

UPS belum terpasang 17 Des 11
Selesai Belum

Ruangan panas (perlu penambahan AC)
Selesai Belum


2. TBFA/JBFA
GF ZONE D
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17 Des 11
Selesai Belum

Ruangan tidak dilengkapi smoke detector
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum
By other
Lubang masuk kabel tidak tertutup rapat
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


93 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Shop drawing panel tidak ada
Selesai Belum
By other
3. TBFA/JBFA
GF ZONE B
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Ruangan tidak dilengkapi smoke detector
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum
By other
Lubang masuk kabel tidak tertutup rapat
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum
Tidak ada

4. TBFA/JBFA
UG ZONE C
Grounding panel belum tersedia 14/12/11
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Ruangan tidak dilengkapi smoke detector
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum

Lubang masuk kabel tidak tertutup rapat
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


94 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum


5. TBFA/JBFA
UG ZONE D
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Ruangan tidak dilengkapi smoke detector
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum
By other
Lubang masuk kabel tidak tertutup rapat
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum
Tidak ada

6. TBFA/JBFA
UG ZONE B
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Ruangan tidak dilengkapi smoke detector
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


95 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum
Tidak ada

7. TBFA/JBFA
P2
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Ruangan tidak dilengkapi smoke detector 17/12/11
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum

Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum


8. TBFA/JBFA
LT.1 ZONE B
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Ruangan tidak dilengkapi smoke detector 17/12/11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


96 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Fire Stop tidak tersedia (Riser)
Selesai Belum

Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum


9. TBFA/JBFA
P4
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Ruangan tidak dilengkapi smoke detector 17/12/11
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum

Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum


10. TBFA/JBFA
P6A
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Name tage belum tersedia
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


97 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Perapihan kabel d ipanel 17/12/11
Selesai Belum


11. TBFA/JBFA
LT. 1 ZONE D
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Name tage belum tersedia
Selesai Belum

Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Perapihan kabel d ipanel 20/12/11
Selesai Belum


12. TBFA/JBFA
LT. 1 ZONE C
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Name tage belum tersedia
Selesai Belum

Lubang masuk kabel tidak tertutup rapat
Selesai Belum

Fire Stop
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


98 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
13. TBFA/JBFA
B2 ZONE B
Grounding panel belum tersedia 14/12/11
Selesai Belum

Name plate belum tersedia
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Ruangan tidak dilengkapi smoke detector
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum

Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Kabel-kabel di IHB tidak memakai flexible
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum


14. TBFA/JBFA
B1 ZONE B
Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Name plate belum tersedia
Selesai Belum

Perapihan kabel di riser 17/12/11
Selesai Belum

Fire Stop tidak tersedia (Riser)
Selesai Belum

Terminasi kabel tidak memakai skun
Selesai Belum


15. TBFA/JBFA
LG ZONE D
Grounding belum tersedia
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


99 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Lubang masuk kabel tidak tertutup rapat
Selesai Belum


16. TBFA/JBFA
B2 ZONE D
Grounding belum tersedia
Selesai Belum

Kabel menuju panel tidak menggunakan
tray

Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Lubang masuk kabel tidak tertutup rapat
Selesai Belum

Fire stop belum terpasang
Selesai Belum
Tidak ada shaft
Perapihan kabel di shaft
Selesai Belum


17. TBFA/JBFA
B1 ZONE D
Grounding belum tersedia
Selesai Belum

Kabel menuju panel tidak menggunakan
tray
17/12/11
Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Lubang masuk kabel tidak tertutup rapat 17/12/11
Selesai Belum

Fire stop belum terpasang
Selesai Belum
By other
Perapihan kabel di shaft 17/12/11
Selesai Belum

Name plate 17/12/11
Selesai Belum

Kabel di IHB tidak menggunakan flexible
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


100 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
18. TBFA/JBFA
LT. LG ZONE B
Grounding belum tersedia
Selesai Belum

Kabel menuju panel tidak menggunakan
tray

Selesai Belum

Single line diagram tidak tersedia 17/12/11
Selesai Belum

Lubang masuk kabel tidak tertutup rapat
Selesai Belum

Fire stop belum terpasang
Selesai Belum

Perapihan kabel di shaft 20/12/11
Selesai Belum

Name plate
Selesai Belum

Kabel di IHB tidak menggunakan flexible
Selesai Belum

Penempatan panel terlalu tinggi tidak
sesuai spek/BSN

Selesai Belum
Ruangan terlalu
sempit
Shop drawing tidak ada
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


101 | P a g e


B.3.4. DEFECT CHECKLIST SOUND SYSTEM (2 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. TBSS / JBSS
B1 ZONE B
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 17/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat
17/12/11
Selesai Belum

Fire stop belum terpasang
Selesai Belum


2. TBSS / JBSS
B2 ZONE D
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 17/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


102 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. TBSS / JBSS
B2 ZONE B
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 17/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat
17/12/11
Selesai Belum

Fire stop belum terpasang
Selesai Belum


4. TBSS / JBSS
LG ZONE D
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


103 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. TBSS / JBSS
LG ZONE B
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 17/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum


6. PANEL SOUND
SYSTEM/SYSTEM
MANAGER
B1
Grounding belum terpasang
Selesai Belum

Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun 19/12/11
Selesai Belum

Perapihan kabel di panel/riser
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat
17/12/11
Selesai Belum

Fire stop belum terpasang
Selesai Belum

Shop drawing panel tidak ada
Selesai Belum

Penempatan panel tidak standard,
ruangan terlalu sempit dan juga tidak
memenuhi syarat spek Metakom

Selesai Belum
Ruangan terlalu
sempit
Ruangan panas
Selesai Belum
By other

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


104 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
7. TBSS/JBTS
UG ZONE B
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 17/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat
17/12/11
Selesai Belum

Fire stop belum terpasang
Selesai Belum
By other
Shopdrawing tidak ada
Selesai Belum


8. TBSS/JBTS
UG ZONE D
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 20/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum

Shopdrawing tidak ada
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


105 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
9. TBSS/JBTS
GF ZONE B
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 20/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum

Shopdrawing tidak ada
Selesai Belum


10. TBSS/JBTS
UG ZONE C
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 20/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum
By other
Shopdrawing tidak ada
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


106 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
11. TBSS/JBTS
LT. 1 ZONE B
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 20/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat
17/12/11
Selesai Belum

Fire stop belum terpasang
Selesai Belum

Shopdrawing tidak ada
Selesai Belum


12. TBSS/JBTS
LT. 1 ZONE C
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 17/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum

Shopdrawing tidak ada
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


107 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
13. TBSS/JBTS
LT. 1 ZONE D
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Perapihan kabel di panel/riser 17/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum

Shopdrawing tidak ada
Selesai Belum


14. TBSS/JBTS
B1 ZONE D
Name plate belum tersedia
Selesai Belum

Single line diagram belum, tersedia 17/12/11
Selesai Belum

Terminasi kabel tidak menggunakan skun
Selesai Belum

Cover LSA tidak terpasang
Selesai Belum

Kabel menuju panel tidak memakai tray 20/12/11
Selesai Belum

Lubang masuk kabel pada panel tidak
tertutup rapat

Selesai Belum

Fire stop belum terpasang
Selesai Belum
By other
Shopdrawing tidak ada
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


108 | P a g e


B.3.5. DEFECT TESCOM SOUND SYSTEM (25 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. JBTS
LT. 1 ZONE A
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Single line diagram belum tersedia 17/12/11
Selesai Belum

Set volume/Selector switch 20/12/11
Selesai Belum


2. JBTS
UG ZONE B
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Single line diagram belum tersedia 17/12/11
Selesai Belum

Perbaikan Set volume/Selector switch 20/12/11
Selesai Belum

Perapihan kabel panel di riser 20/12/11
Selesai Belum


3. JBTS
UG ZONE A
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Single line diagram belum tersedia 17/12/11
Selesai Belum

Perbaikan Set volume/Selector switch 20/12/11
Selesai Belum

Perapihan kabel panel di riser 20/12/11
Selesai Belum


4. JBTS
GF ZONE A
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia 17/12/11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


109 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Perbaiki speaker yang tidak berfungsi 17/12/11
Selesai Belum

Single line diagram belum tersedia 20/12/11
Selesai Belum

Perapihan kabel panel/riser 20/12/11
Selesai Belum


5. JBTS
GF ZONE B
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Perbaiki speaker yang tidak berfungsi 20/12/11
Selesai Belum

Single line diagram belum tersedia 17/12/11
Selesai Belum

Perapihan kabel panel/riser 20/12/11
Selesai Belum


6. JBTS
B2 S/D LT. ROOF
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Perbaiki Volume Lt. 1 20/12/11
Selesai Belum

Single line diagram belum tersedia 17/12/11
Selesai Belum

Perbaiki pembagian selector switch 20/12/11
Selesai Belum


7. JBTS
LG ZONE A
Grounding panel belum tersedia
Selesai Belum

Name plate belum tersedia
Selesai Belum

Single line diagram belum tersedia 17/12/11
Selesai Belum

Perbaiki speaker yang tidak berfungsi 20/12/11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


110 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
8. JBTS
LG ZONE A
Grounding panel belum tersedia
Selesai Belum

Perbaikan panel 1 kabel 2 di riser 20/12/11
Selesai Belum

Single line diagram belum tersedia 17/12/11
Selesai Belum

Set volume/selctor switch 20/12/11
Selesai Belum


9. JBTS
LG ZONE B
Grounding panel belum tersedia
Selesai Belum

Name plate panel
Selesai Belum

Single line diagram belum tersedia 17/12/11
Selesai Belum

Perapihan panel
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


111 | P a g e


B.3.6. DEFECT TESCOM BAS (16 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. Panel. AC.IDDC
LG Lt. 1
Wiring diagram belum terpasang 10 Jan 12
Selesai Belum

Shop drawing panel tidak ada 10 Jan 12
Selesai Belum

Status Trip segera diperbaiki 10 Jan 12
Selesai Belum

Fasilitas Trip di panel tidak ada
(PAC.LGB)
10 Jan 12
Selesai Belum

Pastikan panel 2 dapat di auto/remote dari
BAS
4 Jan 12
Selesai Belum


2. PL 1 DDC.PiB
LG P6
Wiring diagram belum terpasang 10 Jan 12
Selesai Belum

Shop drawing panel tidak ada 10 Jan 12
Selesai Belum

PL-P5 tidak bisa di remote dari BAS 3 Jan 12
Selesai Belum

PL-P2 tidak bisa di remote dari BAS 3 Jan 12
Selesai Belum

Pastikan panel-panel dapat di auto/remote
dari BAS
3 Jan 12
Selesai Belum


3. PL/ P.ESC/ DDC
LG L1
Wiring diagram belum terpasang 10 Jan 12
Selesai Belum

Status Trip supaya diperbaiki 10 Jan 12
Selesai Belum

Perbaiki pembacaan Status (ST) dan Trip
(TR)
3 Jan 12
Selesai Belum

Pastikan panel-panel bisa auto / remote 4 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


112 | P a g e


C. MVAC
C.1. STATUS PEKERJAAN MVAC
4 unit Chiller, Cooling Tower, pompa CWP, dan pompa
CHWP, FCU dan AHU sudah dilakukan checklist
peralatan.
Cooling tower, CWP dan CHWP sudah dilakukan
pengetesan.
Mempersiapkan pengetesan untuk 4 unit chiller.
Check bersama ratifikasi defect untuk semua peralatan
MVAC antara NAI, PAKAR, Pengelola dan PP.
Collecting kelengkapan dokumen untuk persiapan Serah
Terima Peralatan.
Training Operator Chiller pihak Trane belum siap
dilaksanakan.
Masih menunggu kesiapan dari subkon untuk melakukan
pekerjaan testing balancing valve di semua sistem AC.
Pemasangan AC di ruang kontrol elektronik akan
ditambah untuk menjaga agar peralatan elektronik dan
suhu ruangan tidak terlalu panas dan terjaga.
Pemasangan akan dilakukan oleh pihak PP.
Panel Motorize belum dipasang yang berlokasi di ruang
Panel Cooling Tower, pemasangan akan dilakukan oleh
pihak Trane.
Pemasangan Inverter AHU akan dikerjakan oleh Trane
dengan target pemasangan 17 Januari 12.
Pengecekan cfm dari AHU akan dilakukan oleh Trane.


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


113 | P a g e


C.2. PROGRES TESCOM MVAC








0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Fan AHU FCU Chiller CHWP Cooling
Tower
CWP
Checklist 100% 100% 100% 100% 100% 100% 100%
Test 85% 80% 100% 0% 100% 100% 100%
85%
80%
100%
0%
100% 100% 100%
PROGRESS TESCOM MVAC
SISTEM
CHECKLIST
(%)
TESTCOM
(%)
KETERANGAN
Fan 100% 85%
AHU 100% 80%
FCU 100% 100% Sudah BA Tescom
Chiller 100% 0%
CHWP 100% 100% Sudah BA Tescom
Cooling Tower 100% 100% Sudah BA Tescom
CWP 100% 100%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


114 | P a g e


C.3. PROGRES RATIFIKASI MVAC











0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Fan AHU FCU Chiller CHWP Cooling
Tower
CWP
Ratifikasi 55% 58% 71% 0% 75% 25% 85%
55%
58%
71%
0%
75%
25%
85%
PROGRESS RATIFIKASI DEFECT MVAC
SISTEM
JML.
DEFECT
RATIFIKASI SISA %
Fan 175 91 84 55%
AHU 236 138 98 58%
FCU 31 22 9 71%
Chiller 21 0 21 0%
CHWP 28 21 7 75%
Cooling Tower 20 5 15 25%
CWP 34 29 5 85%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


115 | P a g e


C.3.1. DEFECT TESCOM FAN
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. IAF B2.01

Panel belum berfungsi 3 Desember 2011
Selesai Belum

Ruang Fan kotor masih ada pekerjaan
sipil
3 Desember 2011
Selesai Belum

Name tag 3 Desember 2011
Selesai Belum

Posisi unit miring gantungan silencer
belum ada
3 Desember 2011
Selesai Belum

Gantungan belum di cat 3 Desember 2011
Selesai Belum

Ruang Fan kotor, masih ada pek. Sipil 3 Desember 2011
Selesai Belum


2. IAF B2.02 Panel belum berfungsi 3 Desember 2011
Selesai Belum

Ruang Fan kotor masih ada pekerjaan
sipil
3 Desember 2011
Selesai Belum

Name tag 3 Desember 2011
Selesai Belum

Posisi unit miring gantungan silencer
belum ada
3 Desember 2011
Selesai Belum

Gantungan belum di cat 3 Desember 2011
Selesai Belum

Ruang Fan kotor, masih ada pek. Sipil 3 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


116 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. EAF B2.01

Velocity EAF B2.01 kebesaran 28 Nopember 2011
Selesai Belum

Ducting masuk ke shaft (bocor) 28 Nopember 2011
Selesai Belum

Name tag untuk unit dan Ruangan 28 Nopember 2011
Selesai Belum

4. EAF B2.02 Velocity EAF B2.01 kebesaran 28 Nopember 2011
Selesai Belum

Name tag untuk unit dan Ruangan 28 Nopember 2011
Selesai Belum


5. EAF B2.03 Velocity kebesaran 1 Desember 2011
Selesai Belum

Gantungan belum di cat 1 Desember 2011
Selesai Belum


6. EAF B2.04 Velocity kebesaran 1 Desember 2011
Selesai Belum

Name tag unit dan ruangan 1 Desember 2011
Selesai Belum


7. EAF B2.05 Velocity kebesaran 1 Desember 2011
Selesai Belum

Name tag unit dan ruangan 1 Desember 2011
Selesai Belum


8. EAF B2.06 Velocity kebesaran 1 Desember 2011
Selesai Belum

Name tag unit dan ruangan 1 Desember 2011
Selesai Belum


9. EAF B2.07 Velocity kebesaran 2 Desember 2011
Selesai Belum

Name tag unit dan ruangan 2 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


117 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
10. EAF B2.08 Name tag unit dan ruangan 2 Desember 2011
Selesai Belum


11. EAF B2.09 Velocity kurang 2 Desember 2011
Selesai Belum

Name tag unit dan ruangan 2 Desember 2011
Selesai Belum


12. EAF B2.10 Velocity kurang 2 Desember 2011
Selesai Belum

Name tag unit dan ruangan 2 Desember 2011
Selesai Belum


13. EAF B2.11 Mesin terjepit tembok 2 Desember 2011
Selesai Belum

Velocity kurang 2 Desember 2011
Selesai Belum

Name tag unit dan ruangan 2 Desember 2011
Selesai Belum


14. EAF B2.12 Mesin terjepit tembok 2 Desember 2011
Selesai Belum

Velocity kurang 2 Desember 2011
Selesai Belum

Name tag unit dan ruangan 2 Desember 2011
Selesai Belum


15. EAF B2.13 Velocity kurang 2 Desember 2011
Selesai Belum

Name tag unit dan ruangan 2 Desember 2011
Selesai Belum


16. EAF B2.14 Velocity kurang 2 Desember 2011
Selesai Belum

Name tag unit dan ruangan 2 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


118 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
17. EAF B1.01 Name tag unit dan ruangan 1 Desember 2011
Selesai Belum


18. EAF B1.02 Velocity kurang 1 Desember 2011
Selesai Belum

Name tag unit dan ruangan 1 Desember 2011
Selesai Belum


19. EAF B1.03 Panel belum berfungsi 28 Nopember 2011
Selesai Belum

Gantungan ducting belum dicat 2 Desember 2011
Selesai Belum

Ducting bocor 2 Desember 2011
Selesai Belum

Damper discharge dipasang masuk ke
dalam shaft
2 Desember 2011
Selesai Belum


20. EAF B1.04 Panel belum berfungsi 28 Nopember 2011
Selesai Belum

Gantungan ducting belum dicat 2 Desember 2011
Selesai Belum

Ducting bocor 2 Desember 2011
Selesai Belum


21. EAF B1.05 Panel belum berfungsi 3 Desember 2011
Selesai Belum

Gantungan ducting belum dicat 3 Desember 2011
Selesai Belum

Ducting bocor 3 Desember 2011
Selesai Belum

Unit mesin dipasang terbalik 3 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


119 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
22. EAF B1.06 Panel belum berfungsi 3 Desember 2011
Selesai Belum

Gantungan ducting belum dicat 3 Desember 2011
Selesai Belum

Ducting bocor 3 Desember 2011
Selesai Belum


23. EAF B1.07 Velocity kurang 3 Desember 2011
Selesai Belum

Name tag unit dan ruangan 3 Desember 2011
Selesai Belum


24. EAF B1.08 Unit fan belum ada 3 Desember 2011
Selesai Belum

Name tag ruangan 3 Desember 2011
Selesai Belum


25. EAF B1.09 Velocity kurang 3 Desember 2011
Selesai Belum

Name tag ruangan 3 Desember 2011
Selesai Belum


26. EAF B1.10 Velocity kurang 3 Desember 2011
Selesai Belum

Name tag ruangan 3 Desember 2011
Selesai Belum


27. EAF B1.11 Gantungan ducting melengkung 5 Desember 2011
Selesai Belum

Velocity kurang 5 Desember 2011
Selesai Belum

Name tag unit dan ruangan 5 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


120 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
28. EAF B1.12 Gantungan ducting melengkung 5 Desember 2011
Selesai Belum

Velocity kurang 5 Desember 2011
Selesai Belum

Name tag unit dan ruangan 5 Desember 2011
Selesai Belum


29. EAF B1.13 Name tag unit dan ruangan 6 Desember 2011
Selesai Belum

Ducting bocor 5 Desember 2011
Selesai Belum

Lampu penerangan belum ada
(temporary)
5 Desember 2011
Selesai Belum


30. EAF B1.14 Name tag unit dan ruangan 6 Desember 2011
Selesai Belum

Ducting bocor 6 Desember 2011
Selesai Belum

Lampu penerangan belum ada
(temporary)
6 Desember 2011
Selesai Belum


31. EAF B1.19 Lokasi unit di R. STP. Kapasitas kurang 1 Desember 2011
Selesai Belum


32. IAE B1.CR.01 Velocity kurang 6 Desember 2011
Selesai Belum

Name tag unit dan ruangan 6 Desember 2011
Selesai Belum


33. EAF LG.FC.01 Manhole tidak ada 6 Desember 2011
Selesai Belum

Name tag belum ada 6 Desember 2011
Selesai Belum

Velocity kelebihan 6 Desember 2011
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


121 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN

34. IAF LG.FC.01 Velocity kelebihan 3 Desember 2011
Selesai Belum


35. EAF LG.FC.02 Name tag unit belum ada 3 Desember 2011
Selesai Belum


36. IAF LG.FC.02 Name tag unit belum ada 3 Desember 2011
Selesai Belum


37. EAF LG.FC.03 Panel belum siap 3 Desember 2011
Selesai Belum


38. IAF LG.FC.03 Name tag unit belum ada 3 Desember 2011
Selesai Belum

Manhole belum ada 3 Desember 2011
Selesai Belum


39. IAF LG.FC.04 Name tag unit belum ada 5 Desember 2011
Selesai Belum

Manhole belum ada 5 Desember 2011
Selesai Belum

Ruang section intake kotor 5 Desember 2011
Selesai Belum

Velocity kurang 5 Desember 2011
Selesai Belum


40. IAF LG.FC.05 Name tag unit belum ada 5 Desember 2011
Selesai Belum

Manhole belum ada 5 Desember 2011
Selesai Belum

Ruang section intake kotor 5 Desember 2011
Selesai Belum

Velocity kurang 5 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


122 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
41. EAF LG.FC.04 Name tag unit belum ada 5 Desember 2011
Selesai Belum

Velocity kurang 5 Desember 2011
Selesai Belum


42. EAF LG.FC.05 Name tag unit belum ada 5 Desember 2011
Selesai Belum

Velocity kurang 5 Desember 2011
Selesai Belum

Kabel grounding mesin tidak rapih 5 Desember 2011
Selesai Belum


43. EAF LG.FC.07 Name tag unit belum ada 6 Desember 2011
Selesai Belum


44. IAF LG.FC.07 Name tag unit belum ada 6 Desember 2011
Selesai Belum


45. SMF LG.01 Name tag unit belum ada 6 Desember 2011
Selesai Belum

Velocity kurang 6 Desember 2011
Selesai Belum


46. SMF LG.02 Name tag unit belum ada 6 Desember 2011
Selesai Belum


47. EAF GF.FC.01 Support unit tidak rapih 7 Desember 2011
Selesai Belum

Velocity kelebihan 7 Desember 2011
Selesai Belum

Tembok masih bolong 7 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


123 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
48. EAF GF.FC.01 Support unit tidak rapih 7 Desember 2011
Selesai Belum

Velocity kelebihan 7 Desember 2011
Selesai Belum

Tembok masih bolong 7 Desember 2011
Selesai Belum


49. SMF GF.01 Velocity kelebihan 7 Desember 2011
Selesai Belum

Manhole tidak ada 7 Desember 2011
Selesai Belum


50. SMF GF.02 Velocity kelebihan 7 Desember 2011
Selesai Belum

Manhole tidak ada 7 Desember 2011
Selesai Belum


51. EAF GF.FC.04 Velocity kelebihan 7 Desember 2011
Selesai Belum

Name tag unit belum ada 7 Desember 2011
Selesai Belum

52. IAF GF.FC.02 Velocity kelebihan 7 Desember 2011
Selesai Belum

Manhole tidak ada 7 Desember 2011
Selesai Belum


53. IAF GF.FC.01A Velocity kelebihan 7 Desember 2011
Selesai Belum

Manhole tidak ada 7 Desember 2011
Selesai Belum


54. IAF GF.FC.03 Velocity kelebihan 8 Desember 2011
Selesai Belum

Manhole tidak ada 8 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


124 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
55. EAF GF.FC.03 Unit mesin belum terpasang 8 Desember 2011
Selesai Belum


56. IAF GF.01 Manhole tidak ada 8 Desember 2011
Selesai Belum

Name tag unit belum ada 8 Desember 2011
Selesai Belum


57. IAF GF.FC.01 Manhole tidak ada 8 Desember 2011
Selesai Belum

Name tag unit belum ada 8 Desember 2011
Selesai Belum


58. IAF UG.01 Panel belum siap 8 Desember 2011
Selesai Belum


59. EAF UG.01 Panel belum siap 8 Desember 2011
Selesai Belum


60. IAF UG.02 Panel belum siap 8 Desember 2011
Selesai Belum


61. EAF L1.01 Velocity kelebihan 8 Desember 2011
Selesai Belum

Name tag unit belum ada 8 Desember 2011
Selesai Belum


62. IAF L1.01 Velocity kelebihan 8 Desember 2011
Selesai Belum


63. IAF L1.02 Plafond belum dipasang 8 Desember 2011
Selesai Belum


64. EAF L1.02 Panel belum danpat difungsikan 8 Desember 2011
Selesai Belum

Name tag unit belum ada 8 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


125 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
65. IAF 3.CH.01 Velocity kelebihan 9 Desember 2011
Selesai Belum


66. EAF 3.07 Velocity kelebihan 9 Desember 2011
Selesai Belum


67. EAF 3.01 Velocity kelebihan 9 Desember 2011
Selesai Belum


68. EAF 3.02 Velocity kelebihan 9 Desember 2011
Selesai Belum


69. EAF 3.05 Velocity kelebihan 10 Desember 2011
Selesai Belum


70. PAF PO.02 Velocity kelebihan 10 Desember 2011
Selesai Belum


71. PAF PO.04 Velocity kelebihan 10 Desember 2011
Selesai Belum


72. PAF PO.03 Velocity kelebihan 10 Desember 2011
Selesai Belum


73. PAF PO.03.01 Velocity kelebihan 10 Desember 2011
Selesai Belum


74. PAF PO.05 Velocity kelebihan 10 Desember 2011
Selesai Belum


75. SMF PO.01 Panel & Kabel power belum terpasang 10 Desember 2011
Selesai Belum


76. IAF G.FC.01 Belum ada manhole 10 Desember 2011
Selesai Belum


77. SMF G.01 / 02 Belum ada manhole 10 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


126 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
78. IAF G.FC Belum ada manhole 10 Desember 2011
Selesai Belum


79. EAF G.FC.03 Belum ada manhole 10 Desember 2011
Selesai Belum


80. IAF G.FC.03 Belum ada manhole 10 Desember 2011
Selesai Belum


81. IAF G.FC.0A Belum ada manhole 10 Desember 2011
Selesai Belum


82. IAF G.FC.05 Belum ada manhole 10 Desember 2011
Selesai Belum


83. IAF G.FC.04 Belum ada manhole 10 Desember 2011
Selesai Belum


84. IAF G.FC.04 Belum ada manhole 10 Desember 2011
Selesai Belum


85. PANEL PAC B2D Bobokan belum tembus 10 Desember 2011
Selesai Belum


86. PANEL PAC B1D Mesin Exhaust Fan mati 10 Desember 2011
Selesai Belum


87. PANEL PAC B2C Mesin Exhaust Fan mati 10 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


127 | P a g e


C.3.2. DEFECT CHECKLIST FAN (22 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
30. EAF-G.FC.1.03 Noise unit Fan sangat keras. 10 Desember 2011
Selesai Belum

Manhole untuk service belum ada. 10 Desember 2011
Selesai Belum

Velosity kelebihan. 10 Desember 2011
Selesai Belum

Name Tag belum ada. 10 Desember 2011
Selesai Belum


31. IAF-UG.02 Name Tag belum ada. 10 Desember 2011
Selesai Belum

Manhole untuk Maintenance belum ada. 10 Desember 2011
Selesai Belum


32. EAF-UG.02 Name Tag belum ada. 10 Desember 2011
Selesai Belum

Manhole untuk Maintenance belum ada. 10 Desember 2011
Selesai Belum


33. IAF-UG.01 Name Tag belum ada. 10 Desember 2011
Selesai Belum


34. EAF-UG.01 Name Tag belum ada. 10 Desember 2011
Selesai Belum

Manhole untuk Maintenance belum ada. 10 Desember 2011
Selesai Belum


35. EAF - 1.03 Name Tag belum ada. 10 Desember 2011
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


128 | P a g e


C.3.3. DEFECT CHECKLIST AHU & FCU B2 & B1
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. AHU B2.02A

Pemasangan Thernometer mepet dengan
pipa inlet water chiller
23 Des 11
Selesai Belum

Motorize Valve belum disambung
Selesai Belum


2. FCU B2.03 Gantungan support belum di cat. 22 Des 11
Selesai Belum

Motorize Vale belum dipasang -
Selesai Belum
Tidak ada di point BAS
Gantungan pipa drain lepas 22 Des 11
Selesai Belum

Ducting supply belum disambung 22 Des 11
Selesai Belum

Isolasi pipa CHWP lepas/rusak 23 Des 11
Selesai Belum


3. AHU B2.01A Pemasangan Thermometer salah 23 Des 11
Selesai Belum

Motorize Vale belum dipasang
Selesai Belum

Mesih AHU terjepit tembok 23 Des 11
Selesai Belum

Manhole tidak dapat dibuka 23 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


129 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
4. AHU B2.01B Gantungan/support belum dicat 22 Des 11
Selesai Belum

Motorize Vale belum dipasang 20 Des 11
Selesai Belum

Diffuser udara keluar kecil (6 unit)
Selesai Belum

Mesih AHU terjepit tembok 23 Des 11
Selesai Belum

Manhole tidak dapat dibuka 23 Des 11
Selesai Belum

5. FCU B2.02 Motorize valve belum disambung -
Selesai Belum
Tidak ada di point BAS
Gantungan/support belum di cat 22 Des 11
Selesai Belum

Isolasi pipa water chiller return
terkelupas/rusak
23 Des 11
Selesai Belum


6. AHU B2.02B Motorize valve belum disambung 20 Des 11
Selesai Belum

Elivasi pipa drain kurang bagus sehingga
drain dapat mengakibatkan mampet/banjir
22 Des 11
Selesai Belum


7. AHU B2.03 Elivasi pipa drain kurang bagus sehingga
drain dapat mengakibatkan mampet/banjir
22 Des 11
Selesai Belum

Ducting return menggangu manhole
mesin
24 Des 11
Selesai Belum


8. AHU B1.01A Pintu manhole plenum duct return tidak
dipasang pengunci, agar waktu
operasional tidak terangkat.
23 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


130 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
9. AHU B1.01B Gantungan plenum tidak berfungsi 24 Des 11
Selesai Belum

Pintu manhole plenum duct return tidak
dipasang pengunci, agar waktu
operasional tidak terangkat.
23 Des 11
Selesai Belum

Valve untuk Pressure Gauge belum
dipasang
22 Des 11
Selesai Belum

Main pipa CHWP tidak dipasang U bolt 28 Des 11
Selesai Belum

10. AHU B1.01C Gantungan lenum tidak berfungsi 24 Des 11
Selesai Belum

Pintu manhole plenum duct return tidak
dipasang pengunci, agar waktu
operasional tidak terangkat.
23 Des 11
Selesai Belum

Valve untuk Pressure Gauge belum
dipasang
22 Des 11
Selesai Belum

Main pipa CHWP tidak dipasang U bolt 28 Des 11
Selesai Belum

Posisi ducting return menggangu pada
saat service dan maintenance
24 Des 11
Selesai Belum

Ducting return tidak sesuai gambar (terlalu
kecil)

Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


131 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
11. AHU B1.01D Pintu manhole plenum duct return tidak
dipasang pengunci, agar waktu
operasional tidak terangkat.
23 Des 11
Selesai Belum


12. AHU B1.02A Motorize terjepit pipa bypass 23 Des 11
Selesai Belum

Hanger support unit kepanjangan 23 Des 11
Selesai Belum

Rubber mounting belum dipasang 23 Des 11
Selesai Belum

Manhole tidak ada -
Selesai Belum
Menunggu keputusan
VO
Duct supply/return belum dipasang -
Selesai Belum
Di hold oleh MK
Banyak sampah diatas ducting 22 Des 11
Selesai Belum

Sensor temperature belum dipasang 27 Des 11
Selesai Belum

13. AHU B1.02B Hanger support unit kepanjangan 23 Des 11
Selesai Belum

Rubber mounting belum dipasang 23 Des 11
Selesai Belum

Manhole tidak ada -
Selesai Belum
Menunggu keputusan
VO
Duct supply/return belum dipasang -
Selesai Belum
Di hold oleh MK
Banyak sampah diatas ducting 22 Des 11
Selesai Belum

Sensor temperature belum dipasang 27 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


132 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
14. AHU B1.02C Hanger support unit kepanjangan 23 Des 11
Selesai Belum

Rubber mounting belum dipasang 23 Des 11
Selesai Belum

Manhole tidak ada -
Selesai Belum
Menunggu keputusan
VO
Duct supply/return belum dipasang -
Selesai Belum
Di hold oleh MK
Banyak sampah diatas ducting 22 Des 11
Selesai Belum

Sensor temperature belum dipasang 27 Des 11
Selesai Belum


15. AHU B1.02D Hanger support unit kepanjangan 23 Des 11
Selesai Belum

Rubber mounting belum dipasang 23 Des 11
Selesai Belum

Manhole tidak ada -
Selesai Belum
Menunggu keputusan
VO
Duct supply/return belum dipasang -
Selesai Belum
Di hold oleh MK
Banyak sampah diatas ducting 22 Des 11
Selesai Belum

Sensor temperature belum dipasang 27 Des 11
Selesai Belum

36. FCU B1.07 Motorize valve belum disambung -
Selesai Belum
Tidak ada di point BAS
Isolasi pipa CHWP return rusak 24 Des 11
Selesai Belum

Bak drain kotor dengan isolasi pipa 24 Des 11
Selesai Belum

Tembok untuk masuk ducting tidak rapih 26 Des 11
Selesai Belum

Gantungan/support belum di cat 23 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


133 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN

37. FCU B1.05 Motorize valve belum disambung -
Selesai Belum
Tidak ada di point BAS
Bak drain kotor dengan isolasi pipa 24 Des 11
Selesai Belum

Gantungan/support belum di cat 23 Des 11
Selesai Belum

Plenum duct retur belum dipasang 27 Des 11
Selesai Belum


38. FCU B1.06 Gantungan/support belum dibaut ke unit
dan mounting belum di pasang
23 Des 11
Selesai Belum

Ducting plenum return manhole belum
dipasang
27 Des 11
Selesai Belum

Gantungan duct lepas 23 Des 11
Selesai Belum

Hanger support unit kepanjangan 23 Des 11
Selesai Belum


39. FCU B1.08 Motorize valve belum disambung -
Selesai Belum
Tidak ada di point BAS
Gantungan/support belum di cat 23 Des 11
Selesai Belum

Push button panel rusak
Selesai Belum

Manhole di Plenum duct tidak ada 28 Des 11
Selesai Belum


40. FCU B1.09 Motorize valve belum disambung -
Selesai Belum
Tidak ada di point BAS
Gantungan/support belum di cat 23 Des 11
Selesai Belum

Manhole di Plenum duct tidak ada 28 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


134 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
41. FCU B1.10 Kabel power belum ditarik 19 Des 11
Selesai Belum

Manhole terlalu kecil -
Selesai Belum
Tidak ada di point BAS

42. FCU B1.11 Manhole terlalu kecil -
Selesai Belum
Tidak ada di point BAS


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


135 | P a g e


C.3.4. DEFECT CHECKLIST AHU LG
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. AHU LG.10 Penempatan alat control filter tidak rapih 27 Des 11
Selesai Belum

Thermometer pecah, dan pemasangan
terlalu dalam sehingga tertimbun isolasi
pipa
28 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Isolasi pipa tidak rapih 24 Des 11
Selesai Belum

Kabel power motorize tidak rapih 28 Des 11
Selesai Belum

Inverter rusak diterminasi power -
Selesai Belum
TRANE
Ducting plenum bocor 26 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak ada 28 Des 11
Selesai Belum

Balancing valve terpasang valve biasa
(tidak sesuai dengan shop drawing)
-
Selesai Belum


2. AHU LG.11 Valve untuk Pressure Gauge tidak ada 28 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Pemasangan control filter alarm tidak kuat 27 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak ada 28 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


136 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. AHU LG.12 Penempatan alat control filter tidak
kuat/rapih
27 Des 11
Selesai Belum

Thermometer pecah, dan pemasangan
terlalu dalam sehingga tertimbun isolasi
pipa
28 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Isolasi pipa tidak rapi/bersihkan 24 Des 11
Selesai Belum


4. AHU LG.01 Isolasi pipa pada valve tidak rapih 24 Des 11
Selesai Belum

Socket untuk thermometer & pressure
gauge berkarat
28 Des 11
Selesai Belum

Name tag di AHU belum ada -
Selesai Belum
TRANE
Diatas plenum duct supply banyak
sampah/kotor
27 Des 11
Selesai Belum

Alat control filter alarm terpasang tidak
rapi
27 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak ada 28 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


137 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. AHU LG.08 Isolasi pipa pada valve tidak rapih 24 Des 11
Selesai Belum

Socket untuk Thermostat dan Pressure
Gauge berkarat
28 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Sambungan kabel power motorize tidak
rapih
28 Des 11
Selesai Belum

Volume dumper pada duct supply isolasi
lepas/rusak
29 Des 11
Selesai Belum

Diatas plenum duct supply kotor, kabel
tidak rapih
29 Des 11
Selesai Belum


6. AHU LG.09 Plenum duct bagian atas bergelembung 29 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Valve u pressure gauge tidak dipasang 28 Des 11
Selesai Belum

Sambungan kabel power motorize tidak
rapi
27 Des 11
Selesai Belum

Balancing valve belum terpasang -
Selesai Belum

Alat control Filter alarm tidak rapi &
kendor
27 Des 11
Selesai Belum

Support main pipa CHWP untuk AHU di
ganjal kayu
28 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


138 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
7. AHU LG.01 Valve untuk Pressure Gauge belum ada 28 Des 11
Selesai Belum

Control filter alarm terpasang tidak rapid
an kendor
27 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Kabel power AHU diatas ducting tidak
menggunakan tray kabel
-
Selesai Belum

Tanggul pintu ruangan belum dipasang -
Selesai Belum


8. AHU LG.02 Valve untuk Pressure Gauge belum ada 28 Des 11
Selesai Belum

Control filter alarm terpasang tidak rapid
an kendor
27 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Lantai ruangan rusak -
Selesai Belum

Kabel power AHU diatas ducting tidak
menggunakan tray kabel
-
Selesai Belum

Plenum duct support melengkung 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


139 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
9. AHU LG.03 Valve untuk Pressure Gauge belum ada 28 Des 11
Selesai Belum

Control filter alarm terpasang tidak rapid
an kendor
27 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Isolasi flexible duct AHU lepas 29 Des 11
Selesai Belum

Kabel power AHU diatas ducting tidak
menggunakan tray kabel
-
Selesai Belum

Plenum duct support melengkung 29 Des 11
Selesai Belum


10. AHU LG.04 Valve untuk Pressure Gauge belum ada 28 Des 11
Selesai Belum

Control filter alarm terpasang tidak rapid
an kendor
27 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Kabel power AHU diatas ducting tidak
menggunakan tray kabel
-
Selesai Belum

Plenum duct support melengkung 30 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


140 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
11. AHU LG.05 Valve untuk Pressure Gauge belum ada 28 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Kabel power motorize tidak rapih 27 Des 11
Selesai Belum

Ducting dari AHU ke Plenum duct supply
bocor
30 Des 11
Selesai Belum

Di atas plenum duct suplly kondisi kotor, 30 Des 11
Selesai Belum


12. AHU LG.06 Valve untuk Pressure Gauge belum ada 28 Des 11
Selesai Belum

U Trap digabung (agar dipisah) 29 Des 11
Selesai Belum

Kabel power motorize tidak rapih 27 Des 11
Selesai Belum

Control filter alarm terpasang tidak rapih
dan kendor
27 Des 11
Selesai Belum

Main pipa drain untuk unit AHU diganjal
batu (tidak sesuai spek)
28 Des 11
Selesai Belum

Pintu -
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


141 | P a g e


C.3.5. DEFECT CHECKLIST AHU GF
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. AHU GF.07

U Trap drain digabung 30 Des 11
Selesai Belum

Drain dari AHU bocor 30 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

Kabel power motorize tidak rapi 28 Des 11
Selesai Belum


2. AHU GF.08 U Trap drain digabung 30 Des 11
Selesai Belum

Drain dari AHU bocor (tidak di lem) 30 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

Kabel power motorize tidak rapi 28 Des 11
Selesai Belum

Body AHU kotor bekas isolasi pipa 26 Des 11
Selesai Belum

Ruangan AHU kotor
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


142 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. AHU GF.09 U Trap drain digabung 30 Des 11
Selesai Belum

Drain dari AHU bocor (tidak di lem) 30 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

Kabel power motorize tidak rapi 28 Des 11
Selesai Belum

Body AHU kotor bekas isolasi pipa 26 Des 11
Selesai Belum

Ruangan AHU kotor
Selesai Belum


4. AHU GF.01 U Trap drain digabung 30 Des 11
Selesai Belum

Isolasi pipa tidak rapi & kotor 26 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

Kabel power motorize tidak rapi 28 Des 11
Selesai Belum

Kabel power dari panel ke inventer tidak
rapih
-
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


143 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. AHU GF.02 U Trap drain digabung 30 Des 11
Selesai Belum

Isolasi Flexible duct ke plenum duct
supply rusak
30 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

Kabel power motorize tidak rapi 28 Des 11
Selesai Belum

Kabel power dari panel ke inventer tidak
rapih
-
Selesai Belum


6. AHU GF.03 Damper pada duct supply tidak diisolasi 30 Des 11
Selesai Belum

Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

U Trap drain digabung 30 Des 11
Selesai Belum

Body unit AHU kotor bekas isolasi pipa 26 Des 11
Selesai Belum

7. AHU GF.04 Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

U Trap drain digabung 30 Des 11
Selesai Belum

Drain dari AHU bocor 30 Des 11
Selesai Belum

Body unit AHU kotor bekas isolasi pipa 26 Des 11
Selesai Belum

Ruangan AHU kotor -
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


144 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
8. AHU GF.05 Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

U Trap drain digabung 30 Des 11
Selesai Belum

Drain dari AHU bocor 30 Des 11
Selesai Belum

Body unit AHU kotor bekas isolasi pipa 26 Des 11
Selesai Belum

Ruangan AHU kotor -
Selesai Belum

Kabel power motorize tidak rapih 28 Des 11
Selesai Belum


9. AHU GF.06 Valve untuk Pressure Gauge tidak
dipasang
29 Des 11
Selesai Belum

U Trap drain digabung 30 Des 11
Selesai Belum

Drain dari AHU bocor 30 Des 11
Selesai Belum

Body unit AHU kotor bekas isolasi pipa 26 Des 11
Selesai Belum

Ruangan AHU kotor -
Selesai Belum

Kabel power motorize tidak rapih 28 Des 11
Selesai Belum






MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


145 | P a g e


C.3.6. DEFECT CHECKLIST AHU (22 & 23 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. AHU-GF.10 U trap drain digabung salah, harus
dipasang di tiap unit AHU
31 Des 11
Selesai Belum

Unit AHU dan Inverter kotor. 26 Des 11
Selesai Belum

Elivasi ruangan tidak bagus lantai masih
banjir / menggenang.
31 Des 11
Selesai Belum

Planum duct supply AHU tidak rapi. 31 Des 11
Selesai Belum

Kabel power motorize valve tidak rapi. 30 Des 11
Selesai Belum

Valve u/ Pressure Gauge belum dipasang 31 Des 11
Selesai Belum

Lantai ruang AHU berlubang. 31 Des 11
Selesai Belum


2. AHU-GF.11 U-trap drain digabung salah, harus
dipasang di tiap unit AHU.
31 Des 11
Selesai Belum

Unit AHU dan Inverter kotor. 26 Des 11
Selesai Belum

Elivasi ruangan tidak bagus lantai masih
banjir / menggenang.
31 Des 11
Selesai Belum

Planum duct supply AHU tidak rapi. 31 Des 11
Selesai Belum

Kabel power motorize valve tidak rapi. 30 Des 11
Selesai Belum

Valve u/ Pess.gauge belum dipasang. 31 Des 11
Selesai Belum

Lantai ruang AHU berlobang. 31 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


146 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. AHU-GF.12 U-trap drain digabung salah, harus
dipasang di tiap unit AHU.
31 Des 11
Selesai Belum

Unit AHU dan Inverter kotor. 26 Des 11
Selesai Belum

Elivasi ruangan dipasang bagus lantai
masih banjir / menggenang.
31 Des 11
Selesai Belum

Planum duct supply AHU dipasang rapi. 31 Des 11
Selesai Belum

Kabel power motorize valve dipasang rapi. 30 Des 11
Selesai Belum

Valve untuk Pressure gauge belum
dipasang.
31 Des 11
Selesai Belum

Lantai ruang AHU berlubang. 31 Des 11
Selesai Belum


4. AHU-UG.04 Body AHU kotor bekas isolasi pipa. 27 Des 11
Selesai Belum

Kabel power motorize tidak rapi. 31 Des 11
Selesai Belum

U-trap drain digabung salah, harus di
pasang tiap unit.
2 Jan 12
Selesai Belum

Support CHWP untuk AHU dicat tidak
rata.
29 Des 11
Selesai Belum

Diatas AHU dan Planum duct banyak
sampah / kotor material bekas.
29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


147 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. AHU-UG.05 Plenum duct supply turun / melengkung
membebani AHU (support kurang).
3 Jan 12
Selesai Belum

U-trap drain digabung salah tidak sesuai
spek kebutuhan AHU, harus dipasang
setiap unit.
2 Jan 12
Selesai Belum

Support pipa CHWP untuk AHU di cat
tidak rata / kurang rapi.
29 Des 11
Selesai Belum

Diatas AHU & Planum duct supply banyak
sampah material bekas.
29 Des 11
Selesai Belum


6. AHU-UG.06 Socket untuk pasang Thermometer terlalu
tinggi, penunjukkan sekala thermo meter
tidak akurat.
31 Des 11
Selesai Belum

Kabel power motorize tidak rapi. 31 Des 11
Selesai Belum

U-trap drain digabung salah tidak sesuai
spek kebutuhan AHU, harus dipasang
setiap unit.
2 Jan 12
Selesai Belum

Diatas AHU & Plenum duct supply kotor
banyak sampah sisa material.
29 Des 11
Selesai Belum


7. AHU-UG.01 Isolasi/Jacketing pipa Inlet / 0ut let ke
AHU tidak rapi.
28 Des 11
Selesai Belum

Body AHU kotor bekas isolasi pipa 28 Des 11
Selesai Belum

Besi siku penguat plenum duct supply
belum di cat.
27 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


148 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Pressure gauge pecah & thermometer
inlet kependam isolasi.
30 Des 11
Selesai Belum


8. AHU-UG.02 Diatas planum duct supply kotor banyak
sampah material bekas.
28 Des 11
Selesai Belum

Body AHU kotor bekas isolasi pipa. 28 Des 11
Selesai Belum

Planum duct supply bocor. 2 Jan 12
Selesai Belum

Isolasi pada pipa tempat motorize di
pasang tidak rapi.
31 Des 11
Selesai Belum

Gantungan/support pipa CHWP klem U-
Bolt tidak dipasang.
27 Jan 11
Selesai Belum


9. AHU-UG.03 Penampang/Depan Pressure Gauge &
thermometer inlet/outlet pipa CHWP tidak
searah, sulit untuk membaca sekala.
29 Des 11
Selesai Belum

Di atas Plenum duct supply banyak
sampah / kotor material bekas.
28 Des 11
Selesai Belum

Bila AHU-UG.03 dimatikan noise
/bergetar.
-
Selesai Belum


10. AHU-L1.08 U-trap drain digabung salah, tidak sesuai
spek kebutuhan AHU, harus dipa
dipasang per unit.
3 Jan 12
Selesai Belum

Di atas AHU & Plenum duct supply kotor
banyak sampah material bekas.
29 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


149 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Planum duct supply bocor pada sudut
penyambungan.
30 Des 11
Selesai Belum


11. AHU-L1.05 U-trap drain digabung, tidak sesuai spek
kebutuhan AHU, harus dipasang per unit.
3 Jan 12
Selesai Belum

Di atas AHU & Plenum duct supply kotor
banyak sampah material bekas.
28 Des 11
Selesai Belum

Body AHU kotor bekas isolasi pipa. 27 Des 11
Selesai Belum

Gantungan/support pipa belum dicat
bekas las.
27 Des 11
Selesai Belum


12. AHU-L1.04 U-trap drain digabung salah, tidak sesuai
spek kebutuhan AHU, harus dipa
dipasang per unit
3 Jan 12
Selesai Belum

Di atas AHU & Plenum duct supply kotor
banyak sampah material bekas.
28 Des 12
Selesai Belum

Body AHU kotor bekas isolasi pipa. 27 Des 11
Selesai Belum

Support pipa pengecatan tidak rata &
bekas las belum dicat.
27 Des 11
Selesai Belum


13. AHU-L1.01 U-trap drain digabung salah,tidak sesuai
spek kebutuhan AHU, harus dipasang per
unit.
3 Jan 12
Selesai Belum

Di atas unit AHU kotor material sisa. 28 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


150 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
14. AHU-L1.02 U-trap drain digabung salah, tidak sesuai
spek kebutuhan AHU, harus dipasang per
unit
3 Jan 12
Selesai Belum

Plenum duct supply rusak / bocor. 31 Des 11
Selesai Belum

Di atas unit AHU kotor sampah material
bekas & botol Aqua bekas
28 Des 11
Selesai Belum

Planum duct supply bocor pada sudut
penyambungan.
31 Des 11
Selesai Belum


15. AHU-L1.03 U-trap drain digabung salah, tidak sesuai
spek kebutuhan AHU, harus dipa sang per
unit.
3 Jan 12
Selesai Belum

Penampang Pressure gauge & thermo
meter tidak searah sulit untuk baca skala.
30 Des 11
Selesai Belum

Planum duct supply rusak / bocor. 31 Des 11
Selesai Belum

Diatas unit AHU kotor & kabel berantakan. 28 Des 11
Selesai Belum


16. AHU Carrefour Man hole di plenum duct Return belum
ada untuk kebutuhan cek / maintenance.
4 Jan 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


151 | P a g e


C.3.7. DEFECT CHECKLIST & TEST POMPA CHWP (16 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. CHWP- Pump No.1 Body pompa tidak di isolasi/kondensasi. 5 Jan 12
Selesai Belum

Suara mekanik pompa waktu running
keras.
6 Jan 12
Selesai Belum

Box Terminasi lobang yg tidak difungsikan
harus ditutup sapaya air & kotoran tidak
masuk.
21 Des 11
Selesai Belum

Pada penampungan tetesan ari dari
mekanik seal pompa tidak dipasang pipa /
slang supaya air tidak berantakan waktu
seal bocor.
-
Selesai Belum

Kabel power dari tray ke motor pompa
tidak di protek bahaya tutup tray dari seng
tajam.
31 Des 11
Selesai Belum

Name Tag /tanda arah panah u/ sirkulasi
air belum di pasang pada pipa CHWP &
CWP.
29 Des 11
Selesai Belum


2. CHWP- Pump No.2 Body pompa tidak di isolasi/kondensasi. 5 Jan 12
Selesai Belum

Box Terminasi lobang yg tidak difungsikan
harus ditutup sapaya air & kotoran tidak
masuk.
21 Des 11
Selesai Belum

Pada penampungan tetesan ari dari
mekanik seal pompa tidak dipasang pipa /
slang supaya air tidak berantakan waktu
seal bocor.
-
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


152 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Kabel power dari tray ke motor pompa
tidak di protek bahaya tutup tray dari seng
tajam.
31 Des 11
Selesai Belum

Name Tag /tanda arah panah u/ sirkulasi
air belum di pasang pada pipa CHWP &
CWP.
29 Des 11
Selesai Belum


3. CHWP- Pump No.3 Body pompa tidak di isolasi/kondensasi. 5 Jan 12
Selesai Belum

Box Terminasi lobang yg tidak difungsikan
harus ditutup sapaya air & kotoran tidak
masuk.
21 Des 11
Selesai Belum

Pada penampungan tetesan ari dari
mekanik seal pompa tidak dipasang pipa /
slang supaya air tidak berantakan waktu
seal bocor.
-
Selesai Belum

Kabel power dari tray ke motor pompa
tidak di protek bahaya tutup tray dari seng
tajam.
31 Des 11
Selesai Belum

Name Tag /tanda arah panah u/ sirkulasi
air belum di pasang pada pipa CHWP &
CWP.
29 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


153 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
4. CHWP- Pump No.4 Body pompa tidak di isolasi/kondensasi. 6 Jan 12
Selesai Belum

Box Terminasi lobang yg tidak difungsikan
harus ditutup sapaya air & kotoran tidak
masuk.
21 Des 11
Selesai Belum

Pada penampungan tetesan ari dari
mekanik seal pompa tidak dipasang pipa /
slang supaya air tidak berantakan waktu
seal bocor.
-
Selesai Belum

Kabel power dari tray ke motor pompa
tidak di protek bahaya tutup tray dari seng
tajam.
3 Jan 12
Selesai Belum

Name Tag /tanda arah panah u/ sirkulasi
air belum di pasang pada pipa CHWP &
CWP
29 Des 11
Selesai Belum


5. CHWP- Pump No.5 Body pompa tidak di isolasi/kondensasi. 6 Jan 12
Selesai Belum

Box Terminasi lobang yg tidak difungsikan
harus ditutup sapaya air & kotoran tidak
masuk.
21 Des 11
Selesai Belum

Pada penampungan tetesan ari dari
mekanik seal pompa tidak dipasang pipa /
slang supaya air tidak berantakan waktu
seal bocor.
-
Selesai Belum

Kabel power dari tray ke motor pompa
tidak di protek bahaya tutup tray dari seng
tajam.
3 Jan 12
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


154 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Name Tag /tanda arah panah u/ sirkulasi
air belum di pasang pada pipa CHWP &
CWP.
29 Des 11
Selesai Belum

Arus / Ampere pd grounding terlalu besar
4,7 Amp harus dibawah 0,5.
3 Jan 12
Selesai Belum

Pressure gauge u/ discharge pompa tidak
di pasang.
29 Des 11
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


155 | P a g e


C.3.8. DEFECT CHECKLIST DAN TEST POMPA CWP (15 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. CWP- Pump No.1 Pemasangan Pressure gauge suction
salah harus dipasang sebelum Strainer.
-
Selesai Belum
Sudah kesepakatan
bersama dengan
pengelola
Suara mekanik pompa waktu running
keras kondisi di VSD freq 50.
6 Jan 12
Selesai Belum

Pada penampungan tetesan air dari
mekanik Seal tidak dipasang pipa / slang
supaya air tidak berantakan ke lantai jika
mekanik Seal bocor.
-
Selesai Belum

Box Terminasi power pompa lubang yang
tidak difungsikan harus ditutup supaya air
/ kotoran tidak masuk
21 Des 11
Selesai Belum

Baut / Mur pengunci kedudukan pompa
degan pondasi kendor
29 Des 11
Selesai Belum

Panel penutup MCCB dari achrilik tidak
ada
31 Des 11
Selesai Belum

Kabel power pompa dari Tray ke motor
pompa tidak diprotek tutup tray dari seng
tajam
31 Des 11
Selesai Belum

Name Tag/tanda arah panah u/sirkulasi
air pada pipa CHWP & CWP belum ada
29 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


156 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
2. CWP- Pump No.2 Pemasangan Pressure gauge suction
salah harus dipasang sebelum Strainer
-
Selesai Belum

Suara mekanik pompa waktu run ning
keras kondisi di VSD freq 50.
Pada penampungan tetesan air dari
mekanik Seal tidak dipasang pi pa / slang
supaya air tidak beranta kan ke lantai
jika mekanik Seal bo cor.
6 Jan 12
Selesai Belum

Box Terminasi power pompa lo bang yg
tidak difungsikan harus di tutup spy air /
kotoran tidak masuk.
21 Des 11
Selesai Belum

Baut / Mur pengonci kedudukan pompa
dgn pondasi kendor.
29 Des 11
Selesai Belum

Panel penutup Mccb dari achrilik tidak ada 31 Des 11
Selesai Belum

Panel kotor 29 Des 11
Selesai Belum

Name Tag/tanda arah panah u/sirkulasi
air pada pipa CHWP & CWP belum
dipasang.
29 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


157 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. CWP- Pump No.3 Pemasangan Pressure gauge suction
salah harus dipsng sebelum Strainer.
-
Selesai Belum

Suara mekanik pompa waktu run ning
keras kondisi di VSD freq 50.
8 Jan 12
Selesai Belum

Pada penampungan tetesan air dari
mekanik Seal tidak dipasang pi pa / slang
supaya air tidak beranta kan ke lantai
jika mekanik Seal bo cor.
-
Selesai Belum

Box Terminasi power pompa lo bang yg
tidak difungsikan harus di tutup spy air /
kotoran tidak masuk.
21 Des 11
Selesai Belum

Baut / Mur pengonci kedudukan pompa
dgn pondasi kendor.
29 Des 11
Selesai Belum

Disply panel fluktuasi/tidak normal. 3 Jan 12
Selesai Belum

Panel kotor. 29 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


158 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
4. CWP- Pump No.4 Pemasangan Pressure gauge suction
salah harus dipsng sebelum Strainer.
-
Selesai Belum

Suara mekanik pompa waktu run ning
keras kondisi di VSD freq 50.
8 Jan 11
Selesai Belum

Pada penampungan tetesan air dari
mekanik Seal tidak dipasang pi pa / slang
supaya air tidak beranta kan ke lantai
jika mekanik Seal bo cor.
-
Selesai Belum

Box Terminasi power pompa lo bang yg
tidak difungsikan harus di tutup spy air /
kotoran tidak masuk.
Baut / Mur pengonci kedudukan pompa
dgn pondasi kendor.
21 Des 11
Selesai Belum

Name Tag/tanda arah panah u/sirkulasi
air pada pipa CHWP & CWP belum
dipasang.
29 Des 11
Selesai Belum

Panel kotor 29 Des 11
Selesai Belum


5. CWP- Pump No.5 Pemasangan Pressure gauge suction
salah harus dipsng sebelum Strainer.
-
Selesai Belum

Suara mekanik pompa waktu run ning
keras kondisi di VSD freq 50.
8 Jan 12
Selesai Belum

Pada penampungan tetesan air dari
mekanik Seal tidak dipasang pi pa / slang
supaya air tidak beranta kan ke lantai
jika mekanik Seal bocor.
-
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


159 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Box Terminasi power pompa lo bang yg
tidak difungsikan harus di tutup spy air /
kotoran tidak masuk.
21 Des 11
Selesai Belum

Baut / Mur pengonci kedudukan pompa
dgn pondasi kendor.
29 Des 11
Selesai Belum

Name Tag/tanda arah panah u/sirkulsi air
belum dipasang pd pipa CHWP & CWP.
29 Des 11
Selesai Belum


6. Dosing Pump Piping untuk dosing pump tidak rapih -
Selesai Belum

Penerangan area dosing pump -
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


160 | P a g e


C.3.9. DEFECT CHECKLIST COOLING TOWER (15 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. Cooling Tower 01 Kabel power u/ Fan cooling Tower tdk
rapi, sebagian pada masuk ke Basin inlet
Cooling Tower / kerendam air (bagian
atas CT).
30 Des 11
Selesai Belum

Kabel power motorize valve belum di tarik. -
Selesai Belum

Name Tag u/ Cooling Tower belum ada. 29 Des 11
Selesai Belum

Name Plate di Cooling Tower tidak ada. 3 Jan 12
Selesai Belum


2. Cooling Tower 02 Kabel power u/ Fan cooling Tower tdk
rapi, sebagian pada masuk ke Basin inlet
Cooling Tower / kerendam air (bagian
atas CT).
30 Des 11
Selesai Belum

Kabel power motorize valve belum di tarik. -
Selesai Belum

Name Tag u/ Cooling Tower belum ada. 29 Des 11
Selesai Belum

Name Plate di Cooling Tower tidak ada. 3 Jan 12
Selesai Belum


3. Cooling Tower 03 Basin bag.atas pinggir dekat filler retak /
perbaiki
3 Jan 12
Selesai Belum

Kabel power u/ Fan cooling tower tdk rapi,
sebagian pada masuk ke Basin inlet
Cooling Tower / kerendam air ( di bagian
atas CT ).
30 Des 11
Selesai Belum

Ganjal kedudukan Cooling Tower dgn 24 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


161 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
pondasi sebagian belum dilepas.
Motorize valve belum ditarik kabel control. -
Selesai Belum

Name Tag Cooling tower belum ada. 29 Des 11
Selesai Belum

Name plate Cooling Tower tadak ada. 3 Jan 12
Selesai Belum


4. Cooling Tower 04 Basin bag.atas pinggir dekat filler retak /
perbaiki
3 Jan 12
Selesai Belum

Kabel power u/ Fan cooling tower tdk rapi,
sebagian pada masuk ke Basin inlet
Cooling Tower / kerendam air ( di bagian
atas CT ).
30 Jan 11
Selesai Belum

Ganjal kedudukan Cooling Tower dgn
pondasi sebagian belum dilepas.
24 Des 11
Selesai Belum

Motorize valve belum ditarik kabel control. -
Selesai Belum

Name Tag Cooling tower belum ada. 29 Des 11
Selesai Belum

Name plate Cooling Tower tadak ada. 3 Jan 12
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


162 | P a g e


C.3.10. DEFECT CHECKLIST CHILLER (16 DESEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. Chiller 01 Pemasangan Flow Switch Evaporator
terpen dam isolasi / casing pipa CHWP.
29 Des 11
Selesai Belum

Motorize valve u/ Condenser & Evaporator
untuk Chiller kabel power belum
disambung.
-
Selesai Belum

Name Tag Kurang jelas / besar dan rapi. 29 Des 11
Selesai Belum

Lebeling u/pipa Condenser dan
Evaporator pada Chiller.
29 Des 11
Selesai Belum

Panel Stater Chiller penyok -
Selesai Belum


2. Chiller 02 Name Tag kurang jelas / besar dan rapi. 29 Des 11
Selesai Belum

Pemasangan Flow Switch Evaporator
terpen dam isolasi / casing pipa CHWP.
29 Des 11
Selesai Belum

Motorize valve u/ Condenser & Evaporator
pada Chiller kabel power belum
disambung.
-
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


163 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
3. Chiller 03 Name Tag kurang jelas / besar dan rapi. 29 Des 11
Selesai Belum

Pemasangan Flow Switch Evaporator
terpen dam isolasi / casing pipa CHWP.
29 Des 11
Selesai Belum

Motorize valve u/ Condenser & Evaporator
pada Chiller kabel power belum
disambung.
-
Selesai Belum

Posisi Condenser dgn tembok dekat sulit
untuk melapsanakan service Condenser.
-
Selesai Belum

Pemasangan valve Press.gauge out let
keda lam isolasi pipa.
30 Des 11
Selesai Belum


4. Chiller 04 Name Tag kurang jelas / besar dan rapi. 29 Des 11
Selesai Belum

Pemasangan Flow Switch Evaporator
terpen dam isolasi / casing pipa CHWP.
29 Des 11
Selesai Belum

Motorize valve u/ Condenser & Evaporator
pada Chiller kabel power belum
disambung.
-
Selesai Belum

Posisi Condenser dgn tembok dekat sulit
untuk melapsanakan service Condenser.
-
Selesai Belum

Pemasangan valve Press.gauge out let
keda lam isolasi pipa.
30 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


164 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
5. Motorize balancing Header supply/ return
belum ditarik kabel power
-
Selesai Belum






MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


165 | P a g e


D. PLUMBING
D.1. STATUS PEKERJAAN PLUMBING
Pengecekan dan pengetesan sumpit
Perbaikan gutter untuk mencegah masuknya sampah ke
dalam Sumpit Carrefour, perbaikan gutter oleh pihak PP.
Pengecekan pada unit toilet
Test Lab akan terbit hasilnya 3 bulan mendatang..
Intake Fan sudah dipasang dan sudah di Tescom, namun
perapihan lubang dinding belum di kerjakan oleh PP.
Beita Acara Tecom STP sudah di terbitkan dengan
catatan Test Lab dan Lubang dinding Intake Fan di
abaikan (tidak menunggu selesai).
Check ratifikasi defect bersama peralatan plumbing.
Ground Water Tank sudah dilakukan Tescom.
Water Level Indicator sudah dipasang oleh pihak PP.


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


166 | P a g e


D.2. PROGRES TESCOM PLUMBING









0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
GAS Sewage Sumpit Deepwell STP Toilet
Checklist 100% 100% 100% 100% 100% 100%
Test 100% 100% 100% 100% 100% 100%
PROGRESS TESCOM PLUMBING
SISTEM
CHECKLIST
(%)
TESTCOM
(%)
KETERANGAN
GAS 100% 100%
Sewage 100% 100%
Sumpit 100% 100%
Deepwell 100% 100%
STP 100% 100% Sudah BA Tescom
Toilet 100% 100%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


167 | P a g e


D.3. PROGRES RATIFIKASI PLUMBING











0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
STP Deep
well
Groun
d Tank
R.
Pomp
a
P.
Transf
er
Water
Hamm
er
Roof
Tank
P.
Boost
er
Toilet Sumpi
t
Checklist 71.40% 66.70% 100% 0% 83.30% 100% 77.80% 40% 0% 71.40%
71.40%
66.70%
100%
0%
83.30%
100%
77.80%
40%
0%
71.40%
PROGRESS RATIFIKASI DEFECT PLUMBING
SISTEM
JML.
DEFECT
RATIFIKASI SISA %
STP 7 5 2 71.4%
Deepwell 3 2 1 66.7%
Ground Tank 4 4 0 100%
R. Pompa 2 0 2 0%
P. Transfer 6 5 1 83.3%
Water Hammer 1 1 0 100%
Roof Tank 9 7 2 77.8%
P. Booster 5 2 3 40%
Toilet 1 0 1 0%
Sumpit 7 5 2 71.4%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


168 | P a g e


D.3.1. DEFECT CHECKLIST INSTALASI GAS (8 NOPEMBER 2011)
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PANEL CONTROL GAS
DETECTOR
GF ZONE B
Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perbaiki penempatan MCB di panel 28 Nop 11
Selesai Belum

UPS tidak tersedia 28 Nop 11
Selesai Belum


2. PANEL CONTROL GAS
DETECTOR
LG
Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perbaiki penempatan Relay 28 Nop 11
Selesai Belum

Perapihan panel 28 Nop 11
Selesai Belum


3. PANEL CONTROL GAS
DETECTOR
UG ZONE C
Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perbaiki penempatan Relay 28 Nop 11
Selesai Belum

UPS belum terpasang 28 Nop 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


169 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
4. PANEL CONTROL GAS
DETECTOR
LT. 1 ZONE B
Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perbaiki penempatan Relay 28 Nop 11
Selesai Belum

UPS tidak tersedia 28 Nop 11
Selesai Belum


5. PANEL CONTROL GAS
DETECTOR
LT. 1 ZONE C
Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perbaiki penempatan Relay 28 Nop 11
Selesai Belum

UPS tidak tersedia 28 Nop 11
Selesai Belum


6. PANEL CONTROL GAS
DETECTOR
UG ZONE B
Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perapihan panel 28 Nop 11
Selesai Belum

Name plate/labeling belum ada 28 Nop 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


170 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
7. PANEL CONTROL GAS
DETECTOR
GF
Ruangan tidak dilengkapi smoke detector 28 Nop 11
Selesai Belum

Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perapihan panel 28 Nop 11
Selesai Belum

Name plate/labeling belum ada 28 Nop 11
Selesai Belum

UPS tidak tersedia 28 Nop 11
Selesai Belum


8. PANEL CONTROL
MCPFA
B1 S/D LT. 2
Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perapihan panel 28 Nop 11
Selesai Belum

Name plate/labeling belum ada 28 Nop 11
Selesai Belum


9. PANEL GAS
DETECTOR
LG ZONE D
Single line diagram belum terpasang 28 Nop 11
Selesai Belum

Grounding panel 28 Nop 11
Selesai Belum

Perapihan kabel di panel 28 Nop 11
Selesai Belum

Name plate/labeling belum ada 28 Nop 11
Selesai Belum

Perbaiki posisi penempatan relay 28 Nop 11
Selesai Belum


10. VAPORIZER Vaporizer 1 dan 3 tidak berfungsi -
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


171 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
11. RUANG GAS Tidak dilengkapi smoke detector 28 Nop 11
Selesai Belum

Proteksi ventilasi -
Selesai Belum


12. INSTALASI Single line diagram belum dilengkapi 28 Nop 11
Selesai Belum

Perapihan relai dan instalasi 28 Nop 11
Selesai Belum


D.3.2. DEFECT CHECKLIST STP
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
43. STP Exhaust Fan tidak sesuai 22 Des 11
Selesai Belum

Tidak ada instalasi air bersih 16 Des 11
Selesai Belum

Test Lab 15 Des 11
Selesai Belum

Rongga di intake fan 15 Des 11
Selesai Belum

Jalur pipa perlu perapihan 15 Des 11
Selesai Belum

Pressure Gauge 15 Des 11
Selesai Belum

Cabang salah satu diffuser rusak 15 Des 11
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


172 | P a g e


D.3.3. DEFECT CHECKLIST STP
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
44. DEEPWELL Kabel tidak rapih 9 Des 11
Selesai Belum

Aksesories pompa belum terpasang 9 Des 11
Selesai Belum

Marking arah aliran 9 Des 11
Selesai Belum

Name tag valve 9 Des 11
Selesai Belum

D.3.4. DEFECT CHECKLIST GROUND TANK
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
45. GROUND TANK Water Level Indicator tidak tersedia 9 Des 11
Selesai Belum

Penerangan di ground tank
Selesai Belum

Pipa over flow 9 Des 11
Selesai Belum

Name tag 9 Des 11
Selesai Belum

D.3.5. DEFECT RUANG POMPA
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
46. RUANG POMPA Detector fire belum tersedia 9 Des 11
Selesai Belum

Kabel tidak dipasang menggunakan kabel
duct
9 Des 11
Selesai Belum




MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


173 | P a g e


D.3.6. DEFECT POMPA TRANSFER
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
47. POMPA TRANSFER Sisi Inlet tidak terpasang Pressure Gauge 16 Des 11
Selesai Belum

Pemipaan belum diberi arah aliran 16 Des 11
Selesai Belum

Name tag 16 Des 11
Selesai Belum

Panel control cover belakang belum
terpasang

Selesai Belum
By Elekttrik
Automatic air vent belum ada 16 Des 11
Selesai Belum

Pondasi pompa belum di cor
Selesai Belum

D.3.7. DEFECT WATER HAMMER
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
48. WATER HUMMER Tidak tersedia jalur bypass dari drain 19 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


174 | P a g e


D.3.8. DEFECT ROOF TANK
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
49. ROOF TANK Nameplate capasitas belum ada 9 Desember 2011
Selesai Belum

Kabel WLC tidak rapih 9 Desember 2011
Selesai Belum

WLC tank sisi B tidak berfungsi
Selesai Belum

Water Level Indicator tidak tersedia 9 Desember 2011
Selesai Belum

Screen Ventilasi tidak ada 9 Desember 2011
Selesai Belum

Pipa overflow disambung ke pipa
distribusi Carrefour

Selesai Belum

Marking arah aliran 9 Desember 2011
Selesai Belum

Name tag 9 Desember 2011
Selesai Belum

Roof Tank Cooling tower belum selesai 9 Desember 2011
Selesai Belum
By VAC
D.3.9. DEFECT POMPA BOOSTER
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
50. RUANGAN BOOSTER
PUMP
Tidak tersedia Automatic Air Vent 17 Des 11
Selesai Belum

Tidak tersedia Pressure Gauge 17 Des 11
Selesai Belum

Name tag 17 Des 11
Selesai Belum


51. POMPA BOOSTER Kabel tidak rapih 9 Des 11
Selesai Belum
By Elektrik
Single line diagram tidak ada 9 Des 11
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


175 | P a g e


D.3.10. DEFECT TOILET
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
52. TOILET Tidak dilengkapi dengan Clean Out di
toilet wanita GF
17 Des 11
Selesai Belum

D.3.11. DEFECT SUMPIT
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
53. SUMPIT Check valve 2,3,4,5,7,17 & 19
Selesai Belum

Check valve 18 & 21 9 Des 11
Selesai Belum

Panel sumpit Inlet/Outlet kabel tidak di
sealant / tertutup rapat/ fire stop
20 Des 11
Selesai Belum

Sumpit No. 14 terdapat rembesan besar
air tanah
9 Des 11
Selesai Belum
BY SIPIL
Sumpit no 16 rusak dan panel kosong 9 Des 11
Selesai Belum

Pipa drain FF tidak masuk pit (sumpit No.
19)
9 Des 11
Selesai Belum

Semua lantai sumpit masih banyak puing 9 Des 11
Selesai Belum
By SIPIL





MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


176 | P a g e


E. FIRE FIGHTING
E.1. STATUS PEKERJAAN FIRE FIGHTING
Peralatan fire fighting sudah dilakukan checklist peralatan,
namun peralatan pemadam kebakaran atau fire fighting system
belum dapat dilakukan tescom, dikarenakan seting PRV belum
menuju kata sepakat. Hal ini sudah dibicarakan oleh pihak
konsultan desain.

E.2. PROGRES TESCOM FIRE FIGHTING








0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Pompa
Fire
IHB OHB Siamese Pillar
Hydrant
BCV
Checklist 100% 100% 100% 100% 100% 100%
Test 0% 0% 0% 0% 0% 0%
100% 100% 100% 100% 100% 100%
0% 0% 0% 0% 0% 0%
PROGRESS TESCOM FIRE FIGHTING
SISTEM
CHECKLIST
(%)
TESTCOM
(%)
KETERANGAN
Pompa Fire 100% 0%
IHB 100% 0%
OHB 100% 0%
Siamese 100% 0%
Pillar Hydrant 100% 0%
BCV 100% 0%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


177 | P a g e


E.3. PROGRES RATIFIKASI FIRE FIGHTING






0%
20%
40%
60%
80%
100%
FF
Ratifikasi 67%
67%
PROGRESS RATIFIKASI DEFECT FIRE FIGHTING
SISTEM
JML.
DEFECT
RATIFIKASI SISA %
Fire Fighting 6 4 2 66.7%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


178 | P a g e


D.3.1. DEFECT CHECKLIST FIRE FIGHTING
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. PERALATAN FIRE
FIGHTING
Accessories Hydrant belum lengkap 9 Des 11
Selesai Belum

Accessories yang hilang 9 Des 11
Selesai Belum

Name tag 16 Des 11
Selesai Belum

PRV belum dibuka 15 Des 11
Selesai Belum

Pondasi tangki solar belum di cor 16 Des 11
Selesai Belum

Temper Switch belum di connect ke
MCFA
19 Des 11
Selesai Belum






MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


179 | P a g e


F. TRANSPORTASI GEDUNG
F.1. STATUS PEKERJAAN TRANSPORTASI GEDUNG
Acrylic pada Lift Service 06 belum tersedia. Pihak Hyundai
akan mendatangkan item tersebut secepatnya.
Kondisi pit Lift Service 06 masih ada rembesan air dari
lantainya, dan akan diperbaiki oleh PP (Civil).
Escalator 46 unit defect sudah closed dan B.A Tescom
sudah diterbitkan, sisa 2 unit yang belum siap operasi.
Travelator 8 unit defect sudah closed dan B.A Tescom
sudah diterbitkan.
Pengecekan defect bersama PP, PAKAR, NAI dan
Pengelola.
46 unit Escalator dalam proses BAST-1.
8 unit Travelator dalam proses BAST-1.
Gondola hingga saat ini belum siap dilakukan Tescom
(informasi by owner).


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


180 | P a g e


F.2. PROGRES TESCOM TRANSPORTASI GEDUNG






0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Escalator Travelator Lift Gondola
Checklist 100% 100% 100% 0%
Test 100% 100% 100% 0%
100% 100% 100%
0%
PROGRESS TESCOM TRANSPORTASI GEDUNG
SISTEM
CHECKLIST
(%)
TESTCOM
(%)
KETERANGAN
Escalator 100% 100% 2 unit belum opr.
Travelator 100% 100%
Lift 100% 100%
gondola 0% 0%

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


181 | P a g e


F.3. PROGRES RATIFIKASI TRANSPORTASI GEDUNG








0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Escalator Travelator Lift Gondola
Ratifikasi 100% 100% 66.70%
100%
100%
66.70%
PROGRESS RATIFIKASI DEFECT
TRANSPORTASI GEDUNG
SISTEM
JML.
DEFECT
RATIFIKASI SISA %
Escalator 33 33 0 100%
Travelator 10 10 0 100%
Lift 45 30 15 66.7%
Gondola 0 0 0 -

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


182 | P a g e


F.3.1. DEFECT TESCOM ESCALATOR & TRAVELATOR
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. ESCALATOR 17 Grounding kabel belum ada 9 Desember 2011
Selesai Belum

Elevasi lantai kurang rata 12 Desember 2011
Selesai Belum


2. ESCALATOR 18 Grounding kabel belum ada 9 Desember 2011
Selesai Belum

Elevasi lantai kurang rata 12 Desember 2011
Selesai Belum


3. ESCALATOR 20 Step lamp bagian atas tidak ON 12 Desember 2011
Selesai Belum


4. ESCALATOR 33 Oli kurang 12 Desember 2011
Selesai Belum


5. ESCALATOR 34 Oli kurang 12 Desember 2011
Selesai Belum


6. ESCALATOR 35 Oli kurang 12 Desember 2011
Selesai Belum


7. ESCALATOR 36 Oli kurang 12 Desember 2011
Selesai Belum


8. ESCALATOR 37 Oli kurang 12 Desember 2011
Selesai Belum


9. ESCALATOR 38 Oli kurang 12 Desember 2011
Selesai Belum


10. ESCALATOR 08 Overlaping test (10cm) 16 Desember 2011
Selesai Belum


11. ESCALATOR 14 Step lamp bagian bawah tidak ON 16 Desember 2011
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


183 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
12. ESCALATOR 10 Step lamp bagian bawah tidak ON 9 Desember 2011
Selesai Belum


13. ESCALATOR 25 Ampere hunting (bermasalah) 16 Des 12
Selesai Belum

Noise (berbunyi) 16 Des 12
Selesai Belum

Overlapping test (23 cm) 16 Des 12
Selesai Belum


14. ESCALATOR 41 Overlapping test (13 cm) 16 Des 12
Selesai Belum


15. ESCALATOR 43 Setting econo rusak 16 Des 12
Selesai Belum

16. Cover safety brush kiri bawah tidak ada 16 Des 12
Selesai Belum


17. ESCALATOR 44 Ampere hunting (bermasalah) 16 Des 12
Selesai Belum


18. TRAVELATOR 01 Overlapping test (14 cm) 16 Des 12
Selesai Belum


19. TRAVELATOR 02 Overlapping test (13 cm) 16 Des 12
Selesai Belum


20. TRAVELATOR 03 Handrail guard switch kanan & kiri atas
agar di setting ulang
16 Des 12
Selesai Belum

Overlapping test (15 cm) 16 Des 12
Selesai Belum


21. TRAVELATOR 04 Handrail guard switch kanan atas &
bawah agar di setting ulang
16 Des 12
Selesai Belum

Handrail cacat 16 Des 12
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


184 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
22. TRAVELATOR 05 Overlapping test (50 cm) 9 Des 12
Selesai Belum


23. TRAVELATOR 06 Overlapping test (29 cm) 16 Des 12
Selesai Belum

24. TRAVELATOR 07 Overlapping test (200 cm) 7 Desember 2011
Selesai Belum


25. TRAVELATOR 07 Overlapping test (35 cm) 16 Desember 2011
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


185 | P a g e


F.3.2. DEFECT CHECKLIST ELEVATOR
NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
1. Lift Panoramic Panel power tidak rapih
Selesai Belum
Lingkup PP
Dinding belum tertutup sempurna
Selesai Belum
Lingkup PP
Atap ruang mesin cacat (melendut)
Selesai Belum
Lingkup PP
Lubang laluan sling tidak dilengkapi
dengan tanggulan /pelindung
5 Jan 12
Selesai Belum

Pipa AC tembus dinding tidak di sealant 29 Nop 11
Selesai Belum

Tidak tersedia lampu emergency
Selesai Belum
Lingkup PP
Tidak tersedia APAR
Selesai Belum
Lingkup PP
Tidak tersedia fire detector
Selesai Belum
Lingkup PP
kabel tidak lengkap 28 Des 11
Selesai Belum

Tidak tersedia hook mesin
Selesai Belum
Lingkup PP
Lubang laluan sling tidak rapih 28 Des 11
Selesai Belum

Pemasangan baut pada beam tidak
kencang/ tidak dilangkapi dengan ring per

Selesai Belum

Safety reel atas sangkar tidak melingkupi
semua area maintrance

Selesai Belum

Kabel limit switch tidak dilengkapi conduit
Selesai Belum

Pit belum dilengkapi dengan tangga
Selesai Belum

Kabel door switch tidak dilengkapi conduit
Selesai Belum


MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


186 | P a g e


NO UNIT ITEM DEFECT TARGET PENYELESAIAN KETERANGAN
Lampu pit tidak menyala 28 Nop 11
Selesai Belum

Sling belum dada penanda level 1 Jan 12
Selesai Belum

Mounting outdoor unit tidak terpasang
Selesai Belum

Posisi indoor AC berada di panel listrik 29 Nop 11
Selesai Belum

Kabel tidak rapi/tidak menggunakan duct 16 Des 11
Selesai Belum


2. Lift Service No.2 Laluan sling car belum ditutup 12 Des 11
Selesai Belum

Sling belum dada penanda level 28 Nop 11
Selesai Belum

Safety reel atas sangkar tidak melingkupi
semua area maintrance
30 Nop 11
Selesai Belum

Pipa AC tembus dinding tidak di sealant 28 Nop 11
Selesai Belum

Coran buffer retak 14 Desember 2011
Selesai Belum

Lantai pit belum di water proofing
Selesai Belum


3. Lift Passenger No.5 Shaft belum selesai (masih bolong)
Selesai Belum

Pengecatan di Separator Beam belum
selesai

Selesai Belum

Lantai entrance belum selesai
Selesai Belum

Lantai pit belum di water proofing
Selesai Belum



MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


187 | P a g e


F.4. LIST BERITA ACARA TRANSPORTASI GEDUNG
ESCALATOR
No. Unit No. BA TESCOM Tgl. Penerbitan Melayani Void
ESCALATOR 1
144/SK/ME-NAI/TC/XII/11 17-Dec-11 B1 - LG 4
ESCALATOR 2
ESCALATOR 3
142/SK/ME-NAI/TC/XII/11 17-Dec-11 LG - GF 4
ESCALATOR 4
ESCALATOR 5
141/SK/ME-NAI/TC/XII/11 17-Dec-11 Entrance Timur - LG 6
ESCALATOR 6
ESCALATOR 7
160/SK/ME-NAI/TC/XII/11 27-Dec-11 Entrance Timur - GF 6
ESCALATOR 8
ESCALATOR 9
143/SK/ME-NAI/TC/XII/11 17-Dec-11 B2 - B1 2
ESCALATOR 10
ESCALATOR 11
151/SK/ME-NAI/TC/XII/11 17-Dec-11 Entrance Selatan - LG 7
ESCALATOR 12
ESCALATOR 13
155/SK/ME-NAI/TC/XII/11 21-Dec-11 Entrance Selatan - GF 7
ESCALATOR 14
ESCALATOR 15
150/SK/ME-NAI/TC/XII/11 17-Dec-11 Entrance Selatan - GF 7
ESCALATOR 16
ESCALATOR 17
153/SK/ME-NAI/TC/XII/11 21-Dec-11 B2 - B1 3
ESCALATOR 18
ESCALATOR 19
149/SK/ME-NAI/TC/XII/11 17-Dec-11 B1 -LG 3
ESCALATOR 20
ESCALATOR 21
152/SK/ME-NAI/TC/XII/11 21-Dec-11 LG - GF 3
ESCALATOR 22
ESCALATOR 23
153/SK/ME-NAI/TC/XII/11 21-Dec-11 B2 - B1 3
ESCALATOR 24
ESCALATOR 25
170/SK/ME-NAI/TC/I/12 9-Jan-12 UG - L1 3
ESCALATOR 26
ESCALATOR 27
167/SK/ME-NAI/TC/I/12 5-Jan-12 L1 - L2 2
ESCALATOR 28
ESCALATOR 29
175/SK/ME-NAI/TC/I/12 10-Jan-12 L2 - L3 2
ESCALATOR 30
ESCALATOR 31
148/SK/ME-NAI/TC/XII/11 17-Dec-11 LG - GF 8
ESCALATOR 32
ESCALATOR 33
147/SK/ME-NAI/TC/XII/11 17-Dec-11 B2 - B1 1
ESCALATOR 34
ESCALATOR 35
146/SK/ME-NAI/TC/XII/11 17-Dec-11 B1 - LG 1
ESCALATOR 36
ESCALATOR 37
145/SK/ME-NAI/TC/XII/11 17-Dec-11 B1 - LG 1
ESCALATOR 38

MONTHLY REPORT TESTING & COMMISSIONING TANGCITY MALL
PERIODE 15 DESEMBER 2011 16 J ANUARI 2012


188 | P a g e


ESCALATOR 41
159/SK/ME-NAI/TC/XII/11 27-Dec-11 GF - UG 9
ESCALATOR 42
ESCALATOR 43
169/SK/ME-NAI/TC/I/12 5-Jan-12 UG - L1 9
ESCALATOR 44
ESCALATOR 45
158/SK/ME-NAI/TC/XII/11 27-Dec-11 L1 - L2 9
ESCALATOR 46
ESCALATOR 47
174/SK/ME-NAI/TC/XII/11 11-Jan-12 L2 - L3 9
ESCALATOR 48

TRAVELATOR
No. Unit No. BA TESCOM Tgl. Penerbitan Melayani Void
TRAVELATOR 1
161/SK/ME-NAI/TC/XII/11 27-Dec-11 B1 - LG 2
TRAVELATOR 2
TRAVELATOR 3
171/SK/ME-NAI/TC/I/12 6-Jan-12 UG - GF 2
TRAVELATOR 4
TRAVELATOR 5
166/SK/ME-NAI/TC/I/12 5-Jan-12 GF - UG 2
TRAVELATOR 6
TRAVELATOR 7
168/SK/ME-NAI/TC/I/12 5-Jan-12 UG - L1 7
TRAVELATOR 8