Adopting Concept
Design
Schem.
Design
Design
Dev.
Tend.
Doc
Concept design
Data collection Yes
Traffic circulation study Yes
Assess traffic types Yes
Best practice discussions Yes
Approx. Space allocation for elevator cores Yes
Meeting & Support-2 Mnths Yes
Schematic Design
Population charts and stacking diagram Yes
Design criteria identification Yes
Traffic analysis, passenger elevators Yes
Traffic study results discussions Yes
Elevator core plan dimension details Yes
Elevator shaft vertical dimension details Yes
Schematic Design report Yes
Meeting & Support-2 Mnths Yes
Design Development
Implement client comments Yes
MEP, structure, ELV Design coordination Yes
Interior Design coordination Yes
Machinery space details [MRL lifts] Yes
Machinery space details [MR above lifts] Yes
Elevator technical summary spread sheet Yes
Detail Design report Yes
Review DD Arch. Drawings Yes
Meeting & Support-2 Mnths Yes
Tender Documents
Implement Client comments Yes
Full length specs Yes
Review TD Arch. Drawings Yes
Meeting & Support-2 Mnths Yes


Contact: Samson Babu, Technical Director
Mobile: 00971507689545



Review existing specification & drawings.
Issue full submittal required list, agree on time schedule Yes
Review technical submittals & report Yes
Review layout shop drawings & report Yes
Cab interior/fixture drawings review & report Yes
Approval of interior fit out vendors, comments only Yes
Material sample approval & report Yes
Review handing over documentation: Site data, 3rd party certicates,
warranty certificates, O&M Manuals Yes
Review QA/QC documentation, interface management plans Yes
Provide coordination recommendations for other engineering disciplines Yes
Provide technical support for the project's duration, answer queries [directly
related to elevators] by the main contractor. Yes
Optional Site Inspection Services
On-site meetings for technical submittals, shop drawings, sample approvals
& Report. Yes
On-site inspections for mock-ups, progress inspections, final inspections
& Report Yes
Material delivery inspections & Report Yes
Installation progress inspections & Report Yes
CTU [Construction Time Use] lifts inspection & Report Yes
Final performance inspection, in full working condition & Report Yes
Construction Supervision Tasks