Activity ID Activity Name Original

Duration
Remaining
Duration
BL1 Early
Start
Actual Start Total
Float
Free
Float
C110 Grade Site 3 0 01-Mar-12 01-Mar-12
C120 Procure Forms 7 0 03-Mar-12 03-Mar-12
C130 Excavate Pads 4 0 05-Mar-12 05-Mar-12
C140 Site Work 8 8 19-Mar-12 0 0
C150 Pad Footings 8 0 08-Mar-12 08-Mar-12
C160 Bored Pile F... 5 2 06-Mar-12 06-Mar-12 0 0
C170 Slabs on Gr... 6 6 17-Mar-12 1 0
C180 Columns 2 2 23-Mar-12 1 0
C190 Roof Slab 12 12 25-Mar-12 1 1
C200 Finishes 15 15 23-Mar-12 0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
7
Day
Grade Site
Procure Forms
Excavate Pads
Site Work
Pad Footings
Bored Pile Fdns
Slabs on Grade
Columns
Roof Slab
Finishes
ID Standard Activity Status 21-Mar-12 15:46
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Charbel El Helou
P6 , 2.) A.)
Page 1 of 1
Date Revision Checked Approved
21-Mar-12 00... P6 , 2.) A.) Charbel El He...
Activity
ID
Activity Name Original
Duration
Remaining
Duration
BL1 Early
Start
Actual Start Total
Float
Free
Float
C120 Procure Forms 7 0 03-Mar-12 03-Mar-12
C160 Bored Pile F... 5 2 06-Mar-12 06-Mar-12 0 0
C170 Slabs on Gr... 6 6 17-Mar-12 1 0
C180 Columns 2 2 23-Mar-12 1 0
C190 Roof Slab 12 12 25-Mar-12 1 1
C200 Finishes 15 15 23-Mar-12 0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
Day
Procure Forms
Bored Pile Fdns
Slabs on Grade
Columns
Roof Slab
Finishes
ID Standard Activity Status 21-Mar-12 15:26
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Charbel El Helou
P6 , 2.) b.)
Page 1 of 1
Date Revision Checked Approved
21-Mar-12 00... P6 , 2.) b.) Charbel El He...