Sub : Consent for starting construction activities for 33kV substation SS2 at Marjan Island
Dear Sir,
Once the due diligence has started in Dec13, construction work at SS2 is under hold . The project is becoming critical now as construction work at Pacific and Santorini reports is in full swing and is likely to be completed by beginning of next year. Both of them are our customers with connected load application of 21 MW and we are supplying temporary power to them. We cannot fulfill their demand next year with existing cable network , which consist of 2 X 3core 300 sqmm 11kV Al XLPE cable. Therefore, kindly accord your consent to mobilize the consultant and ask contractor to start the work so that the substation can be commissioned by end of this year.