You are on page 1of 143

TERRITORIAL COOPERATION OBJECTIVE

FINANCIAL MANAGEMENT HANDBOOK


March 2007
2

INTERACT is financed by the European
Regional Development Fund (ERDF)
Financial Management Handbook

3
This handbook is for information only. It is not designed to replace the regulations, which
remain the only binding legal text. The views contained in this document are those of the
authors and the Managing Authority of the INTERACT programme is in no way liable for any
use made of the information contained herein.
This handbook has been written to accompany the INTERACT training seminars on financial
management originally developed by INTERACT Point Qualification and Transfer in
Denmark. It aims to cover all the most common procedures and questions relating to the
financial management of Territorial Cooperation programmes and projects and give insights
into how the regulations are implemented in practice.
We would like to thank the European Commission DG Regional Policy for commenting on the
content of this handbook and recommending changes.
We would also like to thank the many programmes and projects from all strands of
INTERREG and from across Europe who contributed their expertise, documents and time.
Finally we would like to thank the participants of all previous financial management seminars,
whose opinions and questions have been invaluable in further developing the content of the
handbook.
INTERACT Point Qualification and Transfer
January 2007
INTERACT Point Qualification and Transfer
Jernabengade, 22
DK 8800 Viborg
t: (+45) 87 27 10 85, f: (+45) 86 60 16 80
ip.qt@interact-eu.net
www.interact-eu.net
Financial Management Handbook
4
Financial Management Handbook
5
Contents
Glossary...................................................................................................................... 7
Introduction ............................................................................................................... 11
Note on terminology and abbreviations..................................................................... 14
Main abbreviations used in the text........................................................................... 14
Different rules for new Member States 2007 2013................................................. 15
1. The programme cycle in Territorial Cooperation programmes.............................. 16
1.1 Key Financial Activities in the programme lifecycle......................................... 16
1.2 Key challenges in Territorial Cooperation programmes .................................. 18
1.3 Quality targets for key activities....................................................................... 19
2. Start up phase: Programme level.......................................................................... 21
2.1 Key elements to support financial activities (2007 2013) ............................. 21
2.2 Key points in developing programme management structures ....................... 22
2.3 Programme management bodies.................................................................... 23
2.3.1 The Monitoring Committee and the Member States................................. 23
2.3.2 The Steering Committee .......................................................................... 25
2.3.3 The Managing Authority ........................................................................... 26
2.3.4 The Joint Technical Secretariat................................................................ 28
2.3.5 The Paying Authority / Certifying Authority............................................... 29
2.3.7 Intermediate Bodies ................................................................................. 32
2.3.8 Audit Authority.......................................................................................... 34
2.4 The responsibility chain................................................................................... 35
2.5 The main programme documents ................................................................... 36
2.5.1 The Operational Programme (OP) ........................................................... 36
2.5.2 The Description of Management and Control Systems............................ 37
2.5.3 Memoranda of Understanding between the programme and the Member
States ................................................................................................................ 39
2.5.4 Project contracts and partnership agreements......................................... 39
2.6 The need for strong cooperation between management bodies..................... 40
2.7 Staff and Training............................................................................................ 42
2.8 From systems to start-up................................................................................. 43
3. Financial framework.............................................................................................. 44
3.1 Sources and uses of programme funds .......................................................... 44
3.1.1 ERDF........................................................................................................ 44
3.1.2 Pre-financing or the programme advance payment ................................. 46
3.1.3 Co-financing (or match-funding)............................................................... 46
3.1.3 Private co-financing.................................................................................. 48
3.1.4 Own contribution ...................................................................................... 49
3.1.5 Letters of Commitment ............................................................................. 50
3.2 Programme financial tables............................................................................. 51
3.3 Priorities and measures .................................................................................. 53
3.4 ERDF grant rates in the new period 2007 2013........................................... 54
3.5 The Technical Assistance (TA) budget ........................................................... 58
3.6 Additional Administration Tools....................................................................... 61
3.6.1 Bank accounts.......................................................................................... 61
3.6.2 Interest on programme accounts.............................................................. 61
3.6.3 Monitoring systems .................................................................................. 62
3.6.4 More on the Business Plan ...................................................................... 63
4. Operating Phase: Programme Level ..................................................................... 65
4.1 Allocation of funding........................................................................................ 65
4.2 Calls for applications ....................................................................................... 70
4.3 Project approval and rejection......................................................................... 71
4.4 Contracting...................................................................................................... 72
4.5 Basic programme financial flows..................................................................... 73
4.6 Spending forecasts ......................................................................................... 75
Financial Management Handbook
6
4.7 Project claims for payment .............................................................................. 76
4.8 Tackling poor project spending ....................................................................... 80
4.9 Tackling a de-commitment threat .................................................................... 82
4.10 Recycling funds and end of programme de-commitment.............................. 83
4.11 Payment Claims to the Commission ............................................................. 84
5. Start-up phase: Project Level ................................................................................ 85
5.1 How to get project budget right ....................................................................... 86
5.1.1 Resource Planning................................................................................... 87
5.1.2 Cost Estimating ........................................................................................ 88
5.1.3 Cost Budgeting......................................................................................... 88
5.2 Budget detail vs. flexibility ............................................................................... 90
5.3 Helping projects get it right.............................................................................. 92
5.4 The assessment process ................................................................................ 93
5.4.1 Eligibility check......................................................................................... 94
5.4.2 Assessing project budgets ....................................................................... 96
5.4.3 Risk assessment ...................................................................................... 97
5.5 After approval .................................................................................................. 97
6. Operating phase: Project Level ............................................................................. 99
6.1 Avoiding project financial problems................................................................. 99
6.2 The payment chain Project reporting and claims for payment ................... 101
6.2.1 Reporting requirements.......................................................................... 101
6.2.2 Control / certification of claims ............................................................... 102
6.2.3 Assessment of reports............................................................................ 102
6.3 Helping projects with implementation problems............................................ 103
7. Certification of payment and financial control ..................................................... 106
7.1 First Level Control ......................................................................................... 108
7.1.1 Who is checked?.................................................................................... 110
7.1.2 Who are the controllers? ........................................................................ 110
7.1.3 What is checked by the first level controller? ......................................... 113
7.1.4 What is checked by programme management bodies? ......................... 118
7.1.5 What happens if there are problems? .................................................... 118
7.2 Second Level Control / Audit......................................................................... 119
7.2.1 Content of audits and common problems detected................................ 125
7.3 Financial Corrections and Recovery ............................................................. 126
8. Project and programme closure.......................................................................... 129
8.1 Project closure .............................................................................................. 129
8.2 Steps to project closure................................................................................. 130
8.3 Programme closure....................................................................................... 132
8.4 Third Level Control ........................................................................................ 135
Annex 1 Regulatory Framework.............................................................................. 136
Annex 2 First level control in INTERREG 2000-2006 ............................................. 138
All the EU regulations referred to in this document have been listed in Annex 1 and they can
be downloaded from the INTERACT website at:
http://www.interact-eu.net/604900/443793/0/0
Financial Management Handbook
7
Glossary
Advance payment (also called pre-financing): A small part of the ERDF paid to the
programme at the start to cover the programmes start up costs and to make the first
payments to the projects. In the 2000-2006 funding period the Advance Payment was 5% for
all programmes and in the new funding period 2007-2013 it will be 7% for programmes
involving at least one of the new EU Member States, Greece or Portugal and 5% for
programmes involving the EU-15 MS spread over three or two years respectively.
Audit Authority: A national, regional or local authority or body, functionally independent of
the managing authority and certifying authority, designated by the Member State for each
operational programme and responsible for verifying the effective functioning of the
management and control systems. (Source: Art. 59 EC 1083/2006) Assisted by a Group of
Auditors from the countries participating in the programme, the Audit Authority develops an
audit strategy according to which it carries out the inspection of the programme systems and
procedures and of a selected sample of projects. Actual audits are sometimes contracted to
audit firms.
Audit: In Territorial Cooperation programmes this term refers to second level control and the
audits carried out by other organisations such as the Commission. Audit is an inspection of
the programme systems and the financial records of a sample of projects. It should confirm
the sound operation of the programme management and control systems and the accuracy,
reliability and eligibility of funding claims.
Audit trail: A sequence of information i.e. accounting records that provide detailed
information about expenditure actually incurred. The accounting records show the date they
were created, the amount of each item of expenditure, the nature of the supporting
documents and the date and method of payment. The audit trail provides evidence of the
expenditure claimed and enables tracing the financial data to its source. (Source: Annex 1
EC 438/2001).
Automatic De-commitment (N+2 rule): A process whereby money can be taken back by
the European Commission from programmes that are not spending at a predefined rate. It is
a tool to encourage efficient financial management and avoid funds being left inactive in
programme accounts for many years as it intends to speed up the absorption of funds within
programmes. According to the N+2 rule, funds allocated to a programme must be spent
within three years (where N is the commitment year and +2 is the year by the end of which
funds committed in N have to be spent). The rule is applied at programme level but
programme managers may choose to reallocate expenditure away from inefficient projects
that are slowing programme spending.
Beneficiary: Operator, body or firm, whether public or private, responsible for initiating or
initiating and implementing operations. In the context of Territorial Cooperation programmes,
this means all partners participating in a project. (Source: Art 2 EC 1083/2006)
Business Plan: A document setting out the main programme management activities that
need to be carried out. It is fine-tuned at the Monitoring Committee meetings and becomes
the basis for Technical Assistance spending. The business plan is a medium term planning
tool providing a longer perspective than the annual or 6-monthly work plans normally
submitted to Monitoring Committees but providing greater detail and accuracy than the long
term plans provided in the Operational Programme.
Certifying Authority: A national, regional or local authority or body designated by the
Member State to certify statement of expenditure and applications for payment before they
are sent to the Commission. (Source: Art 59 EC 1083/2006). The Certifying Authority
manages programme funds and transactions with the Commission and recovers incorrectly
paid funds.
Certification: Means that expenses have been approved by the body officially responsible. It
occurs at two stages in the claims process: Firstly, all expenditure from every project partner
Financial Management Handbook
8
is certified by that partners first level controller. Secondly, the Certifying Authority certifies
every programme claim before it is sent to the Commission.
Claim for payment: Every time a project reports to the programme it sends a statement of
expenditure showing how much money it has spent. This statement also acts as a claim for
the ERDF that the project expects to receive from the programme (based on the approved
ERDF grant rate). Programmes follow the same procedure when they want to claim money
from the Commission.
Control / controllers: In Territorial Cooperation programmes this is used only to refer to the
first level control check. 100% of project expenditure is certified by a designated controller in
each partners country. This may result in some deductions if some of the expenditure is
incorrect. When the correct amount has been confirmed, the controller will sign a controllers
declaration certifying that the expenditure has been approved.
Detailed Costed Workplan: A project planning document containing a detailed breakdown
of the activities to be carried out, when they will take place, the resources required (staff,
equipment etc) and the cost for these resources. This document forms an essential basis for
realistic project budget estimates but should not be regarded as a guarantee of how the
project will be implemented: Project managers cannot predict everything that will happen in
this project and the work plan is their best estimate.
Description of management and control systems: A document which describes in detail
the roles and responsibilities of the programme bodies (Monitoring and Steering Committee,
Managing Authority, Certifying Authority, Audit Authority, Joint Technical Secretariat) and
outlines step-by-step procedures for how to handle the main programme activities. (Source:
Art 71 EC 1083/2006 + Art 21 1828/2006)
Eligibility: This term is used in financial control to describe expenditure that complies with all
the relevant EU, national and programme rules. Eligible expenditure can be reimbursed from
funding allocated to the project under the Subsidy Contract. Any spending that breaks one of
these rules will be found ineligible and will not be paid by the programme.
Financial report: Part of the progress report. Project Lead Partners have to submit a
progress report to their Joint Technical Secretariat at the end of each reporting period. It
contains a retrospective accounting of the total costs incurred during the reporting period.
First Level Control: Controls on the project level undertaken when project partners submit a
Payment Claim.
Ineligible expenditure: Expenditure presented for payment from the programme funds,
which does not comply with eligibility rules.
Intermediate bodies: Any public or private body or service which acts under the
responsibility of a managing or certifying authority, or which carries out duties on behalf of
such an authority vis--vis beneficiaries implementing operations. (Source: Art 2 (6) EC
1083/2006).
International Audit Standards: Auditing good practice standards developed by a number of
international organisations. These standards cover all aspects of audit work and in some
cases are being further developed to specifically address audit in the public sector. Audit in
the new programme period will have to comply with the relevant standards.
Irregularity Any infringement of a provision of Community law resulting from an act or
omission by an economic operator which has, or would have, the effect of prejudicing the
general budget of the European Union by charging an unjustified item of expenditure to the
general budget. (Source: Art 2 (7) EC 1083/2006).
Joint Technical Secretariat (JTS): A body responsible for day-to-day management of the
programme. It assists the managing authority, monitoring committee and audit authority with
carrying out their tasks.
Financial Management Handbook
9
Lead Partner: Administrative leader of the project who is responsible for ensuring that all
project activities are carried out according to the approved project application and that all
partners have all expenditure certified by the designated first level controller. The Lead
Partner signs a subsidy contract with the Managing Authority.
Managing Authority: A single programme body responsible for ensuring the effective
implementation of the agreed programme strategy in accordance with the pre-determined
quality standards. The Managing Authority takes the lead in establishing systems and
procedures and ensures they are maintained.
Memorandum of understanding / Letters of agreement: Documents drawn up between
the national or regional authorities participating in a programme and the programmes
management bodies. They are reciprocal agreements defining both MA requirements from
the Member States and the Member States requirements from the MA and other
management bodies. (Source: Art 59.3 EC 1083/2006)
Monitoring Committee: A committee which provides each Member State with
representation in the programme and safeguards the Member States interests. It takes
decisions on the programme level and needs to be kept informed of progress towards
programme objectives, the status of programme finances and any problems in programme
level bodies and procedures.
OLAF (European Anti-Fraud Office): Community office charged with detecting and putting
an end to irregular or fraudulent expenses within the Community budget framework.
Operational Programme: Document submitted by a MS and adopted by the Commission
setting out a development strategy with a coherent set of priorities to be carried out with the
aid of ERDF. (Source: Art 2 EC 1083/2006). It is the most important programme document
describing the programmes background, objectives, priorities, financing and implementation.
Partnership Agreement: It is a requirement that for each operation a lead beneficiary shall
lay down the arrangements for its relations with the beneficiaries participating in the operation
in an agreement comprising provisions guaranteeing the sound financial management of the
founds allocated to the operation, including the arrangements for recovering the amounts
unduly paid. (Source: Art 20 EC 1080/2006) In practical terms the partnership agreement
sets out the main responsibilities of the signatories (Lead Partner and Project Partners),
financial provisions (how the project budget will be subdivided between partners, eligible
expenditure and procedures for claiming payments) and governance issues (structures and
roles, procedures including settlement of disputes, etc.) on how the project should be
managed and implemented.
Progress Report: Comprised of the Activity Report and Financial Report (Payment Claim) it
documents the progress of the operation and serves as a payment request. Lead Partners of
operations have to submit a progress report at the end of each reporting period to the Joint
Technical Secretariat.
Real costs: The whole system of payments is based on this principle. Projects can only
claim amounts that they have really been charged (amounts incurred) in connection with
work required for the project, and can only claim them from the programme after these
amounts have actually been paid by the project.
Recovery: When funds are incorrectly (or unduly) paid to a project, the programme has to
get them back from the project partner concerned. Programmes normally do everything
possible to avoid this sometimes difficult procedure by holding back the last part of project
payments until they have control guarantees that the spending claimed is correct.
Separation of functions: The management and control systems of operational programmes
set up by Member States shall provide for compliance with the principle of separation of
functions between and within such bodies. (Source: Art 58 (b) EC 1083/2006. It is required
that the most important tasks in the programme management system are assigned to
different bodies to allow for the checking of work carried out elsewhere and remove
opportunities for corruption.
Financial Management Handbook
10
Steering Committee: An optional programme body responsible for the selection of projects
and in some cases post-approval monitoring.
Sub-contractor: A third party that is assigned tasks on behalf of the partnership. These
tasks will be the subject of a contract and the sub-contractor will need to be selected through
public procurement procedures.
Subsidy Contract / Grant Offer Letter: Contract between the Managing Authority and the
operations Lead Partner. It determines the rights and responsibilities of the Lead Partner and
the Managing Authority, the scope of activities to be carried out, terms of funding,
requirements for reporting and financial controls, etc. In the new programme period contracts
should also allow the possibility to de-commit money from under-performing projects.
System audits: A task carried out under the responsibility of the Audit Authority throughout
the programme lifetime to check the procedures established by all of the different
management bodies for administering the programme. This check focuses on whether these
systems will allow sound management of the programme and whether the systems described
are actually in use.
Systemic errors: Problems detected in the programme management and control system
affecting large parts of the programme and which can lead to major cuts in the Commission
funding. They can occur at project level (e.g. failure to secure the audit trail) or programme
level (e.g. giving incorrect advice on public procurement). Systemic errors generally result in
a suspension of payments and large grant cuts.
Technical Assistance: One of the priorities in the INTERREG / Territorial Cooperation
programmes covering the operating costs of the programme. It is financed in the same way
as all other costs with an ERDF contribution and a co-financing component. The
programmes TA budget is kept in a separate bank account to ensure that there can be no
confusion with other programme funds.
Third Level Control: In future this will also generally be carried out by the Audit Authority. It
involves preparing and approving the final statement of programme expenditure, the final
report and a winding up declaration certifying that all expenditure declared is correct and
that the findings of all controls and audits have been implemented. This control must be
completed before the programme can close.
Winding up declaration: A document confirming that the necessary checks have been
carried out and all corrective actions required have been completed. It is used by the
Commission to make the decision to close the programme and make the final payment.
Virement: Technical term sometimes used to describe the movement of money between
priorities. These movements of funds require Commission approval.
Financial Management Handbook
11
Introduction
1. The aim of this handbook is to help programme administrators from all three strands of the
Territorial Cooperation programmes and from different programme management bodies to
maximise the use of ERDF and secure high quality projects while at the same time ensuring
that financial management standards are met. These standards can be summarised by the
term sound financial management, defined as consisting of three key principles:
The principle of economy requires that the resources used by the institution for the pursuit
of its activities shall be made available in due time, in appropriate quantity and quality and at
the best price.
The principle of efficiency is concerned with the best relationship between resources
employed and results achieved.
The principle of effectiveness is concerned with attaining the specific objectives set and
achieving the intended results.
1
The handbook sets out to show how good financial management can act as a positive force
rather than an obstacle in achieving programme objectives by providing programme and
project managers with a clear framework and timelines for implementation.
2. The content has been developed from the official requirements for financial management
contained in the EU regulations governing the current funding period 2000 2006 and
proposed changes in requirements for the next funding period 2007 - 2013. Every effort has
been made to provide the latest information on the requirements in the new period. In some
cases however interpretation is needed from the European Commission and concerns about
the accuracy or relevance of the content should be addressed to INTERACT Point
Qualification and Transfer, who can provide updated information.
In addition to the Community regulations governing Territorial Cooperation programmes,
every Member State has its own national rules, in particular regarding the eligibility of
different kinds of costs. It has not been possible to provide an overview of all of these rules
and questions about national requirements should be directed to programme bodies.
3. The focus is on how the regulatory framework is applied in the programmes. In order to do
this attention is paid to both good practices and common problems so as to suggest workable
solutions. This may have the unintended effect of suggesting that financial management in
Territorial Cooperation programmes is always problematic. On the contrary, the main
elements are relatively simple.
The Good Practice boxes included throughout the text build on these elements and suggest
how they can be applied in practice. It is not suggested that everything proposed will be
appropriate in all programmes. Every Member State has its own procedures and
requirements for financial management. Full standardisation is not possible or desirable and
some of the suggestions in this handbook may need to be tailored to programme conditions.
Regardless of procedures, however, certain minimum performance targets are identifiable. If
these targets are not being met, there is a clear need for change. The start of the new
programme period presents an opportunity for every programme to reconsider its procedures
and whether they could be simplified and streamlined. These good practices have been
identified through over two years of dialogue with the programmes.
4. The main target group for the handbook is finance staff in Territorial Cooperation
programmes and others whose work with programme management requires an
understanding of the main financial principles and procedures. Wherever possible the content
is limited to the financial aspects of programme implementation but it is sometimes necessary
to consider wider programme management issues. Much of the information will also be


1
Council Regulation No 1605/2002 on the Financial Regulation applicable to the general budget of the
European Commission. 27.2
Financial Management Handbook
12
relevant to project level finance managers. Projects should, however, always check the
requirements of their own programmes before using the recommendations in the handbook.
There is perhaps one surprising omission. We have not included a detailed section on
interpreting the 12 rules of the current eligibility regulation. This is because an excellent
analysis of these rules is already available in the Eligibility Handbook produced by
INTERACT Point Managing Transition and External Cooperation (MTEC) in Vienna. The
handbook is available online at http://www.interact-eu.net/913123/1068570/0/0

Financial
controllers will nevertheless still find much that is relevant in this handbook.
5. The handbook was developed to accompany the INTERACT training seminar on Financial
Management in Territorial Cooperation programmes. Anyone wanting further detail or the
opportunity to discuss the points raised is recommended to attend the next seminar, which
includes case studies and additional examples of many of the points discussed here. Details
of the timing and location of future training seminars can be found on the INTERACT website
at www.interact-eu.net

under Events. Alternatively, send an e-mail requesting information to
ip.qt@interact-eu.net

6. Where relevant, boxes indicating the main changes in the new programme period and info
boxes defining important terms have also been added to the text.
The main regulations governing INTERREG / Territorial Cooperation programmes

Current period
2000 2006

New period
2007 2013

General Reg. 1260/1999

General Reg. 1083/2006

ERDF Reg. 1783/1999

ERDF Reg. 1080/2006

Use of EURO Reg. 643/2000

Management and Control Systems Reg.
438/2001

Eligibility of expenditure Reg. 448/2004



Implementing Reg. 1828/2006

7. There are many text boxes in the handbook containing different kinds of background
information. They have been flagged with one of the four icons and should help you find your
way around.

These sections cover the rules, regulations and main terminology involved in INTERREG /
European Territorial Cooperation programmes. They are an introduction for those who are
not familiar with the programmes.

These sections contain information explaining how the rules work on a practical example.

Financial Management Handbook
13

These sections address good practise examples on how to successfully implement the
regulatory requirements into workable solutions.

These sections contain a summary of the key points presented. These may be valuable
tips and ideas which are listed in a comprehensive way.

Structure of the handbook
One of the central points of this handbook is that all financial management activities are inter-
linked and sound financial management requires that these links are understood and
exploited. Some division of the content has, however, been necessary and the handbook is
broadly structured in two sections: Programme Level and Project Level. The table below
gives an overview of some of the main points covered in each section.

Key financial activities during programme and project life cycles

Start Up

Implementation

Closure

Programme

Bodies
Systems
Tools
Documentation

Funds
management and
payments

First and
Second Level
Control

Closure
statements

Project

Budget plans
Application
Contracting
Partnership
Agreements

Management
of spend

Monitoring
First and
Second Level
Control

Final
payments

The text within each section follows the programme and project lifetime and the main
procedures required at different stages. Nevertheless it is generally impossible to properly
understand one level without also considering the other and we would recommend that all
readers study both sections to get a full overview.
Financial control has been included in a separate section towards the end, being of equal
interest to the project and programme levels. The handbook ends with a brief discussion of
both project and programme closure, which draws heavily on previous sections and has
therefore been left as a concluding comment.
Financial Management Handbook
14
Note on terminology and abbreviations
At the time of writing programmes are in a period of transition with the old programmes
(2000-2006) still running and preparations well underway for the launch of the new
programmes (2007-2013). This handbook is largely based on the new period. Where
terminology from the previous period is used it should be understood as describing a practice
or procedure that may no longer apply in future.

Main changes in terminology

Current period
2000 2006

New period
2007 2013

INTERREG

Community Initiative Programme

Territorial Cooperation Objective (sometimes
called INTERREG IV)

Operational Programme
Paying Authority

Certifying Authority
Second Level Control Group Audit Authority

Art 5 Declaration Art 71 Declaration (Description of management
and control systems)

Main abbreviations used in the text
AA Audit Authority (new period)
CA Certifying Authority (new period)
CIP Community Initiative Programme (old period)
CSG Community Strategic Guidelines
ERDF European Regional Development Fund
EU15 The 15 EU Member States joining before 1 May 2004
EU10 The 10 EU Member States joining on or after 1 May 2004
FLC First Level Control
IB Intermediate Body
ISA International Standards on Auditing
JTS Joint Technical Secretariat
LP Lead Partner
MA Managing Authority
MC Monitoring Committee
MS Member State
MSC Combined Monitoring and Steering Committee
OLAF European Anti-Fraud Office (Office Europen de Lutte Anti-Fraude)
OP Operational Programme (new period)
PA Paying Authority (old period)
SC Steering Committee
SLC Second Level Control
TA Technical Assistance
TC Territorial Cooperation (new period)
Financial Management Handbook
15
Different rules for new Member States 2007 2013
It is extremely important to realise that the new regulations define two different groups of
Territorial Cooperation programmes with different rules in a number of key areas:
Different rules will apply to programmes involving Member States with a GDP of below
85% of the EU average (the new Member States, Portugal, Greece and east German
lnder)
Different rules on advance payments from the Commission will apply to all programmes
involving at least one of the new
2
MS (EU12) as compared to programmes involving
only old
3
MS (EU15)
It is important to note that these different rules apply to the whole programme if it involves
one of these countries (for example, the whole of the Finland-Estonia programme will be
covered by the rules for new Member States). The changes are summarised below but much
more detailed descriptions are available in relevant sections of the handbook for anyone
unfamiliar with the old rules.

Changes in the new programme period: Comparison New MS vs. Old MS

New MS

Old MS

ERDF grant rates

Up to 85% (programme level)

(Including Greece, Portugal and east
German lnder)

Up to 75% (programme level)

(Excluding Greece and Portugal)

De-commitment

N+3 in the first half of the programme
period changing to N+2 for the second
half

(Including Greece and Portugal)

N+2 in the whole programme
period

(Excluding Greece and Portugal)

Spending on
housing

Eligible (with conditions)

Not eligible

Advance
Payment

7% paid in 3 annual instalments:

2%-3%-2%

5% paid in 2 annual instalments:

2%-3%

(Including Greece and Portugal)




2
New MS are countries that acceded to the European Union on or after 1 May 2004. Though
increasingly outdated, the terminology is maintained for ease of reference.
3
Old MS refers to EU-15
Financial Management Handbook
16
1. The programme cycle in Territorial Cooperation
programmes

Territorial Cooperation financial management Operational objectives

Maximise the use of ERDF
Secure high quality projects
Secure quick enough pace of spend to avoid de-commitment
Develop programme confidence on eligibility
Ensure that financial control standards and deadlines are met
Limit bureaucracy
Actively manage potential problems using different planning timescales:
o Long-term: Operational Programme
o Mid-term: Business Plan
o Short-term: Action points between Monitoring Committee meetings

1.1 Key Financial Activities in the programme lifecycle
All Territorial Cooperation programmes and projects follow the same broad lifecycle with
start up, implementation and closure phases. The first task of finance staff is to understand
the key requirements at each stage so challenges can be predicted and managed.
The programme lifecycle provides a basic framework of regular events and deadlines to
which clear targets can be assigned. Commission spending deadlines (de-commitment
targets) determine the programme spending targets which in turn will be used to set targets
for allocating funds to projects. Similarly, workflows generally follow the project lifecycle with
predictable peaks during calls for applications and assessment of reports. All of these
elements should be considered at the start of every programme to gain an overview of the
resources and procedures that will be needed to cover different needs as they arise.
This initial assessment of the financial lifecycle of the programme should form the foundation
for the two key documents describing the way that the programme will be implemented: the
Operational Programme (CIP in the current programmes) and the Description of Systems
and Procedures (Article 5 declaration in the current programmes). These documents should
provide the outline for all financial management activities for the duration of the programme.
Each phase of the lifecycle involves different activities though there is of course some overlap
between phases.
Financial Management Handbook
17
Key financial activities in the programme lifecycle

Start up:
In Operational
Programme

- Identify programme management bodies and define
roles
- Establish legal framework e.g. agreements with
Member States
- Produce financial tables and financial sections of the
OP
- Decide split of funds between priorities and grant
rates
- Define as far as possible all financial management
and control procedures e.g. for application and
assessment, contracting, management of TA budget

Start up:
Other elements
required

- Define systems and requirements for work of programme
management bodies (Description of management and
control systems)
- Produce application forms
- Produce report forms
- Set up monitoring system (based on application
and report forms) for project and programme levels
- Produce guide for applicants, FAQs and fact sheets
- Carry out first project development events
- Identify first, second and third level control bodies
- Identify and secure required resources (e.g. staff)

Implementation:
Initial stage

- Run first project developer events (including advice on
project budgeting and financial management)
- Produce spending forecasts and profile of allocations
required
- Assessment of initial applications and possible
adjustment of programme documents
- Allocation of funding
- Systems control visit to programme

Implementation:
Main stage

- Monitoring of funds in priorities and possible movement
of funds
- First level control
- Verify spending and make payments
- Continuing advice to projects on financial issues
- Claims to the Commission
- Payments to projects
- Initiate second level control
- Mid-term evaluation

Closure

- Final report
- Winding up declaration
- Payment of 5% retention from Commission
- Final payments to projects
- Closure of programme management bodies

Financial Management Handbook
18
1.2 Key challenges in Territorial Cooperation programmes
There are a number of challenges that also need to be considered to smoothly implement this
basic scheme. Perhaps the most important of these are the EU de-commitment rules.

What is de-commitment and the N+2 rule?

De-commitment was introduced as a tool to encourage efficient financial management and
avoid large amounts of funds being left inactive in programme accounts for many years. At
the start of each year (year N), the Commission allocates or commits funds to each
programme. These funds have to be spent within three years (by the end of N+2). If they
have not been spent they are returned to the Commission or de-committed from the
programme.

This means that programmes have to operate efficiently and begin allocating funds and
therefore helping the regions of Europe as quickly as they can. It has been a very
successful tool in these terms and has meant that programmes have re-evaluated not just
the way funding is allocated but a whole range of management issues from speeding up
control work to building project development capacity in programme areas.

INTERREG programmes have sometimes struggled to spend the money in time because
of the added challenges of building cooperation between different countries, which often
delay both programme and project start-up. Despite this, the amounts lost to de-
commitment have been lower than anticipated though many other programmes avoided
de-commitment of funds only through extraordinary effort and increasing the reporting
burden on projects.

Critics of the rule argue that it threatens quality and instead shifts the focus onto spending
money. Indeed, the threat of de-commitment led to the creation of the concept of project
under-spending (projects failing to meet the spending targets in their budgets).

There is, however, strong Member State support for the rule as a way of ensuring the
efficiency of EU funds management so, even though it has been relaxed for some
programmes in the new period, it is extremely unlikely to ever be abolished. This means
finance staff need to establish monitoring systems capable of detecting any waste of funds
in project spending.

De-commitment can put pressure on quality by encouraging programmes to approve
inappropriate projects or activities in order to secure higher spending levels. The objective for
finance staff is to ensure the efficiency and security of programme implementation while still
avoiding a loss of funds and the regional development opportunities this funding should have
provided. The key to success is effective planning.
An additional challenge is transforming the regulatory framework conditions for implementing
the different levels of financial control used in Territorial Cooperation programmes into
workable systems. There is considerable nervousness about liability for the misuse of
European funds and this has tended to lead to a steady increase in the number of financial
controls in place. In some cases the controls used are already disproportionate to the funds
involved with, for example, project statements of expenditure being checked three times
during first level control in some programmes. Every effort must be made to reverse this trend
while maintaining standards and here it is essential to secure the full backing of National
Authorities.
A related issue is that of eligibility of expenditure and the frequent confusion that arises
from interpreting these rules. No regulation or guidelines will ever be able to cover all of the
situations that arise in project implementation and no single interpretation will be acceptable
to all Member States. This handbook therefore addresses eligibility from the perspective of a
small number of key principles and the belief that programmes must develop the confidence
to make their own decisions on these issues.
Financial Management Handbook
19
There is no magic solution to these problems but achieving spend of all funds allocated to a
programme does depend on setting up and operating effective financial procedures from the
start of a programme to its closure and on taking quick action as soon as any problems are
discovered. This is the role of the programmes finance staff.
1.3 Quality targets for key activities
In addition to the actual tasks, a number of important quality targets and the main factors
influencing them can also be identified at different stages of the programme lifecycle.

Quality targets and common problems

At start-up

Target: Set up an efficient programme management structure with good working
relationships between the bodies in the structure and adequate staff resources, good
systems to underpin key financial management activities, and clear documentation to
make responsibilities and systems transparent.
Common problems: Duplication and lack of clarity about the precise role of different
bodies. This should be improved by the change to single management bodies in future and
the requirement for a Handbook of Standard Procedures for every programme detailing
the tasks of each body.

Target: Managing de-commitment. Establish the exact amounts to be spent and
deadlines. Set realistic allocation targets and deadlines to achieve the required spend and
decide actions if projects are under-performing.
Common problems: Programme spending targets are often too unrealistic because they
are based on inaccurate project forecasts. Programmes, national and regional authorities
are also sometimes unwilling to take action against under-performing projects. There is a
need to set targets and discuss actions to improve projects early in the programme.

Target: Secure good projects. Use the application and selection process to ensure
soundly based projects, which spend according to forecast. Provide information to
partners. It will allow them to meet programme requirements.
Common problems: Not enough attention is paid to project and finances and
management during the selection phase and these issues need to be included in selection
criteria. Programmes also need to provide detailed information on budgeting and budget
management. If programmes de-commit due to project under-performance, this loss needs
to be passed on to the project concerned and project contracts should contain provisions
for doing this.

During Operation

Target: Fund management. Allocate funds effectively and keep track of expenditure.
Report to decision makers on progress and options for corrective action.
Common problems: Programmes have not allocated sufficient funds during the start up
phase. It is impossible to accurately predict annual project spending either because
insufficient budget information is provided or projects are allowed to repeatedly miss
targets without corrective action being taken.

Targets: Make swift payments to meet verified spending and generate claims to the
Commission.
Common problems: Projects fail to declare spending in time. This is, however, often due
to excessive bureaucracy and the time it takes authorities to certify spending. The new
regulations include a three-month limit for completing this procedure.

Financial Management Handbook
20
Quality targets and common problems continued

Target: Audit and monitoring. Ensure consistent and regular monitoring checks from
programme start, deal swiftly with irregularities and recovery of funds, minimise their
occurrence through advice to projects.
Common problems: Many audit and control responsibilities rest with the Member States
but Territorial Cooperation programmes have a low priority because of the relatively small
amounts of funding involved. As a result, structures are not set up on time. The new
regulations require that most of these structures are in place shortly after programme start.

Target: Secure project spending. Give ongoing advice to projects and streamline the
budget modification process.
Common problems: Little advice is available on setting up project budgets and as a result
spending forecasts for early stages are often much too optimistic. Programmes need to
advise on realistic budget profiles, provide flexibility for changes and ensure that spending
forecasts have a sufficient safety margin for project under-spending.

Target: Administration of the Technical Assistance budget. Maximise the use of the TA
budget and programme staff to support programme activities through Business Planning.
Common problems: Especially in small programmes, TA budgets can be small in
comparison to the tasks that need to be financed (and in many cases they will be smaller
in the new period). Detailed forecasting is needed to ensure the liquidity of programme
management bodies.

At closure

Target: Swiftly complete closure statements based on sound financial management and
monitoring systems, which have been run during the programmes lifetime and minimise
delays in making final payments to projects.

Common problems: Closure should allow an analysis of project and programme
achievements compared to the resources allocated. Monitoring systems are not always
adequate for providing this kind of information. Delays in financial control work can also
mean that critical findings are released too late for effective action to be taken.

Financial Management Handbook

21
2. Start up phase: Programme level

Start up phase at programme level: Summary

Establish a joint structure with clear financial responsibilities and good communication
links between bodies within the structure. Ways of doing this include formal agreements,
regular informal contacts, rules of procedure and briefing for the MC and SC. Ensure
financial functions are adequately staffed with a clear separation of functions and that staff
are well trained.

Set up frameworks for:
Funds management and prepare a first forecast of payment claims for the year
Payments cycle
Certification of payment claims to ensure that certification by approved auditors can be
obtained within three months
Monitoring controls including first and second level and final checks
Dealing swiftly with irregularities

Set up administration tools:
Two bank accounts, neither split between Member States
A digital database
A technical assistance budget

Present to the first MC a Business Plan describing resource requirements for
administration of the programme. Agree arrangements for co-financing contributions from
Member States/ regions.

Provide documentation to meet the European Commission requirements including an
indicative financial plan in the OP. Soon after approval draw up detailed requirements for
securing the audit trial and the handbook of procedures.

Programme start-up involves a number of key decisions that will have a lasting impact on the
effectiveness and efficiency of implementation. The first of these is the selection of the
programme management bodies and the next, delegation of the roles and responsibilities
between these bodies. The basic outline for these structures needs to be included in the
Operational Programme and forms a key part of the Commission decision on whether to
approve the programme. The OP is supplemented after approval by a more detailed
Description of Systems and Procedures and a Handbook of Standard Procedures.
These documents form part of the independent systems check of the programme and also
need to be approved by the Commission.
Some major changes have been introduced in the new regulations particularly with regard to
programme management bodies. These are covered in more detail below but we start with a
summary of services that management structures have to deliver to the programme.
2.1 Key elements to support financial activities (2007 2013)
The key elements which should be set up at the start of a programme to support financial
activities are outlined in the requirements for management and control systems in the
regulations as follows:
The management and control systems of operational programmes set up by Member States
shall provide for:
The definition of the functions of the bodies concerned in management and control and
the allocation of functions within each body;
Compliance with the principle of separation of functions between and within such bodies;
Procedures for ensuring the correctness and regularity of expenditure declared under the
operational programme;
Financial Management Handbook
22
Reliable accounting, monitoring and financial reporting systems in computerised form;
A system of reporting and monitoring where the responsible body entrusts the execution
of tasks to another body;
Arrangements for auditing the functioning of the systems;
Systems and procedures to ensure an adequate audit trail;
Reporting and monitoring procedures for irregularities and for the recovery of amounts
unduly paid.
4
These tasks are divided between a number of bodies including the Member States, the
Monitoring and Steering Committee the single Managing Authority, Certifying Authority and
Audit Authority and the Joint Technical Secretariat. The regulations contain clear descriptions
of the role of each of these bodies and stress that the main principle to observe is the
separation of functions between them and in particular of management, control and
payment responsibilities. Two areas of potential conflict need to be addressed. Firstly, tasks
assigned in the regulations to one body are often delegated to another (typically the JTS) and
this needs to be defined in detail so all stakeholders are clear about precise roles. The
second problem is related. Some tasks such as project monitoring require the input of more
than one management body, with one body responsible for checking the work of the others.
In the interests of efficiency, there is clear need to make sure that work is coordinated in
order to secure quality standards while avoiding duplication. These relationships are
therefore defined in two important documents the Operational Programme and the
Description of Systems and Procedures both of which are covered in more detail later in
this section.
2.2 Key points in developing programme management structures

Key points in developing programme management structures

The framework description of key programme management bodies contained in the
regulations is the main tool for building programme management structure
Set up a limited number of single programme bodies
Single programme bodies serve the interests of all MS participating in the programme
Draw up documentation defining roles of programme bodies
Each body needs to add value to programme management
Management bodies must be well integrated into programme information, managing,
monitoring and control systems
Management bodies must define the standards and systems that need to be in place in
all MS participating in the programme
Programme management bodies will perform 4 main programme management tasks:
o Allocation of funds
o Certifying correct expenditure
o Claiming funds from the Commission
o Paying funds to final beneficiaries

The biggest change in the new period is the introduction of single programme management
bodies and the joint technical secretariat to deliver management functions: Structures in
one country that manage the programme on behalf of all participating countries.
Every programme has found a different solution and there are many tasks to be assigned.
However, the fundamental requirements are relatively clear. Programmes may want to adapt
details to their own needs but effective management can be achieved with a limited number
of responsible bodies.


4
Council Regulation (EC) No 1083/2006 laying down general provisions on the European Regional
Development Fund, the European Social Fund and the Cohesion Fund and repealing Regulation (EC)
1260/1999, 58
Financial Management Handbook
23

Key programme management bodies:

Monitoring Committee
Steering Committee
Managing Authority
Joint Technical Secretariat
Certifying Authority
Control and audit bodies (FLC bodies and Audit Authority)
Intermediate Bodies

Single management bodies

Two of the programme management bodies in the new period are referred to as single:
The Managing Authority (MA) and Certifying Authority (CA). Put simply this means that
there will only be one in each programme.

In the past some programmes have divided these bodies by country with one body to look
after projects and partners from each country. In future the principle of cooperation will
be extended to programme management and each single authority will have to look after
all projects from all countries participating in the programme.

The concentration of programme functions in a limited number of joint bodies should
ensure improved cooperation and efficiency as well as cost savings. The main challenge
for these joint bodies is to define the standards and systems that need to be in place in
other Member States to ensure sound financial management and to define their
responsibilities with regard to these systems. In the past, the division of management tasks
and responsibilities between too many different bodies has too often meant that different
standards have been applied and that no central source of reliable programme data has
been available.

Joint management bodies

Only one body is referred to as joint the Joint Technical Secretariat. The single bodies
are generally national or regional institutions in one of the Member States and staffed by
public servants of that Member State. The JTS on the other hand has a representative
international staff. Its role is to provide services to all parts of the programme area.

2.3 Programme management bodies
2.3.1 The Monitoring Committee and the Member States
The Monitoring Committee (MC) provides each Member State with representation in the
programme and safeguards the Member States interests. Equally importantly, it allows
programme bodies to inform and remind Member States of the actions needed to fulfil their
obligations under the regulations. The MC comprises representatives from national, regional
and/or local bodies (in the cross-border programmes the regional level will generally play a
stronger role). It takes decisions on the programme level and needs to be kept informed of
progress towards programme objectives, the status of programme finances and any
problems in programme level bodies and procedures.
The strategic role of the MC should be made clear to all members: The committee is
expected not just to follow but also to forecast programme performance based on the
information provided by other programme bodies. It should also be ready to intervene if this
progress is not satisfactory. The MC also approves all official programme documentation
such as fact sheets on eligibility questions and thus needs a detailed understanding of the
issues at stake.
Financial Management Handbook
24
In the current period attendance at some committee meetings has been low and this can
make decision-making difficult. The best way of avoiding the problem seems to be to ensure
that the MC is given an active development role rather than just rubber-stamping the
standard monitoring data that need to be approved. This means that the papers provided to
the committee are very important for providing an informed basis for discussions. Financial
input will be required for:
Briefing on programme progress in realisation of the agreed business plan
Business plan update

What is the Business Plan?

Most programmes have a business plan though it has many different names. The business
plan describes how the TA budget will be used to meet the programmes objectives and
fulfil its obligations. It focuses on concrete actions and should be used as a tool for mid-
term planning (i.e. 2 years ahead). The content of the business plan can then be used for
defining individual annual work plans for different members of staff. It should as a minimum
cover the activities of all bodies drawing funds from the TA budget.

The plan allows programme bodies to agree realistic management strategies and assess
workloads for decisions on staffing. It is approved at the beginning of programme
implementation and generally updated every 6 months following programme needs. The
business plan also includes programme financial targets and ways of achieving them. Not
all actions can be predicted and there is a need for flexibility to deal with actions not in the
plan. Such actions should however be an exception so that all management bodies have a
sufficient degree of certainty for planning their activities.

Basic required content includes:

An overview of the current status of the programme and developments since the last
MC meeting
A forecast of expected developments in the coming period
The main tasks to be carried out to meet objectives in the coming period broken down
by unit / department
An analysis of whether existing resources and particularly staff are sufficient to carry
out these tasks
An analysis of the TA funds available and how they should be used

Review of the programmes financial position comparing the current position with the
targeted position. If there are major differences, a proposal needs to be made for
overcoming this problem. Key figures for the MC include:
o Programme allocation by priority (and measure in the current programming
period)
o Payments to date and N+2. What is the programme situation concerning
N+2? Is there any threat of de-commitment?
o The TA budget
o Is extra spending required by the programme? How much? What initiatives
can be taken to secure this?
o If the programme has de-committed, where will the money be taken from?
(This is a discussion that every MC should have near the start of the
programme)
Future programme strategy: Over time every programme will encounter problems that
need to be solved and situations that call for an adjustment of strategy. Many of these
issues are related to the number, quality and thematic focus of the project applications
being received at different stages of the programme lifecycle. Information on the financial
framework will give the MC an understanding of its options for addressing these
situations, such as:
Financial Management Handbook
25
o Deciding what to do if the programme needs more projects
o What to do in case the programme has too many eligible projects (advice to
the SC on prioritising applications)
o Suitable actions to attract projects within a certain measure
As noted above, the MC also provides a forum for programme bodies to question MS
representatives on the actions being taken to meet national authority obligations in the
programme. This is essential as a number of financial control decisions need to be taken on a
national level and experience from the current period has shown that delays in taking these
decisions can endanger the whole programme.
The main point to bear in mind is that each MS is ultimately responsible for all activities
carried out on its own territory. Further responsibilities can be divided into four groups:
Information:
MS must provide the MA, CA and AA with access to the information they need to carry
out their functions.
Management and Control:
MS are responsible for setting up effectively functioning management and control
systems for OP (via the MC)
Within max 12 months of the approval of the OP, MS must submit to the Commission a
description of systems covering the organisation and procedures of the managing,
certifying and audit authorities (this task is generally delegated to the MA)
MS will establish procedures for ensuring that all documents in the audit trial meet
national audit requirements
MS will designate First Level Controllers and ensure that the appointed body completes
certification within max 3 months
MS, through First Level Controllers, will ensure that all expenditure incurred by partners in
the MS complies with Community and national rules
MS must delegate a representative to sit on the group of auditors assisting the Audit
Authority and to carry out second level control work on their territory when this work has
not been sub-contracted
Eligibility:
MS must provide the national eligibility rules in use for each OP. These rules will apply to
determine the eligibility of expenditure except where Community rules are laid down.
Irregularities:
MS will reimburse to the CA any irrecoverable amounts unduly paid to partners on the
Member States territory;
MS will report to the Commission each quarter on any irregularities which have been the
subject of a primary administrative or judicial finding. Even if no irregularities have been
reported, MS still need to submit this report;
MS will follow up in each quarterly report on actions taken as a result of previously
reported irregularities
2.3.2 The Steering Committee
In the current period most programmes have also had a Steering Committee (SC)
responsible for the selection of projects and in some cases for post-approval monitoring. In
the new period, it is recommended that wherever possible the two committees should be
combined in order to reduce the number of meetings. Some programmes will however retain
a separate Steering Committee in order to separate decisions on the programme level (MC)
and decisions on the project level (SC).
Programmes already using a joint committee strongly recommend that members are
reminded of their role at different points in the meeting (MC or SC) and that a clear division is
maintained between the two parts of the discussion. The SC decides on the allocation of
ERDF funds but these decisions have a major impact on progress towards meeting
programme objectives so the MC clearly has a role in monitoring them. This is especially true
Financial Management Handbook
26
because SC decisions tend more often to be politically motivated and may place national and
regional interests above programme considerations, especially at the end of a programme
when funds are scarce.
In the current period, for example, some SCs have regularly rejected assessments made
according to the agreed programme criteria. The result is that weak applications are
approved and many of the projects concerned perform badly. As will be seen later, this has a
direct impact on programme de-commitment. Two approaches have been introduced to limit
this problem without affecting the independence of SC decisions (and indeed the MA has an
obligation under the regulations to intervene if the approved criteria are not being used).
Firstly, the committee rules of procedure are agreed at the first meeting. These rules can
include a number of safeguards:
SC members should commit themselves to providing sound reasons for rejecting the
project assessments presented to them. These reasons are recorded in the minutes of
the meeting and are available to all stakeholders.
Decisions should be based only on the information in the applications to prevent some
projects gaining an unfair advantage.
All committee members who have been involved in the development of a project should
declare a conflict of interest when it is discussed and play no role in making the decision
about that project.
Secondly, if the recommendations of the assessments are still regularly rejected, the MC
needs to play a role: Regular disagreement with assessment conclusions means that the
programme assessment criteria are wrong, the assessments are being performed poorly or
SC decisions are not being made in accordance with the criteria decided by the Monitoring
Committee. In each of these cases, the MC together with the MA needs to take action and
adjust the programme.
These actions are mentioned here (with apologies to the many well-functioning SCs) because
they are essential for the financial management of the programme. The approval of poorly
prepared projects is a major factor in programme under-performance and the Steering
Committee must apply sound financial criteria as part of the project selection process.
Regardless of whether it is a separate or joint committee, the SC needs to be provided with a
strong assessment of project financial plans and information on the impact on programme
finances of approving different projects (fundamentally whether there is enough money) in
order to make these decisions.
In case a current INTERREG III programme continues in the new period with no changes to
the participating MS, the programmes MC can take decisions on both current and future
programmes as long as there is a clear separation of these two roles.
2.3.3 The Managing Authority
The Managing Authoritys role can be summarised by saying that it is responsible for
ensuring the effective implementation of the agreed programme strategy to pre-determined
quality standards. It therefore takes the lead in establishing systems and procedures and
ensuring that they are maintained though many MAs prefer to assign daily operation of these
systems to the JTS. The indicative list of MA responsibilities below is based on the
regulations for the new period but does not differ substantially from the current period. The
main responsibilities are:
Financial Management Handbook
27

Maintaining standards

Ensuring that projects are approved, delivered and monitored in accordance with
agreed criteria
On-the-spot checks on at least a sample of projects
Ensuring project accounting standards, maintenance of the project audit trail and that
payments have been certified correctly by the designated first level controllers
Ensuring that project partners are aware of the terms under which grants are awarded
and that they have sufficient capacity to fulfil these conditions (Implementing
Regulation 13.1)
Ensuring compliance with information and publicity requirements

Maintaining standards

Ensuring that projects are approved, delivered and monitored in accordance with
agreed criteria
On-the-spot checks on at least a sample of projects
Ensuring project accounting standards, maintenance of the project audit trail and that
payments have been certified correctly by the designated first level controllers
Ensuring that project partners are aware of the terms under which grants are awarded
and that they have sufficient capacity to fulfil these conditions (Implementing
Regulation 13.1)
Ensuring compliance with information and publicity requirements

Providing reliable data to other management bodies

Ensuring that adequate information is provided to the Certifying Authority
Guiding the MC and providing it with documents on which to base its decisions
Drawing up and submitting reports to the Commission
Ensuring evaluations are carried out and meet quality standards

One additional feature of the MA in the future territorial cooperation programmes as opposed
to the national programmes is worth mentioning. Under the Territorial Cooperation Objective
the MA is not responsible for ensuring compliance with national and Community rules
regarding project expenditure
5
because different national rules are in place in each country.
This task becomes instead the responsibility of the first level controllers in each country. The
MAs responsibility in this respect is limited to ensuring that the agreed checks have been
carried out by the designated body.
Ensuring is a key word in the MA responsibilities as defined in the regulations: The MA does
not carry out many of these tasks itself but instead delegates them to another body. Most
often it is the JTS that takes on these responsibilities.


5
General Regulation, 60 (b) and Regulation (EC) No 1080/2006 on the European Regional
Development Fund, 15.1
Financial Management Handbook
28

What is the audit trail?

The regulations and many programme documents refer to the need to safeguard the audit
trail. Put simply this means keeping records to show how every EURO of programme
money has been spent. In most cases this is simply a matter of storing the invoices issued
for products and services delivered. The MA keeps a record of where all of these
documents are stored (most of them will be in project offices) so that financial controllers
can always know where to check if they have questions. These documents have to be kept
until three years after the formal closure of the programme (in theory until 31.01.2019 for
the new programmes), as it is still possible for European audit bodies to carry out checks
until then.

There are, however, some costs for which it is not possible to show an individual project
invoice such as overheads where the project will only pay part of e.g. a larger heating bill.
In this case documents of equivalent probative value need to be provided. This means
that they provide reliable proof of how the money was spent and different programmes and
countries have different rules for defining how such documents should be presented.

Finally, it is not always enough to prove that the money has been spent. In many cases
proof also needs to be supplied that value for money principles have been observed.
The most common requirement is for evidence of public procurement procedures showing
that attempts have been made to find the cheapest suppliers. See section 7.1.3 for more
details of documents required to secure the audit trail.

Generally speaking, original documents are needed for the audit trail. In the new
programme period each Member State will draw up national standards to be met if copies,
electronic versions or other formats are used. If this documentation is not available, the
spending it covers will be rejected. The basic rule is: If you cant prove it, it never
happened!

2.3.4 The Joint Technical Secretariat
The JTS is the body whose role is least defined in the regulations, which state only that it:
shall assist the managing authority and the monitoring committee, and, where appropriate,
the audit authority, in carrying out their respective duties.
6
Most JTS responsibilities are therefore delegated from other bodies while its central role in
project development varies too much between programmes to be defined in standard terms.
In the most successful examples in the current programmes, the JTS has specialized in all
communication down to the project level and in processing the reporting information
received from the projects. The MA tends to specialize in more formal communications
upwards to the Member States and Commission. Reports on programme progress tend to
be shared tasks.
The JTS is the first point of contact for many project developers and project partners and
provides guidelines and support during project development as well as often carrying out at
least part of the assessment of project applications. It also generally plays a strong role in
monitoring project implementation and spending, and recommending changes based on the
results. As such its staff need considerable financial expertise and there is a need for
programme level discussion of the advice they will give and the systems they will use. It is
important to note that the MA retains responsibility for checking that, for example, the
financial control of projects has been completed satisfactorily even if this work is carried out
by another body. This is the reason why the systems established by the programme play
such a vital role: They define the MAs requirements and allow it to rely on declarations from
other bodies that these requirements have been fulfilled.


6
ERDF Regulation, 14.1
Financial Management Handbook
29
According to the regulations the JTS is not meant to provide support to the CA since the CA
would normally be working on payment claims prepared by the JTS. However, if the CA
issues a request for information, the JTS is of course required to provide all necessary
information to the CA in order for it to carry out its work correctly.
2.3.5 The Paying Authority / Certifying Authority
One other single programme body is important in implementation: The Paying Authority or
Certifying Authority as it will be known in the new period. There is no significant change in
function between the PA and the CA so for ease of reference we refer always to the CA
below.
As can be seen from the figure below, the CA plays a key role in payment procedures and
also acts as a final control body before claims are made to the Commission. The main
tasks are as follows:
Certification and quality control

Certifies accuracy and standards used to calculate statement of expenditure
In general, guarantees uniform quality standards in certification of expenditure and
payment requests to the Commission as well as clarifies the nature and quality of the
information these requests are based on

Managing programme funds and transactions with the Commission

Draws up claims to the Commission
Maintains computerized accounting records of expenditure declared to the
Commission and payments received
Receives funds from the Commission and makes payments to LP
Keeps a separate programme bank account for ERDF

Recovering incorrectly paid funds

Recovers funds unduly paid to beneficiaries / project partners (together with Lead
Partners and Member States)

The CA administers the programme bank accounts (generally one for project payments and
one for TA) and is often responsible for ensuring programme liquidity (that there are
enough funds in the account to make payments). It gathers project claims for payment from
the MA and compiles these into claims to the Commission generally two or three times a
year. As a result, many CAs also play a role in drawing up spending forecasts and managing
the N+2 situation.
The accounting records it keeps will cover the claims made, amounts received from the
Commission and payments actually made to projects. Separate records held by the MA will
record the amounts claimed by projects and any deductions made as a result of control work.
It must be possible at all times to reconcile these accounts and ensure that both systems
agree on the amounts that have or should be paid. The CAs role in dealing with irregularities
(basically funds that should not have been paid out) is covered later in the handbook and has
to be summarized in an annual report to the Commission submitted by 31 March each year.
7

2.3.6 Relationship between the Certifying Authority and Managing Authority
One main difficulty that has arisen in the current period is in defining where the MA
responsibility for certification stops and where the CAs starts. It is clear that the CA has a
supervisory role towards the MA but that there is little value in repeating all of the checks of
project expenditure already carried out by the MA. This means that the CA too must focus on
ensuring that reliable systems and procedures are in place and that programme documents


7
Implementing Regulation, 20
Financial Management Handbook
30
require all programme bodies and projects use them and only allow certifications based on
the agreed procedures. Clarity about the CA role in this respect is vital: The change of name
in the new period stresses that the key role of the CA is certification of expenditure and it
must define how it will achieve sufficient certainty about the standards in place to make this
certification.

Managing Authority Certifying Authority Relationship

Managing Authority (MA) Certifying Authority (CA)

Approves individual project claims

Ensures that project level financial control
has been carried out properly

Prepares programme claims

Ensures the reliability of the MAs work

Keeps accounting records on project level

Implements control and audit findings
Keeps accounting records on programme level

Checks that control and audit findings have
been implemented

Clear separation of functions and independence is essential
Important to avoid duplication of control work

In general terms then, the MA is responsible for approving project claims (on the basis of
satisfactory first level control) and for providing the project figures used for drawing up
programme claims to the Commission. The CA is responsible for certifying these claims to
the Commission by carrying out a control of the information behind the claim. The nature of
these checks by the CA varies but they must include a review of:
- Measures taken to prevent, detect and correct irregularities, and to report them to the
Commission
- The conditions pursuant to Article 32(3) and (4) were met (submission of programme
complement, annual implementation report, mid-term evaluation etc);
- The expenditure declared was incurred and paid within the period of eligibility, and is
supported by evidence
- The operations complied with the relevant provisions of the assistance as adopted by
the Commission Decision and went through the proper selection procedures
- Operations related to State Aid were approved by the Commission and requirements
from other Community policies, such as public procurement, publicity and
environment, have been complied with
- Recoveries made since the last statement of expenditure have been deducted from
the present statement of expenditure and the amounts recovered are indicated in an
annex by measure.
Financial Management Handbook
31
1. Project Lead Partner
6. CA
5. Commission
4. CA
3. MA and/or JTS
2. First level control
bodies
Basic Territorial Cooperation programme payment procedures and bodies responsible

6. Makes payment to project
5. Approves valid claims and
transfers money to CA
2. Certify that expenditure claimed
complies with relevant rules and
regulations
3. Confirms that certification and
reports are satisfactory
4. Certifies programme claim based on MA /
JTS information
1. Draws up project report and claim payment
Financial Management Handbook
32
The paper highlights some good practice in carrying out this role. It suggests that the CA
should review reports of Article 4 and Article 10 control work and follow-ups to ensure quality.
It should also review some of the MA systems and information held on projects to make sure
that agreed procedures are in use and that the expenditure declared can be reconciled with
other records. Some of these checks can be limited based on positive outcomes of other
systems controls but the CA still has a responsibility to carry out and document meaningful
checks.
To conclude, the CA is very clearly charged with checking the correctness of the expenditure
declared by the MA (and any intermediate bodies). In order to do this it must develop
sufficient knowledge of the systems in place and the key findings of other control work.

What are Article 4, Article 9 and Article 10 checks?

These article numbers come from Regulation 438/2001, which contains information on
financial control in INTERREG. This regulation will no longer apply in the new period but all
of the checks it describes will continue just with different names.

All project expenditure needs to be checked to make sure that it has really been spent on
carrying out project activities and that none of the relevant rules have been broken. After it
has been checked, it is officially approved or certified. This process is called First Level
Control or Article 4 checks (after the article in the regulation which describes what needs to
be done).

As outlined above, the CA needs to check that everything has been done properly before
accepting project claims and actually paying the money to them. These are the Article 9
checks.

Finally, an independent outsider is sometimes asked to check a sample of this control
work. This process is called Second Level Control or Article 10 checks. You can find a lot
more information on this later in the handbook.

Control and audit: What is the difference?

In the current period these two words have been used differently in different programmes
leading to considerable confusion in some cases. The new regulations make the
terminology clear: Control is first level control and audit is second level control (see the box
above for definitions of these terms). Control is carried out by a controller, audits by an
auditor.

2.3.7 Intermediate Bodies
In addition to the main management bodies described above, the regulations allow for
Intermediate Bodies (IBs) to take over part of the management of the programme.
Intermediate Bodies are defined as:
any public or private body or service which acts under the responsibility of a managing or
certifying authority, or which carries out duties on behalf of such an authority vis--vis
beneficiaries implementing operations.
8
The number and tasks of the IBs established by programmes in the current period (and
particularly the cross-border programmes) has varied enormously but four main groups can
be identified:


8
General Regulation (EC) 1083/2006, 2 (6)
Financial Management Handbook
33
Many Member States making the transition from PHARE
9
to INTERREG have kept the
structures used to implement PHARE. Rather than redesigning the whole programme
structure halfway through implementation, PHARE management bodies have taken over
the same role in INTERREG on the new Member State side of the border. This has led to
the formation of sub-MAs and sub-Pas amongst others.
Intermediate bodies are often established to ensure that the programme has
representation on the local / regional level and that programme activities are not
centralised at one MA / JTS. These bodies are generally concerned mostly with project
development and can be particularly valuable in large programme areas. Sometimes a
whole office is established (a sub-JTS). In other cases only one person is employed
(often called a Contact Point).
Organisations with in-depth knowledge of a particular theme (e.g. ministries) are
sometimes given responsibility for selecting and monitoring projects under that theme.
Programme efficiency. Language and administrative barriers have often meant that it is
simply easier to manage funds separately on different sides of a border. This has,
however, limited active cooperation and will not be accepted in future.
In the new period there is considerable pressure, however, to streamline programme
structures and as a result the added value of some of these bodies is being seriously
questioned. There have been two main complaints. Firstly, true cooperation is expected from
projects and should therefore also be a requirement for programme bodies: One basic
condition for this is that management should be entrusted to single bodies working for all
participating Member States. The second problem has been one of coordination. In too many
cases, IBs have pulled in different directions developing their own interpretations of
programme strategy and using different standards. Perhaps more importantly, they have not
been properly integrated into the main management systems and procedures and in the
worst cases this means that it is not possible to get a collected picture of programme status
and that errors enter the programmes monitoring and accounting systems. Sub-Paying
Authorities have a particularly bad reputation in this respect and it is unlikely that they will be
allowed in future territorial cooperation programmes.
These problems are addressed in the new regulations. As explained previously, they propose
that each programme should have only one single MA and CA and a Joint Technical
Secretariat. Although still allowed, Intermediate Bodies should be seen as the exception and
will only be approved if their added value can be convincingly demonstrated. A likely example
of IBs that will be accepted is the use of sub-JTSs or Contact Points to achieve better
coverage of the programme area, as they have been a valuable addition in many existing
programmes. IBs that duplicate key management functions on either side of a border are, on
the other hand, extremely unlikely to be approved. Two questions therefore need to be asked
about every organisation in the programme management structure:
What value does it add to programme activities?
How will it be integrated into programme information, management, monitoring and
control systems?
The second of these questions is also covered in the new regulations, which contain strict
requirements for defining the role and organisation of IBs in relation to other programme
structures:
The Member State may designate one or more intermediate bodies to carry out some or all of
the tasks of the managing or certifying authority under the responsibility of that authority.
10
Where one or more of the tasks of a Managing Authority or Certifying Authority are performed
by an intermediate body, the relevant arrangements shall be formally recorded in writing.


9
Poland Hungary Assistance for the Reconstruction of the Economy. Despite the name, the PHARE
programme was extended to cover most of the countries of Central and Eastern Europe.
10
General Regulation 1083/2006, 59.2
Financial Management Handbook
34
The provisions of this regulation concerning the Managing Authority and Certifying Authority
shall apply to that intermediate body.
11
There are a number of key points here. Firstly, the main programme bodies retain full
responsibility for all of the actions of IBs. Secondly, the relationship must be described and
will be included in the Description of Systems and Procedures for approval by the
Commission. Finally, the provisions mentioned in the last section refer in particular to the
information to be provided according to Article 21 of the same regulation. This requires a full
written description of all of the main systems and procedures in place (amongst other things),
thereby ensuring that IB actions will be properly integrated with other management bodies.
In conclusion, setting up an IB that is adequate for meeting these requirements will be an
extensive procedure. In programmes where there have previously been many IBs,
management bodies should ask themselves whether these bodies could not effectively be
incorporated into the programme in a less formal way (e.g. through participation on
committees and working groups).
2.3.8 Audit Authority
The Audit Authority is the last of the compulsory programme management bodies. It is
covered in detail in the chapter on Certification of payment and financial control but we
provide some basics here.
The Audit Authority is based in the same country as the MA but in Territorial Cooperation
programmes it will generally be assisted by a Group of Auditors with one representative from
each participating country. The Audit Authority plays a vital role in programme start-up,
implementation and closure. Firstly, it is generally the Audit Authority that carried out the
independent check of a programmes management systems as laid out in the Description of
Systems and Procedures. The AA must approve the proposed structures if they are to be
accepted by the Commission. During implementation the AA is responsible for organising
second level control. In particular, the AA should verify the effective functioning of programme
management and control systems and control an appropriate sample of operations. The AA
will draw up the audit strategy and decide which projects should be checked on the basis of a
representative random statistical sample. In some programmes the actual audit visits to
projects are sub-contracted to an external company. In others they are carried out by the AA
and the members of the Group of Auditors. At programme closure it is also the AA that is
responsible for drawing up the Winding up declaration. This is a document confirming that
the necessary checks have been carried out and all corrective actions required have been
completed. It is used by the Commission to make the decision to close the programme and
make the final payment.
Some of this terminology is new but this way of working is actually in place in most
programmes already. The main reason for including the AA as part of the formal
management structure is to ensure that it is set up at programme start and that second level
control work is not delayed as it has been in many cases in the current period
12
.


11
Implementing Regulation, 12
12
See Implementing Regulation, 23 for the information that needs to be provided about the AA at
programme start-up.
Financial Management Handbook
35

The Audit Authority and the Group of Auditors

2.4 The responsibility chain
The whole system of Territorial Cooperation programme management depends on the
delegation of responsibility from the Member State level down to the project implementers.
Each level of the programme management hierarchy assigns tasks to be implemented at the
next level down and defines the controls it will require to ensure that this implementation is
properly managed. In this way, financial liability for European funds is distributed across the
programme and should finally pass to the end-user of those funds: The project implementer.
The framework description of the key programme management bodies contained in the
regulations is the main tool for building programme finance systems to ensure that this
happens. Where though should programmes start? Fundamentally, there are four programme
management tasks: allocating funds, certifying correct expenditure, claiming funds from the
Commission and paying these funds to final beneficiaries. In addition to the main
management structures, the various control and audit bodies assisting the programme also
need to be integrated into. If the bodies and tasks involved in each of these key procedures
are clearly defined, the basic framework will be in pace.
Each level needs to define the framework under which it will allow other bodies to act
independently. For example, the MA (together with the MSC) will generally define the
decision-making powers of the head of the JTS and the limits where additional authorisation
must be requested. It will also define the tasks that the JTS must carry out in order to comply
with programme requirements. Within this framework, the head of the JTS will then have the
freedom on how best to meet objectives on a day-to-day basis.
National Auditor

Combined report on each
checked project
Project checks

Audit Authority (MA
country)
Group of
Auditors
Project checks
Commission Annual report on
second level
control
Financial Management Handbook
36
These points need to be stressed because of experiences from some current programmes. In
some cases, roles have not been adequately defined and this has led to unnecessary
conflicts about who should be doing what. In other cases, management bodies have not been
willing to delegate powers and this has led to unnecessary delays due to the need to seek
approval for even minor decisions. Both situations have seriously impacted programme
performance. Certainly, the relationship between programme bodies is a trust-building
process and new structures should expect some tensions. This is why it is so essential to
invest time in laying out the main requirements in the programme documents.
2.5 The main programme documents

Key programme management documents

1. Operational Programme (OP)
2. Description of Systems and Procedures
3. Letter of Agreement / Memorandum of understanding
2.5.1 The Operational Programme (OP)
The OP is the most important programme document and is used by the Commission to make
a decision on whether the programme should go ahead. It is defined in the regulations as the:
document submitted by a Member State and adopted by the Commission setting out a
development strategy with a coherent set of priorities to be carried out with the aid of a
Fund,
13
More specifically, it should include:
Analysis of the cooperation area, including strengths and weaknesses and how to
deal with them this should reflect the specific programme objectives identified and
the allocation of funds to each priority.
Outcome of the ex-ante evaluation on the expected impact of the programme.
An outline of the different programme priorities and a justification for why these have
been chosen. The priorities should be further specified in overall goals and quantified
indicators on implementation, results and impact to measure the progress towards
achieving the goals.
Breakdown of the spheres of assistance by category i.e. description of the type of
actions that will be funded under each priority. This has important implications for the
eligibility of project applications.
Joint programme financial tables (i.e. no breakdown by Member State). The first table
should show the ERDF contribution split by programme year. The second table
should show the total funding available, i.e. ERDF and public co-financing, for the
whole programming period and per priority.
Information on programme implementation arrangements, structures and
responsibilities (see below), the monitoring and evaluation system and the Monitoring
Committee, procedures for financial flows, information and publicity activities.
Information on the electronic monitoring system for exchange of digital data between
the programme and the Commission.
An indicative list of any major projects expected to be submitted under the
programme. It is very unlikely, however, that most Territorial Cooperation
programmes will carry out this kind of project (generally over 50 million and
requiring special procedures and Commission approval) they are best run under
national programmes.
Certainly, the emphasis of the OP is on programme content and strategy but it also contains
basic information on management structures, the responsibilities of the bodies involved and


13
General Regulation (EC) 1083/2006, 2 (1)
Financial Management Handbook
37
the relationships between them (details of requirements can be found in the ERDF
Regulation, 12). As a minimum this will cover the institutions that will take on the different
management functions and which of the responsibilities listed in the regulations are assigned
to them.
2.5.2 The Description of Management and Control Systems
After approval, the programme needs to move from the general structures of the OP to a
more detailed description of exactly how programme management will operate. This is
included in a separate document known in the 2000-2006 period as the Article 5 Declaration.
Requirements for this description have been made stricter in the new period and it must
cover the MA, CA, AA and all IBs (and should also include the MSC and JTS). The
declaration develops the information in the OP to provide a step-by-step description of how
different programme bodies will handle the main documentation and procedures. The new
General Regulation (Art 58) lays out the general principles governing the establishment of
management and control systems and requires:
A clear definition of the functions of the bodies concerned in management and control
and a clear allocation of functions within each body
Compliance with the principle of separation of functions between and within each body
Procedures for ensuring the correctness and regularity of expenditure declared under the
operational programme
Reliable accounting, monitoring and financial reporting systems in computerised form
A system of reporting and monitoring where the responsible body entrusts the execution
of tasks to another body
Effective arrangements for auditing the proper operation of the system
Systems and procedures to ensure an adequate audit trail
Reporting and monitoring procedures for irregularities and for recovery of amounts unduly
paid
Financial Management Handbook
38

Responsibilities and bodies in Territorial Cooperation management structures

Main responsibilities defined
in OP and national letters of
agreement with the
programme

Main responsibilities defined
in OP and Rules of
Procedure












Main responsibilities defined
in OP, Art 5 declaration
(description of systems and
procedures), subsidy
contract and approved
application



The full content to be included in the description covers four articles of the Implementing
Regulation ( 21 - 24) but some of the key information it should provide on each body is:
The description of the tasks entrusted to them
The organisation chart of the body, the allocation of tasks between or within their
departments, and the indicative number of posts allocated
The procedures for selecting and approving operations
The procedures by which beneficiaries' applications for reimbursement are received,
verified and validated, and in particular the rules and procedures laid down for verification
purposes in Article 13 [MA administrative and on-the-spot checks], and the procedures by
which payments to beneficiaries are authorised, executed and entered in the accounts
The procedures by which statements of expenditure are drawn up, certified and submitted
to the Commission
Reference to the written procedures established for the purposes of points (3), (4) and (5)
Eligibility rules laid down by the Member State and applicable to the operational
programme
The system for keeping the detailed accounting records of operations and information
referred to in Article 14(1) under the operational programme.
14


14
Implementing Regulation, 22
Member
States
European
Commission

Monitoring
Committe
Managing
Authority

Intermediate
Bodies
Certifying
Authority

Project
Lead
Partners
Project
Partners

Joint
Technical
Secretariat

Audit
Authority

R
e
s
p
o
n
s
i
b
i
l
i
t
y

a
n
d

l
i
a
b
i
l
i
t
y

Main responsibilities are
defined in OP, description
of systems and procedures
and letters of agreement
Main responsibilities defined in project
partnership agreement and approved
application
Financial Management Handbook
39
When completed this document is submitted to the Audit Authority which will audit the
systems in place to ensure that programme staff are familiar with what needs to be done
although where systems and procedures are essentially the same in the new period as they
have been in the past, this systems check will be less detailed. The AA needs to complete its
checks in time for the approved document to be submitted to the Commission within twelve
months of programme approval.
Preparing this description can be a major task but in addition to setting out the procedures to
be used, it has a number of benefits. First and foremost it provides all programme
stakeholders (especially staff) and the Commission with an accepted version of how the
programme will be run. Lack of security about roles and responsibilities has been a significant
problem in some programmes so far and is often stated as a major factor in high staff
turnovers. Secondly, it provides confidence in the standards being applied and reduces the
risk of systemic faults (problems that are assessed as affecting large parts of the programme
and can lead to major cuts in Commission funding). Finally, it aids cooperation and serves as
a reference point in cases of disputes about programme implementation.
The description of systems and procedures will perhaps be the most important document
from a financial management perspective, as it contains the first detailed description of
financial management and control systems for each programme. The importance of these
systems cannot be over-emphasised.
2.5.3 Memoranda of Understanding between the programme and the Member States
Sometimes also known as letters of agreement, these documents are generally drawn up
between the national or regional authorities assigned responsibility for programme
implementation in each participating Member State and the Managing Authority (on behalf of
other programme bodies). They are reciprocal agreements defining both MS requirements
from the programme and the programmes requirements from the MSs. Much of the content
is standard and defines the relationship between the programme and the MSs and the bodies
appointed in each MS for various programme related tasks. Some individual requirements
are also included such as additional reporting on projects from a given MS and procedures
for paying MS contributions to the TA budget. In general, these agreements attempt to
harmonise programme procedures with particular national requirements.
In turn the MSs commit to fulfilling their obligations in the recovery of funds incorrectly paid
out and providing the information required for the MA, CA and AA to carry out their duties. In
the new period this will refer particularly to the timely identification of approved controllers
and auditors and providing the national eligibility rules that are to be used in the programme.
2.5.4 Project contracts and partnership agreements
Another important link to consider is the one between the programme and its projects. This is
covered in detail in the project section of the handbook but is mentioned here to emphasise
that the process of delegation must extend right down to the project partners. The subsidy
contract (or grant offer letter) between the MA and the project LP ensures that final
beneficiaries (project partners) are required to meet the standards of, and supply adequate
information for, programme management and control. In the new period subsidy contracts
should also address failures of project implementation and the risk of projects losing funds if
they are responsible for programme de-commitment.
In the new period a Lead Partner will be responsible for laying down the arrangements for its
relations with all the partners participating in the operation. The agreement will take form of a
partnership agreement and it will extend the arrangements agreed upon between the MA and
the LP to the level of each partner. It should also stress that the partners are financially liable
for all of the expenditure they incur and that any funds incorrectly paid out will be recovered
from the partner concerned.
Financial Management Handbook
40

Some key principles

Territorial Cooperation programming, including the set up of financial management and
control systems, is based on a number of key principles. Proposals for systems and
procedures should always be checked to see that they comply with these principles:

Partnership: The countries and regions participating in a programme need to cooperate on
finding optimal solutions. Most programme tasks should not be carried out on a national
basis but rather on behalf of and for the benefit of the whole programme area.

Proportionality: Expenditure on financial management and control should be limited in
relation to the funds available to the programme. Programmes need to find cost effective
solutions that can still deliver the necessary quality.

Subsidiarity: Functions should not be centralised but should instead be carried out by a
competent body at the most appropriate level.

Transparency: Information on all systems, procedures and requirements should be freely
available along with evidence that these systems, procedures and requirements are being
consistently applied.

Additionality: Programme funding shall not replace national, regional and/or local funding.
Programme funding shall not be used to fund activities that participating organisations
have a statutory requirement to carry out.

Some other keys to success:

Simplicity: Reduce burdens on projects and programme bodies, speed up processes and
avoid mistakes by removing complexity and unnecessary detail. Introducing new rules is
rarely the way to improve management.

Place projects at the centre: Helping projects operate effectively and spend their grants in
full and on time should be the first aim of all the bodies involved in programme operations.
National and regional rules that put barriers on effective implementation should be
identified and challenged

Flexibility: Operations must of course always respect EU and national legal requirements.
However, it is important to distinguish between these requirements and the programmes
administrative rules. For the latter, there may be opportunities to relax requirements and
deadlines sometimes if this can help projects without risk to standards.

2.6 The need for strong cooperation between management bodies

Bodies in the joint structure should:

Work together and communicate regularly
Set up good formal and informal communication mechanisms
Have clearly defined responsibilities
Identify, monitor and adjust the programmes objectives and address all factors
threatening their achievement
Recognise and respect the challenges of working with different cultures, in different
languages and with physical distance

Financial Management Handbook
41
No matter how well responsibilities are defined and how good the programmes
documentation is, no programme can succeed if the different bodies involved do not work
together.
Many programme functions involve the close working of at least three or four of the
programme bodies. One good example where there have been problems in the current
programmes is creating an accurate annual spending forecast. This involves collection of
reliable figures from the projects, analysis and adjustment of this data by the MA or JTS
before the PA sends the forecast to the Commission. If, as has happened, another
programme body steps in during this process and grants extensions to large numbers of
projects, all previous work will have been wasted. It is therefore crucial to clearly identify the
division of financial responsibilities between the bodies in the joint structure, to identify the
programmes goals in terms of financial performance and agree on the measures that will
achieve these goals (and perhaps those that will be damaging and should be avoided).
It is also important to set up good communication mechanisms, both formal and informal,
between the bodies in the joint structure. It may seem too obvious to repeat but different
languages and cultures and physical distance can hinder communication and understanding.
Despite this, in many programmes staff at different implementing bodies do not meet. This
can result in pointless and unfounded criticism while dialogue frequently leads to rapid
problem-solving. Investing a little time in this type of meeting may be the single most effective
way of tackling internal programme difficulties.
Regular communications between the MA, JTS and CA should be established as a priority. In
the current programmes physical distance has sometimes prevented this and this has led to
the proposal in the new regulations for the MA and JTS to be located close to each other.
Some programmes have found it helpful to set out responsibilities and relationships in formal
agreements or memoranda of understanding not only between MA and each participating
country or region but also between programme bodies such as the MA and CA.
It may also help all parts of the joint structure and the MC and SC to operate more effectively
if briefing on the nature of financial activities and issues likely to arise during the period of the
programme is given at the start of the programme e.g. in a workshop. This may be
particularly useful for SC members, who need to be made aware of the implications of
approving weak projects. It should also be remembered that many committee members are
not financial experts. Good briefing material and an overview of the decisions required should
therefore be provided well in advance of each meeting.
Financial Management Handbook
42
2.7 Staff and Training

Ensure adequate staff levels for managing programmes and have these approved in
a business plan

Promote customer service approach of all programme staff when dealing with projects
Useful programme staff expertise:
Basic accounting procedures
EU regulations on financial management
Management of project finances
Accounting and public procurement procedures of the country hosting MA and CA
Knowledge of national eligibility rules in participating MS
Advisory and presentation skills

Essential to separate:
Programme management, control and payment functions
Advising projects vs. managing projects

Important to:
Develop programme confidence on eligibility
Give consistent advise to projects

Bear in mind there is high risk of losing knowledge and expertise due to high staff turnover

There is no standard answer to the question of how many staff are needed for the financial
management of a Territorial Cooperation programme. The answer depends on the set-up of
the programme and the stage of the programme cycle that has been reached (there is a
general need for more finance staff in later years when many projects are reporting). This is
why it is so important for programmes to predict and monitor workflows, and adjust staffing
levels accordingly (see the info box on Business Plans earlier in this chapter).
It is clear, however, that some existing staff levels are inadequate and that the bottlenecks
this can create are a major threat to programme implementation. This has been particularly
problematic in first level control bodies in the current period and has led to the introduction of
the three-month time limit for certification in the new period. Obviously, staffing will be the
main factor in ensuring that this deadline can be met. As noted above, the Description of
Systems and Procedures for the new period requires that indicative staffing levels for
management bodies are included to set a realistic baseline. This should be extended to
include financial control bodies.
Staff carrying out first level control in the current period have in some cases also been
neglected in terms of training and support. Their role is vital but they are sometimes left alone
with this responsibility and have no formal support structure for providing advice on difficult
issues. Programmes should in future consider providing on-going training to address this
problem. Where staff are particularly inexperienced, the Audit Authority and national
auditors should also be prepared to act as experts providing binding decisions on difficult
eligibility questions.
In terms of required skills for programme secretariats and MAs the main areas are financial
expertise in basic accounting procedures, the operation of EU regulations concerning
financial operations, and management of project finances. Staff should also be familiar with
the accounting and public procurement procedures of the country hosting the MA and CA and
should have some knowledge of national eligibility rules in participating countries. Advisory
and presentational skills are also useful for interaction with the MC and SC.
The problem of inexperienced staff and high turnover has been identified by system
controllers as a major risk factor. This is particularly true of international JTS staff. These staff
generally form the interface between the programme management and the projects and need
to give fast, clear and consistent advice. The description of systems and procedures can
Financial Management Handbook
43
again play an invaluable role here (if it contains a detailed enough description of procedures)
by ensuring that knowledge of essential systems and procedures is not lost when staff leave.
Some programmes have therefore developed the original declaration into a staff training
manual and use this to keep all important information updated.
In general, however, the staff situation in all programme bodies needs to be managed. Some
losses are due to unclear roles and responsibilities. Others because salaries are
uncompetitive compared to similar private sector positions. Others again because of
insufficient training and development possibilities. Whatever the cause, keeping good staff is
clearly a major factor in programme success.
2.8 From systems to start-up
Formal approval of a programme by the Commission is only the starting point and
workloads should be expected to rise after approval. Aside from preparing the
Description of Systems and Procedures for submission, there are a number of other
deadlines in the new regulations, which require a rapid pace of development over the
first year of the programme and aim to ensure that the first projects are up and
running by the second year at latest. Finance staff will be involved in most of this
work.

Programme deadlines

Submission of programme to Commission
No more than five months after adoption of the Community Strategic Guidelines (General
Regulation 32.3). Latest estimated date for adoption of CSG = 6 October 2006. Latest
date for programme submission = 6 March 2007

Spending forecast for 2007 + 2008 to the Commission
No later than 30 April 2007 (General Regulation 76)

Set up Monitoring and Steering Committee (MSC)
No more than 3 months after approval (General Regulation 63) Members must be
identified in the OP (ERDF Regulation 12+14)

Communication Plan
No more than 4 months after approval (Implementing Regulation 3)

Approval of project selection criteria by MSC
No more than 6 months after approval of programme (General Regulation 64)

AA to present Audit Strategy, (including sampling technique, indicative audit plan)
Within 9 months of approval (General Regulation 62)

Description of systems and procedures
No later than 12 months after approval and before submission of first payment claim to
Commission (General Regulation 71)
To include a report on the results of the system audit (probably by Audit Authority)

The remaining parts of this handbook cover the requirements that need to met by the
programme implementing arrangements established.
Financial Management Handbook
44
3. Financial framework
3.1 Sources and uses of programme funds

Basic funding mechanism in Territorial Cooperation programmes

Programme financing comes from two different sources: European funding from the
European Regional Development Fund (or ERDF) and co-financing provided by
organisations in each Member State. Once allocated to the programmes, these funds are
divided between a number of programme priorities (e.g. 50% for job creation, 25% for the
environment and 25% for transport). Projects apply for grants from these priorities and 94%
of total programme funds are awarded to the successful applicants. 6% of the ERDF
contribution to programme funds (plus the agreed cofinancing) are retained within the
programme to cover operating costs. (This is according to the current interpretation of the
regulations. This interpretation may however change in the future and the TA budget may be
calculated on the basis of 6% of the total programme funds including cofinancing. This
section of the handbook covers some of the factors that affect these basic financial flows.
3.1.1 ERDF
The Territorial Cooperation programmes are just one small part of the much larger European
Regional Development Fund (ERDF)
15
. The overall funds for the programmes are decided on
the European level. They are then divided between the Member States, which allocate the
funds to the programmes they are involved in, based largely on population in the programme


15
Relatively small. Total ERDF funds for the period 2007-2013 are 308,041,000,000. Of this the
approximately 80 Territorial Cooperation programmes are allocated 2.52% or 7,750,081,461.
EU contribution (ERDF)
75%
Programme operating
costs (Technical
Assistance) 6%*
Grants to projects - 94%*
Programme budget
(allocated into priorities)
Contributions of
participating countries,
regions and organisations
(co-financing) 25%*
75%*

6% 94%*

25%*

* Figures vary between programmes details
Financial Management Handbook
45
area. As soon as they have been allocated to a programme, however, the funds enter a
common pot and should be accessible to projects from any of the participating countries.

The common pot and the programme bank account

Member States allocate funds to the programmes they are involved in and most
programmes get quite different amounts from the different countries involved. In theory,
this should be irrelevant to the programme. Once the money enters the common pot, it
should be granted to the best projects no matter where they come from. In practice, the
situation is often more complex. Some programmes in the current period have used the
regional MS allocations to the programme as the basis for deciding which projects get
approved: If a country puts in 50 million, its projects should get 50 million back. This has
led to funding imbalances with one country claiming a majority of programme funds.
Projects from the other country will not have enough funds to actively participate in all
projects and this of course has a negative effect on cooperation.

Obviously, Member States do monitor how much their projects are receiving from each
programme and compare it to the amounts allocated but in the most successful
programmes funds are never guaranteed to any one country or region: If they want to
access the funding, they have to develop quality projects. This has led to the requirement
in the new programmes that there can be no national (or regional) sub-accounts because
money committed to a programme does not belong to a Member State. It is in the
common pot and available to all. Therefore programmes should not in future monitor or
report on allocation by Member State or region.

Funds are allocated (committed) to the programme at the start of each year 2007-2013, with
most programmes having a pretty equal allocation for each year. The funds are not, however,
paid to the programme bank account. Instead, the programme must claim the funds from the
Commission after the projects have spent them, with every programme entitled to claim as
much as the Commission has so far allocated. Programme claims actually take some time to
start arriving at the Commission because projects must first be approved and start spending.
This means that there is always more than enough money committed to cover programme
claims.
In the past this meant that large amounts were committed to the programmes but were not
claimed until many years later (and could not therefore be used more constructively). This
was the reason for the introduction of the de-commitment rule whereby the Commission
reduces the amount it has allocated to a programme if the funds have not been spent after
three (N+2) or four (N+3) years. See the info box on page 13 and later sections of the
handbook for more information on how this works.
Country A allocates
50 million to
programme
Country B allocates
15 million to
programme
Common pot

Project partners in
country A granted 40
million
Project partners in
country B granted
25 million
Financial Management Handbook
46
3.1.2 Pre-financing or the programme advance payment
One small part of the ERDF allocated to the programme is paid into the programmes account
at the start. This advance payment is to cover the programmes start-up costs and to make
the first payments to projects. This advance should be deposited in an interest bearing
account to generate extra funds for programme actions. When any claim to the Commission
is paid, the programme again has the amount of the advance in its accounts minus any
expenses incurred between making the claim and receiving the payment. This means that the
programme should always have a reasonable operating budget. The annual ERDF
contribution to the programmes Technical Assistance is generally transferred to the TA
account at the start of each year to provide these operating funds. TA expenditure claimed
from the Commission is then paid back into the account holding the advance.
The amount of the advance payment and the way in which it is paid are two of the major
changes in the new programme period. In the current period all programmes have received
an advance of 7% of the total ERDF allocated, paid in one instalment at programme start up.
In future, two different systems will operate. Programmes that only include EU15 countries
will receive a 5% advance with 2% paid in the first year and 3% in the second year. All
programmes that include one of the other Member States (the new Member States) will
receive 7%, where 2% paid in the first year, 3% in the second year and 2% in the third year.

Calculating the advance payment

Example 1: DK-SE (both EU15)

Programme ERDF: 50 million*
Advance in 2007 (2%): 1 million
Advance in 2008 (3%): 1.5 million
Total advance: (2%+3%): 2.5 million

Example 2: IT-SL (one EU12)
Programme ERDF: 50 million*
Advance in 2007 (2%): 1 million
Advance in 2008 (3%): 1.5 million
Advance in 2009 (2%): 1 million
Total advance: (2%+3%+2%): 3.5 million

* The figures given are just examples and in no way reflect the real programme budgets

In addition to providing the programme with funds to cover operating costs, the advance
payment has important implications for de-commitment. See section 4.1 for more on how this
works.
3.1.3 Co-financing (or match-funding)
75% of programme funds come from the ERDF. The other 25% are contributions from other
sources (though see the section on ERDF rates for important clarifications about how these
figures can vary).
16
Co-financing is an important principle in the Territorial Cooperation
programmes. On the one hand it requires a financial commitment from the organisations
participating and ensures that they have a stake in ensuring successful project
implementation and promoting results. On the other, co-financing is often paid out in full or in
part at project start-up and gives them operating capital until the first claim to the programme
is paid. Despite this, projects will sometimes actually need to find more than the co-financing
amount in order to start operations because of the reimbursement approach of the


16
This is a complex subject with significant national variations and we cover only some of the main
points here. Anyone wanting to know more should see National Co-Financing of INTERREG IIIA
Programmes produced by INTERACT Point Managing Transition and External Cooperation and
available on the INTERACT website.
Financial Management Handbook
47
programmes whereby money can only be claimed after it has been spent. Although the
money is ultimately paid back, project partners need sufficient liquidity if they are to become
involved in cooperation projects.
Co-financing is provided through a number of different systems at present. Again, the
diagram at the start of this chapter is a simplification. Generally co-financing is not paid into
the programme budget (though there are a few programmes that manage these funds on
behalf of participating regions). Instead, the co-financing is normally paid direct to the
approved projects. When the projects prepare a statement of expenditure and claim funds
from the programme, the programme pays 75% of the total expenditure ensuring that 25%
of funds are always provided from other sources. Projects normally have to provide
information on where this funding has come from and this is vital if private co-financing is
involved (see below).
The term co-financing can also be misleading. This contribution is not always in the form of
money and can instead be provided as staff hours or other resources. This is discussed in
more detail in the section on own contributions. When co-financing is given in the form of
funds, it comes in varying proportions from national, regional and local sources depending on
the programme though regional funds tend to dominate. Some programmes also allow the
private sector to contribute and the special requirements for this are discussed below.
There are two main ways of deciding which projects receive these funds. On the one hand,
automatic co-financing systems operate in some countries. In these cases there is an
allocation in national, regional and/or local budgets, which guarantees to provide co-financing
for approved projects. Other countries run a competition system. Here there is no guarantee
of co-financing even though national and/or regional bodies normally have some funds
allocated for this purpose. Project partners must instead put together a package of funds from
different bodies, which each contribute according to the value that they place on the projects
objectives. This also spreads the ownership of the project, making it more likely that several
different bodies will take up the project results when it is completed.
Both systems have advantages and disadvantages. The key disadvantage of the competition
system is that it can be hard for projects to secure the co-financing they need. This can,
however, be a good way of improving general project quality, as partners must convince the
bodies involved of the value of the activities planned. In areas where public budgets are
already very limited, however, there is a danger that failure to secure co-financing may be a
serious limiting factor in a programmes ability to allocate funds. This is particularly true for
cross-border programmes where many of the partners are small organisations, which lack the
networks to effectively lobby for funding.
Automatic co-financing certainly removes this problem but can create a new problem that is
more serious. Consider, for example, automatic co-financing coming from a region. Every
year, the region needs to know how much money it will be expected to provide in co-financing
so that the regional budget can be prepared. Furthermore, any co-financing that has not been
allocated by the end of the year will probably have to be returned to the regional budget and
will be lost to the body responsible for administering the co-financing. This means that
programmes need to ensure that each region meets its co-financing targets and that meeting
these budget targets becomes a dominant factor in project selection. There is a clear danger
that project quality suffers and that, when coupled with a guarantee of ERDF funding to each
region, narrower regional aims may well be pursued at the expense of wider programme
objectives.
It is also hard to coordinate annual budgeting in regions with the seven year budget cycle of
the programmes: Programmes need to allocate heavily in the first years but regions may well
prefer to spread co-financing commitments more evenly across the programme period. This
can lead to de-commitment problems if the programme is prevented from allocating funds
because of a lack of available co-financing. These issues are equally relevant to national
automatic co-financing. Problems can be avoided if the regions concerned are sufficiently
flexible and are willing to apply longer timeframes to budgets allocated to Territorial
Cooperation programmes.
Financial Management Handbook
48
3.1.3 Private co-financing
A small number of programmes in the current period have included private co-financing. This
decision needs to be taken when writing the Operational Programme and estimates need to
be included in the programme financial tables of the amount of private co-financing.
In the 20002006 period private co-financing has been problematic. One reason is that
projects using private co-financing must report on the amounts involved and the total can
never exceed the programme estimate included in the financial tables in the OP. It needs to
be remembered that private organisations can claim a lot more from the programme than
they contribute themselves and as their own contribution is often made up of staff time, EU
funds can look like a very attractive opportunity. The programmes, however, are aimed
primarily at public sector actions to support regional cooperation and development and not at
the support of private enterprises. The limits set in the programme financial tables ensure that
the private sector does not secure a disproportionate share of programme funds. As a result,
excess private funds in the programme above the amount stated in the financial tables do not
generate ERDF. In the current period they are instead treated as programme revenue and
can actually lead to a reduction in the ERDF paid whenever there is a shortfall in the public
co-financing promised (see the info box below for an example). In future excess private funds
will not be a problem as long as all of the public funds originally promised have also been
paid.
Similar problems can also arise each time a claim is made to the Commission. We take the
example of a programme funded 50% ERDF, 40% public co-financing and 10% private co-
financing. These rates apply to the programme and it will not be possible to apply them in all
projects, as some projects will have no interest for the private sector. Individual projects may
therefore have a larger proportion of private funding. If projects with a strong element of
private co-financing perform well, it is quite possible that a claim to the Commission will report
spending of 50% ERDF, 35% public and 15% private co-financing. When processing such a
claim, the Commission cannot know whether this trend will be reversed in later claims or
whether the amount of private co-financing will eventually exceed the amount in the financial
tables. In such cases the Commission generally caps the claim, paying out a lower amount
of ERDF than the total claimed and reserving the rest to see whether the necessary public
co-financing is made available at a later point (see section 3.4 for a more detailed discussion
of the capping procedure).

The effect of excess private funds on programme finances in 2000 2006

The programme budget is 100 million total split in the OP financial tables as follows:

ERDF: 75% Public co-financing: 15% Private co-financing: 10%
ERDF paid: 75 million

The actual amounts claimed at the end of the programme are split as follows:

ERDF: 75% Public co-financing: 10% Private co-financing: 15%
ERDF paid: 60 million

In this case the Commission will say that only 20 million of the required co-financing has
been provided (5 million of the necessary public contribution was missing). As a result,
the Commission will only pay a total of 60 million out of a possible total of 75 million.
Member States have to pay the 15 million bill. Some programmes have made this
expensive mistake in the past. Private sector involvement has to be very carefully
monitored.

A couple of additional points also need to be considered by programmes planning to include
private co-financing. Firstly, there is the risk of bankruptcy, which can be made more acute by
the fact that all partners must spend first and wait for payment. If a company collapses
halfway through a project this can leave programme authorities trying to reclaim funds for
unfinished activities. For this reason many programmes demand bank guarantees from
Financial Management Handbook
49
private partners. Secondly, once a private partner enters a project, the funds it spends
become subject to the same controls as all other Territorial Cooperation funding and this is
particularly important when ensuring that private partners are only reporting real costs and
are not making a profit from their involvement. Private partners are often unhappy about
these arrangements, which require them to allow full access to their accounts by outside
controllers. Finally there is the question of compliance with State Aid rules. These rules were
established to prevent unfair distortion of competition through public support to private
companies. There are strict threshold values and rules regarding how such payments can be
made and any programme that funds the private sector must carefully monitor compliance
with these rules.
In the new programming period 2007 2013 it will again be possible to include private co-
financing in the programme financial tables. The amount of private contribution will be
indicated at the start and will need to be approved by the European Commission as an
integral part of the operational programme. Consequently, these amounts will be binding and
the programme will need to provide the indicated shares of public and private funds. In case
programmes provide more private co-financing than stated in the financial tables, it will not be
regarded as revenue and will not have to be deducted from the ERDF claimed by the
programme but it will not generate additional ERDF. In case programmes are unable to
provide the agreed amount of private co-financing, it will be possible to replace the missing
part with public co-financing. However this mechanism will not work the other way round as it
will not be possible to replace the missing public co-financing with the private co-financing.
This is because by agreeing the overall financial tables at the beginning of the programme,
Member States have committed themselves to providing a certain amount of public funding to
the programme. Replacing that with private funding later in the programme means that they
no longer meet their commitments. In conclusion, private funding can be increased but public
funding cannot be decreased.

The easy solution to private sector involvement

Most programmes do not include private co-financing in their financial tables. Private
enterprises are welcome to take part in project activities but they cannot receive ERDF
payments and their financial contribution cannot be used as co-financing.

An exception has been made in some programmes for organisations acting in a public-
similar way for the purposes of the project. In these cases, private organisations can get
ERDF in the same way as public organisations (even though there is no private co-
financing in the financial tables).

There has been quite a lot of discussion about the definition of public-similar. Most
importantly, no profit can be made during or after the project, all project results must be
made freely available to the public and partners have no physical or intellectual ownership
rights. ERDF funds in these cases cannot be used for business start-up, funding regular
operations or acquiring assets. This system allows the easy incorporation of businesses
providing services like research and organisations covered by private law such as the
French associations.

3.1.4 Own contribution
As noted above, funding comes from many different sources and in many cases the
organisations actually participating as project partners will provide their own contribution. This
is worth mentioning as such contributions are often not paid as cash: There is little value in
paying funds out of an organisation only to pay them back at a later date. Such contributions
tend therefore to take the form of services such as paid staff time and office space. Most
such contributions are covered by the eligibility rules on in-kind contributions, which cap the
maximum value allowed. One exception is paid staff costs, which count as an in-cash
contribution are not subject to any limits under the regulations. It is therefore possible for
participating organisations to fund their whole contribution through staff costs and
Financial Management Handbook
50
programmes need to pay particular attention to ensuring that these are real costs based on
standard rates.

Financial control and rules governing co-financing

As soon as co-financing is allocated to a project, it becomes subject to the same
regulations and controls covering all Territorial Cooperation spending. All co-financed
expenditure must therefore be included in standard financial controls because if it is spent
on ineligible costs, the ERDF grant will have to be reduced in proportion.

Many co-financing organisations, however, insist on carrying out their own controls to
ensure that the co-financing has been spent in accordance with internal financial
management rules. As this control must be additional to the programme controls and
cannot replace them, these results in considerable duplication of effort. Most problems
actually tend to occur when co-financing is still regarded as a component of e.g. regional
funds and is not distinguished as programme funds. Projects, for example, sometimes
need to transfer funds across the border to other partners to pay for shared activities.
Internal budgetary rules governing project funds must be flexible enough to allow for this
type of transaction. This is not always the case.

3.1.5 Letters of Commitment
In addition to proof that co-financing is being paid (provided through the statements of
expenditure), programmes also require proof at the project application stage that co-financers
are aware of the project and have allocated funds for financing it. This proof is in the form of
Letters of Commitment, which guarantee that each co-financing organisation will provide a
set amount of funding to the project. They are required for the full amount of co-financing.
Some programmes have experienced significant problems with co-financing organisations
refusing to pay the promised co-financing, while other programmes very rarely have
problems. Past experience will obviously influence the legal status that each programme
assigns to the letters of commitment. If the programme has had this type of problem, the
commitment to provide co-financing should be put on a contractual basis as soon as possible
so the original letter promising co-financing represents a legal commitment. If this cannot be
done, special provisions must be included in the project subsidy contract and partnership
agreements.
Projects sometimes have difficulty providing these documents to accompany the application
form. Applications tend to be worked on until the last minute but co-financers will not provide
the letters without having studied the final application. Programmes therefore need to take a
pragmatic approach and rather than rejecting or delaying an application to the next
application round, allow projects to submit these documents up to the day on which the SC
meets. Projects unable to provide the documents by this date should not be approved as the
partnership is not in place.

Sources and uses of programme funds: Summary

Regardless of their original source, once allocated to a project all funds are subject to
the rules governing the Territorial Cooperation Objective
Requirements in the regulations are the minimum standards for implementing
Territorial Cooperation programmes
Programmes should not monitor allocations or spending by Member State or region.
Funds allocated to the programme enter a common pot
Programme resources should be allocated to projects on merit and regardless of
location - if one region / country is under-performing in project generation, programmes
should assist them rather than provide funding guarantees

Financial Management Handbook
51
3.2 Programme financial tables
The programme financial tables in the OP provide the basic information required for financial
management on the programme level. They indicate the flow of funds into the programme
and because of the de-commitment rule also dictate the rate at which funds must be spent
and claimed (e.g. maximum three years after they have been committed to the programme
for N+2 programmes). As such they provide the baseline against which annual targets can be
set and performance measured. In case a programme decommits part of its ERDF, the
programme financial tables need to be reprogrammed in order to reflect the modification in
funds allocation.

Key elements of programme financial tables:

Must be in EURO regardless of currencies in participating Member States
There should be no breakdown by Member State or region
Show the ERDF allocation for each priority and each year, the total amount of public/
equivalent funding and estimated private funding (if used)
Show separately estimates of non Member State funding
Need to be reprogrammed if a programme decommits funds

Example of programme financial table in 20002006 (showing split by year)

Member States EURO
Total ERDF Total Central Regional Local Other
1=2+13 2=3+8 3 4 8=912 9 10 11 12 13 16
TOTAL YEARS
2000 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0
2001 38.831.506 38.831.506 19.415.753 19.415.753 19.415.753 5.582.031 4.611.241 4.611.241 4.611.240 0 0
38.831.506 38.831.506 19.415.753 19.415.753 19.415.753 5.582.031 4.611.241 4.611.241 4.611.240 0 0
2002 43.932.800 43.932.800 21.966.400 21.966.400 21.966.400 6.315.341 5.217.021 5.217.019 5.217.019 0 0
43.932.800 43.932.800 21.966.400 21.966.400 21.966.400 6.315.341 5.217.021 5.217.019 5.217.019 0 0
2003 43.742.228 43.742.228 21.871.114 21.871.114 21.871.114 6.287.946 5.194.390 5.194.390 5.194.388 0 0
43.742.228 43.742.228 21.871.114 21.871.114 21.871.114 6.287.946 5.194.390 5.194.390 5.194.388 0 0
2004 45.083.526 45.083.526 22.541.763 22.541.763 22.541.763 6.458.801 5.360.988 5.360.987 5.360.987 0 0
45.083.526 45.083.526 22.541.763 22.541.763 22.541.763 6.458.801 5.360.988 5.360.987 5.360.987 0 0
2005 47.500.308 47.500.308 23.750.154 23.750.154 23.750.154 6.761.908 5.662.750 5.662.749 5.662.747 0 0
47.500.308 47.500.308 23.750.154 23.750.154 23.750.154 6.761.908 5.662.750 5.662.749 5.662.747 0 0
2006 50.218.560 50.218.560 25.109.280 25.109.280 25.109.280 7.103.427 6.001.953 6.001.952 6.001.948 0 0
50.218.560 50.218.560 25.109.280 25.109.280 25.109.280 7.103.427 6.001.953 6.001.952 6.001.948 0 0
TOTAL 269.308.928 269.308.928 134.654.464 134.654.464 134.654.464 38.509.454 32.048.343 32.048.338 32.048.329 0 0
Total ERDF 269.308.928 269.308.928 134.654.464 134.654.464 134.654.464 38.509.454 32.048.343 32.048.338 32.048.329 0 0
Structure
Total
Eligible
cost
Public expenditure
Private
Elig. Cost
Other
financial
instruments*
Total
Public Elig.
Cost
Community participation National public participation

The example above is from the current programme period. In future the split between
national, regional and local sources of co-financing will not be required. Column 4 shows the
annual ERDF commitments to the programme and will thus set the spending targets for the
programme. Other essential information is also included:
Separate information on the budget for participating Non-Member States. The table
above covers all participating Member States but if Non-Member States such as Norway
and Switzerland are participating, a separate table will have to be provided showing their
contribution. This allows programmes to ensure that allocations to partners from these
countries do not exceed permitted levels (i.e. the amount these countries have paid into
the programme). This will continue to be the case for Norway and Switzerland in the new
period. Most other participating non-Member States will be covered by the IPA or ENPI
17
.
Some programmes in the current period have also included a split by Member State
based on each countrys allocation to the programme. This will not be permitted in future.


17
Instrument for Pre-Accession and European Neighbourhood and Partnership Instrument
Financial Management Handbook
52
A breakdown of funding by priority (including one for TA) Included in a separate table.
This indicates the general split of funds across the programme and ensures that spending
is appropriately distributed across programme objectives
Public and private co-financing. The table above has public co-financing only. Any
planned private contribution would be included in column 13. Programmes can choose
one of two ways for calculating the total programme funds using either total eligible
expenditure or total eligible public expenditure. If the tables are based on total eligible
expenditure, private sector co-financing can be included. Additional public funding can be
used to replace private funding but if, on the other hand, there is more private co-
financing than is included in the tables, the difference will be counted as programme
revenue and the ERDF grant will be cut.
Example of programme financial tables in 2007 2013
Programme financial tables in the new period will be simplified offering flexibility to
programmes. According to EC 1080/2006 12.6, each OP shall contain 2 financial
tables. The first one should break down for each year the amount of the total
financing appropriation envisaged for the contribution from ERDF. It is much simpler
compared to the tables required in the current period as it only gives information on
the ERDF budget available each year.

Programme financial table: Split by year

Year ERDF

2007

2008

2009

2010

2011

2012

2013

Grand Total
2007 2013

Programme financial table 1, EC 1080/2006 12.6a
The second programme financial table required in the new period specifies for the whole
programming period, for the OP and for each priority axis, the amount of the total financial
appropriation of the Community contribution, the national counterparts, and the rate of ERDF
contribution.
Financial Management Handbook
53

Programme financial table: spit by priority axis and financing source

For information

ERDF
(1)
National
public
(2)
National
private
(3)
Total
funding
(1)+(2)+(3)

Co-
financing
rate
EIB Other
Priority
Axis 1

Priority
Axis 2

Priority
Axis

Total

Programme financial table 2, EC 1080/2006 12.6b
3.3 Priorities and measures

Priorities and measures: Summary

Programmes are managed through a number of thematic priorities
Each priority has a separate budget allocation
Allocation and spending in each priority should be closely monitored
Movement of money between priorities requires new financial tables approved by the
Commission
Final changes to the financial tables in the current programmes must have been
submitted for the Commissions approval by 31 December 2006
Priorities can be used for managing sub-programmes
There will be no measures in the new programme period

The programme budget is divided between a number of different priorities, defined as:
One of the priorities of the strategy in an operational programme comprising a group of
operations which are related and have specific measurable goals;
18
The allocation of funds between priorities ensures that different funds are targeted at different
objectives and each priority will receive a higher or lower share of the total funds depending
on its importance. Typically there should be 3 or 4 priorities in each programme in the new
period.
Current programmes are also managed through priorities but each priority is also divided into
a number of more detailed measures. There is a separate budget allocation for each priority
and measure (though the split between measures is not included in the programme financial
tables). In future there will be no measures and the priorities will instead be managed through
quantified targets set for each priority (the measurable goals referred to above). These
quantified targets should provide a useful tool for monitoring the distribution of programme
funds across priorities and give a clear indicator of when there is a need to allocate additional
funding to under-performing priorities.


18
EC 1083/2006 General Regulation, 2 (2)
Financial Management Handbook
54
The movement of money between priorities (sometimes called virement) requires
Commission approval as it can imply a shift in programme focus (if most funds are taken out
of the environment priority and put into transport for example). Generally, however, there
should only be a need for this type of transfer in the later stages of the programme when
funding is running out and, in particular, after unspent funding is returned to the programme
by the projects. This unspent funding returns to the priority from which it was originally
allocated and problems can arise if very small amounts are returned to one priority and there
is not enough to fund a worthwhile project. These amounts can therefore be moved so that
one priority has enough money to fund a good project. Other movements of funds are related
to project performance against the targets for each priority. If it is clear that the targets for one
priority will be met but other priorities have not yet reached their goals, there can be
arguments for providing additional funds to the weaker priorities.
Final changes to the financial tables for the current programmes must have been submitted
for approval by 31 December 2006
19
. Project implementation and programme spending can
in theory continue until 31.12.2008 (though in practice all project spending needs to be
completed well before this to complete financial control and closure procedures). The final
programme statement of expenditure to the Commission must therefore comply with the
limits set in the tables submitted over two years before closure and this can be complicated if
projects return funds and new actions are launched to try to absorb this money. In the final
years of the programme it is therefore important that allocations and spending in each priority
are monitored closely. Programmes where private co-financing is included in the financial
tables or different ERDF rates are applied should see the section on calculating the final
payment for a description of how the 2% flexibility rule is applied.
Finally, priorities are also used in the management of sub-programmes. Particularly where
programme areas have been combined, sub-programmes are often used to ensure that
programme activities remain closely linked to local institutions and populations. Assigning
each sub-programme a priority means that the budget for each sub-programme can be easily
monitored and funds can be relatively easily transferred out of under-performing sub-
programmes. Some programmes using this system in the current period have experienced
problems, however, as sub-programmes do not agree to release funding until it is too late for
the other parts of the programme to absorb the funds and avoid de-commitment problems.
Agreements therefore need to be in place to assess degrees of under-performance and when
money should be transferred. Alternatively, a general agreement about the funding split
between sub-programmes can be made outside the framework of the priorities. All sub-
programmes can then use the same thematic priorities and actions to compensate under-
performance of one sub-programme will not require a Commission decision.
3.4 ERDF grant rates in the new period 2007 2013

New ERDF grant rates and their implications

The new grant rates are 75% or 85% ERDF maximum applied at programme level
Different grant rates may be applied to different priorities with a minimum 20% and
maximum 100% ERDF contribution
Transfer of funds between priorities with different grant rates will be complicated
Claims to the Commission may be capped if different priority rates are used
With higher grant rates, allocation and the risk of under-spend will be concentrated in a
smaller number of projects
Higher ERDF grant rates imply a substantial cut in co-financing going to projects
Higher ERDF grant rates imply smaller total programme budgets
Some programmes are considering using lower ERDF grant rates to avoid reduced co-
financing contributions
Different ERDF grant rates in neighbouring programmes bring a danger of funding
competition


19
Draft Guidelines on closure of assistance (2000-2006) from the Structural Funds.
Financial Management Handbook
55
It was stated above that programme funds were made up of 75% ERDF and 25% co-
financing. In actual fact, the situation is more varied than this and will be even more so in the
coming period.
Current period 2000 2006
In the current period, the percentage of ERDF funding granted to projects varied according to
the region where the project partner was located: The standard rate was 50% but regions in
the less wealthy Objective 1 areas received 75%. This meant that two partners from the
same project might have different grant rates and this has been very difficult to manage.
New period 2007 2013
In future, all project partners in the same programme will be eligible for the same rate of
ERDF funding either 75% or 85%. The two different ERDF rates depend on the GDP of the
participating Member States with 85% ERDF for programmes including a new Member State,
Greece, Portugal or one of the east German lnder. All programmes including at least
one of these countries will use the 85% rate (though see below). All other
programmes will use the 75% ERDF rate. Co-financing will therefore be reduced to 15% or
25% respectively.
It is, however, important to note that these rates are maximums and are applied to the
programme level. This means firstly that programmes may adopt a lower ERDF rate for the
whole programme if they can gain the support of participating Member States. This can be
essential if total programme budgets are not to be cut significantly (see the info box below).
Secondly, different ERDF rates may be applied to different priorities with a minimum of 20%
and up to a maximum of 100%. The most urgent priorities may therefore be funded at a
higher rate to encourage applications (though 100% ERDF funded projects imply a risky lack
of financial commitment from participating partners). Finally, different projects within the same
priority may also be funded at different rates: The only requirements are that decisions are
taken on the rates for the priorities when the programmes financial tables are drawn up and
that the costs reported for the programme as a whole do not exceed the 75% / 85%
maximum.

Why some programmes are rejecting 75% ERDF

The increase in ERDF payments is a real benefit to projects as it greatly reduces the
amount of co-financing they will have to find. On the programme level, however, it reduces
the funds available for the programme area considerably. For example:

2000-2006 2007-2013

Programme ERDF budget 100 million 100 million
ERDF rate 50% 75%
Co-financing provided 100 million 33 million
Total budget available 200 million 133 million

As a result some programmes in Member States where finding co-financing has not
generally been a problem in the past have already decided to keep the 50% ERDF rate.
Other programmes will see an increase in the ERDF budget, which will offset the
reductions in co-financing. Others again accept the reduction as a necessary consequence
of improving a difficult co-financing situation.

One unfortunate consequence is that there may be funding competition between
overlapping programme areas with regions eligible in two programmes choosing the one
with the higher ERDF grant. This again needs to be monitored and tackled if the problem is
emerging.

Financial Management Handbook
56
A certain amount of caution will be required if different rates are used for each priority. If
priorities with low ERDF rates do not attract enough applications, it will not be possible to just
transfer these funds to another priority because of the different funding rates being applied.
The final programme statement of expenditure still needs to show 75% ERDF and 25% co-
financing or 85% ERDF and 15% co-financing and managing this while moving funds
between priorities with different funding rates may be challenging as is shown in the example
below.

Moving funds between priorities with different ERDF rates

Example:

Priority 1

Priority 2

ERDF rate 50% 80%
Funds transferred 10.000 0
Value with co-financing 20.000 12500

As can be seen, if funds are moved to a priority with a higher ERDF rate, the value of
these funds shrinks because the co-financing provided is smaller. This means that the
programme will not provide all of the required co-financing and risks a cut in the ERDF
contribution. There are many possible solutions but the missing co-financing must be
provided somehow.

Claims to the Commission may also run into related difficulties if different rates are used.
Spending in a given period will be weaker in some projects and priorities than others. If
projects with one grant rate under-perform while those with another do well, the spending
reported to the Commission may not reflect the required split between ERDF and co-
financing.

Different priority rates and implications: Example

ERDF rate by priority
(Programme =75%)

60% 75% 90% Total
Reported expenditure by
priority

50 75 100 225
Total ERDF reported

30 56.25

90 176,25 (=78.3%)
Total co-financing reported

20 18.75

10 48.75 (=21.6%)

Solutions have already been proposed in the Communication from the Commission on the
simplification, clarification, coordination and flexible management of the structural policies
2000-06
20
. Two possible solutions can be applied and are already used in similar situations
in existing programmes. Under payment option A (see section 9.3.2 of the communication),
the Commission caps payments at 75% ERDF. In the example above, the Commission would
pay only 168,75. The remainder of the ERDF claimed would be held until a future claim
included less than 75% ERDF. At this point the remaining funds would be paid out provided
that total payments did not exceed 75% ERDF. It should be noted that all ERDF claimed
counts towards meeting de-commitment targets even if it has not been paid because of
capping.


20
C(2003) 1255 Communication from the Commission on the simplification, clarification,
coordination and flexible management of the structural policies 2000-06
Financial Management Handbook
57
This on-going monitoring and revision of payments should be quite easy to manage but will
not prevent all problems at programme closure: Projects rarely spend their full budgets so
different small amounts will probably be returned to each priority too late for recycling. This
means that the total ERDF spend declared at the end of the programme may again be
lacking part of the co-financing if high ERDF grant priorities have spent most. The amounts
concerned should, however, be relatively small and it will hopefully be possible to cover them
with interest money. The situation does however need to be monitored.
There is also a second payment option option B. Under this procedure the Commission
pays the full amount on every claim even if it is above the programme ERDF grant rate. In
return it demands written guarantees that the rates will stabilise back to 75-25 (or whatever
rates are in use) by the end of the programme. Obtaining these guarantees is often simply
too complex for a cooperation programme and is advised against though some
programmes have done it successfully in the current period. Obviously, programmes using
this procedure still run a risk of small imbalances between the proportions of ERDF and co-
financing reported at the close of the programme.
Many cross-border programmes also use variable ERDF rates for projects within the same
priority. For example, some programmes simply regard some projects as less important for
achieving programme objectives and reduce the grant rate accordingly. Others use sliding
scales with grants being reduced for each application for similar activities therefore
encouraging projects to develop financial independence. At an extreme, a cross-border
programme might make a grant to a much larger infrastructure project at a rate as low as 2%.
It is not, however an optimal solution. 100% of the expenditure of the large project will then
be subject to Territorial Cooperation rules and financial control and this an unnecessary
complication. Most programmes prefer therefore to ask for applications from sub-projects
focusing on the cross-border dimension of larger projects. The sub-project might still
represent 2% of the total expenditure but can be given a grant at the normal rates without
bringing the rest of the project into programme control procedures.
One important recommendation needs to be observed if variable grant rates are awarded to
individual projects: Treat the priority rate as a maximum and only adjust ERDF downwards. If
higher rates are also used, financial managers will have a constant struggle to balance ERDF
and co-financing and there is a high risk that some co-financing will be missing at the close
of the programme. In addition, transparency requires that projects are informed of the likely
grant rate before submitting an application, that the criteria for deciding grant rates are
publicly available and that formal written decisions are provided recording the reasons for any
reductions.
Implications
Regardless of which of the two new rates a programme is using, there are major changes
from the current period and there is a risk to be managed here. The programmes ERDF will
be absorbed by a smaller number of projects each receiving a larger grant than the 50% most
would have got under the current programmes. Allocation and the risk of project under-
spending may therefore be expected to be concentrated in a smaller number of projects and
avoiding under-spend becomes even more important.
Financial Management Handbook
58
3.5 The Technical Assistance (TA) budget

Summary

The TA budget funds programme operating costs
Programmes should present a Business Plan at the first meeting of the MSC explaining
how the TA budget will be spent. The Business Plan should be updated annually to
reflect progress, changes in objectives and activities, efficiency savings and resources
required for the coming year
The most satisfactory approach to making national or regional contributions to the TA
budget is to secure advance payments based on detailed forecasts of activities and
budget requirements over the year ahead
It is important to apply cost control to the TA budget, particularly in smaller
programmes where fixed costs take up a larger amount of the budget. Interest arising
from Member State or regional contributions to the TA budget can be spent on
general measures to support the programme
There is a substantial change in the new programme period: TA budgets will be
capped at 6% of total programme funds (According to the current interpretation of
regulations)

One of the priorities in the financial tables will also show the TA budget or operating costs for
the programme. This is financed in the same way as all other costs with an ERDF
contribution and a co-financing component. The programmes TA budget is kept in a separate
bank account to ensure that there can be no confusion with other programme funds.
Current period 2000 2006
The TA budget to fund programme administration is currently split into two headings. One
covers staff, training, office, travel and accommodation, programme meetings, audit and
financial control, financial management, employer costs and miscellaneous. This should
constitute no more than 5% of total programme funds. The second heading covers other
expenditure such as seminars, studies, evaluation, computerised management systems and
communication costs and there is no ceiling (other than what is approved in the programme
financial tables). Big programmes have tended to set aside 5% for all TA activities while
smaller programmes have made use of this flexibility to increase total TA budgets to as much
as 10%.
New period 2007 2013
In the new period, the TA budget will not be split in this way and the limit for technical
assistance covering all activities will be 6% of the total programme funds meaning a cut for
some programmes. (This is according to the current interpretation of regulations and this may
be changed in the future, i.e. TA budget may be calculated as 6% ERDF contribution to the
programme). The fact that TA is based on a percentage of total programme funds has always
been problematic for small programmes and will continue to be so. Small programmes have
previously made most use of the flexibility to increase overall TA budgets: Since the fixed
costs of operating programmes tend not to vary greatly, there is less freedom for smaller
programmes to adjust their level of activities and associated costs. So, the smaller the
programme, the greater the importance of closely monitoring the TA budget.
Even programmes increasing their TA budget from 5% to 6% may well face a fall in the actual
funds available because of the new ERDF and co-financing rates (see the info box below).
With more bodies (such as the AA) potentially able to claim TA funds, there will be a real
need for strict budgeting.
Financial Management Handbook
59

Calculating the TA budget (2007 2013)

In the new period thought needs to be given to the co-financing rate applied to the TA
budget. In the current period, the TA budget has generally consisted of 5% of the total
ERDF budget and has been co-financed at 50% by the Member States.

Example 1: TA in 2000 2006

ERDF for programme: ? 100.000
TA = 5% of ERDF: ? 5.000

+50% Member State TA co-financing: ? 5.000

Total TA: ? 10.000

In the new period the ERDF financing rate is e.g. 75% with only 25% Member State co-
financing. If these rates are applied to the TA budget, it may lead to a cut in the budget
available:

Example 2: TA in 2007 2013

(75% ERDF and 25% MS co-financing rates for TA

75% ERDF for programme? 100.000
25% MS co-financing: ? 33.000

Total programme funds: ? 133.000

TA: 6% of ? 133.000 = ? 7.980
Total TA = ? 7.980

This example uses a 75% ERDF rate. Obviously, the situation will be worse in programmes
with an 85% ERDF rate. In large programmes this kind of TA cut may be acceptable as there
will still be enough money to carry out activities. In others (especially small programmes) the
possibility could be used to vary the co-financing rate between priorities. The TA priority could
still be co-financed, for example, at the 50% etc, ensuring no cut in TA funds. This situation is
presented in example 3 and 4.
Example 3: Programme uses the flexibility rule allowing it to decide different grant rates for
different priorities
Calculation of TA in 2007 2013 in case of 75% ERDF and 25% MS co-financing for all
priorities with the exception of 50% ERDF and 50% MS co-financing for TA priority
75% ERDF for programme: ? 100.000
25% MS co-financing: ? 33.000

Total programme funds: ? 133.000

If 75% - 25% rates were applied to TA, TA budget is: 6% of ? 133.000 = ? 7.980

ERDF contribution to TA: 6% of ? 100.000 = ? 6.000 an the ERDF rate in this case is 50%

MS contribution to TA: 6% of ? 100.000 = ? 6.000 since MA agreed a 50% co-financing rate
Total TA budget: ? 12.000

In this example, 75% - 25% rates are used for all priorities except TA. This represents a
situation where MSs participating in the programme have agreed different rates for TA: 50%
ERDF and 50% co-financing in order to get a higher TA budget. It is possible for MS to agree
a higher co-financing rate for the selected priorities, e.g. TA as long as it does not influence
the co-financing amount promised by MS.
Example 4: Programme uses the flexibility rule allowing it to decide different grant rates for
different priorities
Calculation of TA in 2007 2013 in case of 85% ERDF and 15% MS co-financing for all
priorities with the exception of 50% ERDF and 50% MS co-financing for TA priority
85% ERDF for programme: ? 100.000
Financial Management Handbook
60
15% MS co-financing: ? 17.5

Total programme funds: ? 117.600

If 85% - 15% rates were applied: TA budget: 6% of ? 117.600 = ? 7.056

ERDF contribution to TA: 6% of ? 100.000 = ? 6.000 an the ERDF rate in this case is 50%
MS contribution to TA: 6% of ? 100.000 = ? 6.000 since MA agreed a 50% co-financing rate
Total TA budget: ? 12.000

In the example 4, 85% - 15% rates are used for all priorities except TA. This example again
represents a situation where MS participating in the programme have agreed different rates
for TA: 50% ERDF and 50% co-financing in order to get a higher TA budget. As previously, it
is possible for MS to agree a higher co-financing rate for the selected priorities, e.g. TA as
long as it does not influence the co-financing amount promised by MS.
To justify TA budget proposals it is advisable to present a Business Plan to the first MC
setting out resources needed for operation of the programme over its life, including staffing
levels needed in the various phases, and a more detailed account of resources required for
the next two years of operation. The TA budget should also be adjusted to reflect experience
with costs under the different headings. Cost accounting of conferences and seminars is
essential in order to fully predict the financial implications of proposals to, for example,
increase the number of seminars or brochures. The costs under some TA budget headings
are more predictable than others. For example, once office space has been hired and staff
appointed, costs can be predicted fairly accurately. However, the variable number of people
attending events, which affects for example catering costs, is more difficult to predict.
In order to monitor costs, TA budgets should be broken down further and on a monthly basis.
The headings used to plan and monitor TA budgets are typically very similar to those for the
projects with staff, overheads, travel and accommodation and publications. Some larger one-
off costs such as establishing monitoring systems and websites are treated separately.
Once outline budgets are approved, the bodies claiming TA funds should be given relative
freedom of action within the approved budget. Some programmes have in the past asked for
very detailed information about the TA budget and required committee approval for even
quite small amounts of expenditure by programme management bodies. If the level of detail
is too great, these requests may interfere with programme work. In principle, the information
presented about the TA should be on the level of budget lines with main activities and targets
presented in a Business Plan.
Since Member States co-finance the budget, the first MC should also agree a method of
securing contributions from the participating countries or regions. There are no formal
requirements for how contributions from countries to the TA budget should be made.
Experience shows that the most satisfactory approach is to secure annual advance payments
of TA co-financing calculated pro-rata from MS contributions to the programme and based on
a detailed forecast of activities and budget requirements in the coming year. This ensures
that the programme has the necessary funds to carry out its activities. Any expenditure
incurred by Member States or regions carrying out some of the forecast activities should then
be reimbursed from the central programme TA account. This system allows proper
certification of claims and secures the audit trail.
An alternative approach is to allow countries to deduct expenses they incur during the course
of the year before making payment of any remaining TA contribution owed to the central TA
budget at the end of the year. This makes life difficult for central budgeting and is less
desirable from the audit viewpoint as it is often impossible for the MA to know exactly how the
funds have been used. It also means that the programme is forced to use more of the 7%
advance from the Commission to fund TA activities. This is not the purpose of the advance,
which is intended principally as a fund for paying project claims.
Procedures for reporting on and monitoring TA budget expenditure should be set up as part
of the programmes control system. In many programmes expenditure incurred against the
TA budget by the secretariat and other programme bodies is checked by the MA for approval
before being passed to the PA for payment. The MA must also ensure independent audit of
TA expenditure (bearing in mind that it also spends from this budget). This is more difficult
Financial Management Handbook
61
where Member States or regions have spent their TA budget contributions directly rather than
contributing them to the TA budget and then invoicing this budget for payment. Programme
structures with large numbers of Intermediate Bodies can also drain the TA budget. Sufficient
funds must be retained for carrying out key programme functions.
TA expenditure is also an important aspect of meeting de-commitment targets for the first
years of the programme when project spending can be expected to be slow. Many of the
most costly TA actions (establishing websites and monitoring systems, preparing programme
publicity actions, running large scale events to attract project developers etc) should be
carried out in the first year of operations and TA may well be the only expenditure claimed in
2007. Although the share of TA in total programme expenditure is relatively low, this early
expenditure can mean that it is a key factor in meeting the first N+2 target.
Most of the current INTERREG programmes will continue in the new programming period.
The Commission has confirmed that these programmes will be able to use the current TA
budget to cover the costs related to the preparation of the new programmes. They will also be
able to use the TA budget from the new programme to cover costs related to the closure of
the current programmes. This includes e.g. costs of preparing and printing the final
programme report.
3.6 Additional Administration Tools
3.6.1 Bank accounts
In order to promote the joint management of funds, it is a requirement to be continued
under the new funding period that the ERDF contribution is paid into a single account with
no national sub-accounts. Similarly, ERDF payments should under no circumstances be
incorporated into regional and national budgets and accounts. If this happens, ERDF funds
become subject to national and / or regional limitations that are frequently in conflict with
Territorial Cooperation programme requirements (for example, concerning the need to
transfer funds to other Member States).
To enable the programme to get underway, the CA should open two EURO bank accounts:
One for the programme overall and one for Technical Assistance. This second account will
hold Member State and ERDF contributions to be used for meeting programme operating
costs. The ERDF contribution for technical assistance is initially paid into the programme
account and then transferred to the TA account. The separation of accounts is to avoid any
confusion between TA funds and those available to be allocated to projects.
3.6.2 Interest on programme accounts
The advance payment from the Commission, TA funds and any other funds the programme
holds before payments are made to projects should be placed in interest bearing accounts.
The interest gained is a useful source of additional funding for the programme.
There is one restriction on the use of the interest money: Any transnational financial
transaction charges incurred by the programme must be covered from the interest earned
(otherwise these expenses will be deemed ineligible). The remainder of the money belongs to
the Member States but it must be allocated to the programme. There are two ways of doing
this. Firstly, the money can be used to replace co-financing that participating Member States
would otherwise have provided (with the funds divided between Member States in proportion
to their original contribution to the programme). Alternatively, the interest can be used as
additional funding to increase the budget available in whatever priority it is assigned to. This
additional co-financing does not generate extra ERDF payments.
The allocation of interest money needs to be carefully considered. If it is used to replace
Member State funds (i.e. it is used as co-financing) there will be no change to the programme
but on the other hand these funds will then have no added value. If interest money is added
to programme funds, additional actions will be possible. It is not necessary to include interest
Financial Management Handbook
62
in the programme financial tables but annual and final reports must contain an explanation of
how the interest money has been used. Possibilities include funding extra projects,
compensating for small de-commitment losses, funding second level control activities and
preparations for the new programme period (it is eligible to use TA from the current period to
do this). It should be noted that interest money is subject to the same eligibility rules as all
other programme funds.
Regardless of how the funds are used, they all need to be spent by the end of the
programme period and the programme final report must include a section of how this money
was used.
3.6.3 Monitoring systems

The Monitoring system

Is a useful tool for programme management and needs to be put in place at the start of
the programme
Is a common database and should be shared by all programme management bodies
removing the risk of different bodies using different figures
Provides programme bodies with a quickly generated overview
Aggregates information on projects and provides an overview of programme progress
Tracks individual project spending and progress
Helps programmes spot serious under-performance

Monitoring systems consist of two important elements: The data that is collected and the
databases for handling this data. These systems need to be set up to fulfil regulations but
should also be a useful tool for financial management. Once more, the main factor in
developing useful systems is to ensure that they are put in place at the start of the
programme: Project applications, report forms and the monitoring system should all draw on
the same key data and all three need to be developed together.
Territorial Cooperation programme monitoring systems need to fulfil a number of different
requirements. Firstly, there is a need to track individual project spending on the one hand and
the progress of the programme on the other. Project monitoring should track performance
against financial targets and allow finance staff to check spending on different budget lines,
by partner etc. This information is used in processing and approving project claims and for
assessing project progress. This part of the system must provide reliable data and include
targets against which to measure actual performance.
Monitoring systems also need to be able to aggregate this information and provide an
overview of spending on priority level, programme level, for non-Member States etc. in order
to provide the information needed for reporting to the Monitoring Committee and making
claims to the Commission. The Implementing Regulation contains the minimum information
required
21
. This essential programme information must be accessible by the Managing,
Certifying and Audit Authorities
22
. In addition programme level monitoring should provide
information on achievement of the measurable goals for each priority.
Just as importantly, monitoring systems need to track activity progress alongside spending
and allow comparison between the two. Project application forms should provide enough
information to assign costs by year, by partner, by budget line and to the main work packages
and the monitoring system should mirror this. Progress on activities can then be monitored


21
List of data on operations to be communicated on request to the Commission, EC 1828/2006, Annex
III
22
Implementing Regulation, 14.1
Financial Management Handbook
63
for serious over or under-spending. There is no consensus on the exact information required
and programmes should base their decision on what they will need to know to spot problems.
Increasingly, the programme monitoring systems in place also automatically generate and/or
check a number of important programme documents such as financial tables for report forms.
Systems can be used to generate automatic warnings if budget lines are over-spent; to store
a record of important questions from projects and the programmes answers; to send
automatic reminders to programme staff when deadlines are approaching. Perhaps most
importantly, if all changes to budgets and financial tables are made directly in the system, this
removes the risk of different programme bodies using different figures. The staff who can
change different types of data need to be identified and a system of controls put in place.
This type of function can save a great deal of time on basic financial management tasks and
provide programme management with quickly generated overviews.
In the current period monitoring system development has been a process of constant fine-
tuning as programmes learn which data are most valuable. A separate study is available on
some of the systems developed
23
. The main problem should be easy to resolve and this was
simply that monitoring systems were not always developed early enough in the current
programmes. Another issue that has sometimes been difficult is when programme databases
are based on standard national systems for handling mainstream Structural Funds
programmes or standard software packages. Care is needed to modify these standard
systems to meet the particular requirements of Territorial Cooperation programmes, for
example, in the handling of different currencies or less or more frequent claims rounds than is
usual in the domestic system. In the worst cases, programmes have to operate two systems
because national systems are inappropriate to programme needs.
3.6.4 More on the Business Plan
Programme management needs to be planned on different timescales. The programme itself
provides a 6-8 year timescale but it is impossible to predict all of the situations that will arise
at the start of this period. The period between MC meetings (typically 6 months) provides
short-term action plans but there is a clear need for a mid-term planning tool (considering
approx. the next two years of implementation), which can forecast future developments with
reasonable accuracy and develop the programme response in time to launch effective
initiatives and secure the necessary resources (especially staff). This is the role of the
Business Plan setting out the main programme management activities that need to be
carried out. MC meetings should be used to fine-tune the plan, which then becomes the basis
for TA spending.
From experience, there is much value in preparing a Business and Implementation Plan. It
pulls together all the activities required of the different programme bodies and produces a
costed workplan for the coming years. This then forms the basis of the technical assistance
budget and coordinating work flows. Since the plan is in effect a statement of activity planned
by all programme bodies, they should all be involved in its preparation.
To realize the full benefit of the Business Plan, an accurate estimate of the costs and timing
should be made of all activities, including the approved staffing levels, office space, IT
resources required, publicity strategy, estimated number of MC and SC meetings for each
year of the programmes operation, etc.
The plan should be updated annually to take account of MC decisions and agreed action
following the mid term review of the programme. Reports on progress in implementing the
Business Plan should be submitted to the MC at least annually. They should review progress
in activities, and identify efficiency savings, new activities and resources required in the
coming year.
The plan is a useful tool for helping to keep control of the TA budget and monitoring costs as
well as in longer term management of resources for staffing. It also provides the basis for
seeking co-financing contributions to the TA budget.


23
Study on Selected Monitoring Systems published by INTERACT Point Managing Transition and
External Cooperation and available on the INTERACT website.
Financial Management Handbook
64

Financial framework: Summary

Current vs. new funding period

2000 2006

2007 2013

50% or 75% ERDF grant rate

2 grant rates:
Up to 85% ERDF programmes with new MS,
Greece, Portugal or one of the east Germany
lnder.

Up to 75% ERDF other programmes

Claims to the Commission may be capped if
different priority rates are used

Transfer of funds between priorities with different
grant rates can be complex

TA consists of two measures
Measure 1 capped at 5% of total programme
funds
Measure 2 uncapped
No breakdown of TA. 6% of all programme funds
for all TA activities (according to the current
interpretation of regulations, which may be
changed in the future, i.e. TA will be calculated as
6% of ERDF contribution to the programme)

Upon MS agreement, it is possible to use different
grant rates for TA

Simplified financial tables recommended by the
Commission

Some programmes monitored spending by MS

No split by MS in the programmes financial tables

National/regional sub-accounts for ERDF
sometimes exist
National / regional sub-accounts for ERDF must
not exist (official sub-programme funds are
possible)

Programmes should set up only two joint
programme bank accounts for:
Funds to be allocated to projects
TA

Priorities and measures in the programme
financial tables

Only priorities in the programme financial tables
Priorities will be managed through quantified
targets set for each priority

7% Advance Payment paid to programme at once
at the start
7% or 5% Advance Payment paid to programme
in annual instalments: 2%-3%-2% or 2%-3%.
Programmes liquidity in the first year may be
reduced

Financial Management Handbook
65
4. Operating Phase: Programme Level
This section considers in more detail how key financial management activities (Funds
Management, Payments to Projects, Certification of Expenditure and Monitoring Controls)
can best be run to help meet programme objectives.

Operating phase on the programme level: Summary

Reporting systems should underpin annual forecasts of payment claims, annual
implementation reports and certified payment claims to the Commission.
Reporting systems should continually review spend against targets and report to the
MC and SC on appropriate action if spending is below target.
The way in which allocations to projects are made at frequent intervals, to existing
projects for extensions, via waiting lists, without conditions can help speed up
spending
Recycling of funds unspent by projects before the end of the projects will give the
opportunity to fund other projects / extensions and may help avoid de-commitment. All
measures to recycle funds into existing or new projects require Steering Committee
approval
Interest on Commission advances provides additional resources for allocation to new /
extended projects.

Programmes enter their main operating phase when they start to allocate funds to projects.
The phase has two main objectives. Firstly, ensuring the quality of the operations funded
through effective selection, monitoring and control. Secondly there is programme efficiency:
The aim should be to make 100% use of funds by ensuring that nothing is lost to de-
commitment and that this process is part of day-to-day management and not an annual end
of year crisis. One key to success is to avoid slow and/or insufficient spending by projects.
Another, which forms the focus of this chapter, is the basic programme procedures governing
the granting, monitoring and payment of funds.
4.1 Allocation of funding
The approach taken to the allocation process has far reaching implications for funds
management. Programmes must ensure that allocations in the first years are sufficient to
generate enough actual spending to comfortably meet the first de-commitment targets. This
means removing barriers to allocation and project start-up and understanding the relationship
between how much is allocated and how much is likely to actually be spent.

De-commitment 2 (see page 13 for more)

As explained before, the Commission commits money to each programme on 1 January of
each year 2007-2013. If the money has not been used within three years (N+2) it is
deducted from the total allocation to the programme. The amount committed each year
therefore provides the spending target that must have been achieved three years later (or
four years in the case of N+3).

As usual, the situation is actually slightly more complicated than this. The amount of the
advance payment to the programme must be deducted from the amount of the first
commitment by the Commission in 2007 to provide the target for the end of 2009. This is
because de-commitment calculations are based on the amount the Commission has paid
out to the programme and the advance is counted as a payment. Furthermore, even
though the advance is paid over two or three years, the whole amount is deducted from
the first de-commitment target because:

Financial Management Handbook
66
Each payment shall be posted to the earliest open budget commitments of the Fund
concerned. (General Regulation, 76.1)

This means that the first de-commitment target is much easier to achieve than the targets
for later years. This compensates for the fact that projects take time to get started and very
little project expenditure can be expected in the first year of a programme.

2007 2008 2009 2010 2011 2012 2013 2014
2% 3%
N
N + 2
2007 2008 2009 2010 2011 2012 2013 2014
2% 3%
N
N + 2

Example: Calculating de-commitment targets in case of a programme working with
5% Advance Payment (3% - 2%)

Total programme ERDF budget: 100 million
Programme advance payment (5%): 5 million

Total ERDF committed to programme 01.01.07: 14.28 million
Total ERDF committed to programme 01.01.08: 14.28 million

Total to be spent by 31.12.09: 9.28 million (= First commitment advance)
Total to be spent by 31.12.10: 23.56 million (= Total of first target + second
target)

The same applies to programmes working with a 7% advance, as the final 3% instalment
will still be paid in 2009 in time to be counted towards the 2010 de-commitment target. One
final point applies to programmes working with N+3. N+3 only applies for the first half of
the programme period and in 2011 these programmes will switch back to N+2. This means
that at the end of 2013 these programmes must achieve the double target of spending all
the funds from 2010 and 2011.

2007 2008 2009 2010 2011 2012 20

13 2014 2015 2016 2017

N

N + 3

N + 3

N + 3

N + 3

N + 2

N + 2

N + 2

N + 2

2007 2008 2009 2010 2011 2012 20

13 2014 2015 2016 2017

N

N + 3

N + 3

N + 3

N + 3

N + 2

N + 2

N + 2

N + 2

Calculating N+2. Money committed on 1
January 2007 and unspent by 31
December 2009 will be de-committed.
Money committed in 2008 must be spent
by 2010 etc.
Double targets for 2013 in
N+3 programmes
Financial Management Handbook
67
There are two basic approaches to allocation: Some programmes allocate strongly at the
start to build up a good safety margin. Others prefer to spread allocations more evenly
throughout the programmes lifetime by limiting the amount of funds that can be granted at
any one meeting of the Steering Committee. This approach is risky and requires strict
monitoring and project budget discipline to compensate for the small safety margins. As a
result, projects under this system tend to be smaller and have a fixed and limited running time
(e.g. two years) making it easier to detect and take action against under-performance at an
early stage. Put simply, allocating a large proportion of programme funds in the early years of
the programme is safer and it is this approach we focus on.

Financial targets and safety margins

As explained above, the commitments of funds from the Commission and the threat of de-
commitment set the main targets for programme performance. Finance managers must
monitor expected TA and project spending against these targets and ensure that annual
spending will exceed the de-commitment threshold.

As can be seen, a large proportion of programme funds need to be allocated at an early
stage to provide a sufficient safety margin. It is also important to note that the annual
spending targets provided by the projects themselves are generally not a reliable way of
determining real programme spending forecasts. Projects tend to under-perform
particularly in their first years of operation and finance staff need to develop a picture of
the normal extent of this under-performance and adjust expectations about project
performance downwards.

To avoid de-commitment, it is crucial to get projects up and running early in the programme
cycle so as to generate payment claims at least in the second year after programme
approval. Given that project spending is generally slow at first, a large percentage of the
programme funds will have to be committed in the first two years of the programme if
reasonable de-commitment safety margins are to be established. It is difficult to provide exact
figures because they will depend very much on the projects approved (some projects, for
example, do achieve significant spending in their first year) so finance staff need to update
forecasts after every SC meeting.

Total
programme
funds
allocated
50 million

Forecast
project
spend 2010
(according
to project
budgets)
23 million

Expected
real
project
spend
2010
15
million
Expected
TA spend
2010
140.000

Committed
01.01.08 /
Target
31.12.10
13 million

Safety margin
2.140.000

Financial Management Handbook
68

Avoiding de-commitment: Three simple steps

Allocate a good proportion of funds near the start of the programme to generate project
spending.

Make sure projects set annual spending targets. Monitor and take action in cases of
serious under-performance.

Remove bottlenecks in programme administration (contracting, financial control etc.) so
projects can spend and claim.

The main requirement for this approach is a good supply of quality applications from the start
of the programme meaning that project development activities should start even before
programme approval and a significant proportion of TA funds in the first years of the
programme should be devoted to project development activities. The main drawback is that it
creates a funding gap in the later years of the programme when there are very few funds to
allocate to projects. This, however, is the price for avoiding de-commitment and keeping all
funds in the programme rather than returning them to the Commission.
Programme opinions vary on what sort of projects it is better to go for in the early years of a
programme. Large projects can provide significant spending and can spin off other projects
later in the programme. However, they can also be at higher risk of not spending all of their
allocation and can be slow to start spending creating major problems because of the scale of
funding involved. Short projects (i.e. two years) often progress well because of the time
pressure and make it easy to recycle money left at the end of a project in later years.
However, if these projects plan a follow-up, there may be disappointment if there is no
funding left for this purpose. One proposal for avoiding this problem is to approve the whole
project budget at the start but only release the second half of the grant on satisfactory
completion of the first half of the project (effectively creating two sub-projects). On balance, a
varied portfolio of different projects will spread the risk more evenly.
Of course, it is the Steering Committee that actually decides on which projects are approved.
Finance managers however need to guide the committee on the pace of allocations required
if de-commitment is to be avoided and the programme as a whole needs to ensure that there
are enough quality project applications available to meet the required pace of allocations. The
diagram below shows an approximate profile.
Financial Management Handbook
69

Programme safe allocation profile

"Safe" allocation profile
0
20
40
60
80
100
2007 2008 2009 2010 2011 2012 2013
Year
%

o
f

t
o
t
a
l

p
r
o
g
r
a
m
m
e

a
l
l
o
c
a
t
i
o
n

Clearly, this allocation profile creates a very different situation towards the end of the
programme allocation phase by which time funds are very limited. To manage the final
project approvals, the total budget available in each priority should also be announced to
guide applicants on the realistic levels of grants that can be expected. Finance staff have a
key role in trying to advise projects on realistic budgets at this stage (without encouraging
applicants to go for the maximum funding available). Some programmes advise funding
exploratory projects at this stage, which will generate early spending in the next programme
funding period when submitting full implementation proposals. Caution is needed here,
however. Exploratory projects should explore new concepts rather than developing actual
applications for the new period (an ineligible activity).
There can be difficulties when funds are running low. Often there are more eligible
applications than funds available and as a result some programmes have reduced the
budgets offered to the approved projects. This does not seem to be an acceptable way of
proceeding. A project cannot be expected to carry out the same activities in the application
with a significantly lower budget. If both budget and activities need to be changed what
exactly is the SC approving? The SC needs instead to take the difficult decision to reject
projects that would have been approved if there was enough funding. Finance staff need to
play a key role at this kind of meeting and to show the effects of each approval on the budget
remaining in each priority.
The allocation phase ends when the programme has allocated all of its funds. This must also
include as much as possible of the unspent project funds, which will be released back to the
programme budget as projects begin to close. Although the programmes run 2007-2013,
these are the years in which the Commission commits money to the programmes. The
deadline for spending the final funds in the new period will be 31 December 2015 (the N+2
deadline for the final funds committed on 1 January 2013). This means that all project
activities have realistically to be completed no later than June 2015 to allow the programme
to assess final reports etc. The last allocations for short study projects could therefore in
theory be as late as January 2015 so although the allocation process will certainly slow down,
it does not end until just before the end of the programme (the same timelines refer to the
current programmes with the deadline for spending set at 31 December 2008).
Financial Management Handbook
70
What went wrong with this process in the current programme period? Actually very few
programmes de-committed funds and the amounts involved were relatively small. This is
despite the fact that many programmes were delayed and started operations one or two
years into the programme funding period with few if any projects ready to apply for funding.
The ones that avoided de-commitment were the ones that were able to move quickly from
programme approval to allocating funds and which were not delayed further by administrative
problems. All programmes are being encouraged to submit their OPs to the Commission as
soon as possible in 2007 to avoid these problems in future though some programmes will not
meet this deadline. Any programme that has not been approved by the end of 2007 will
probably just lose the funds for this year.
A few programmes have been troubled by serious delays in basic administrative procedures
such as contracting and we look at some of the issues involved later in this chapter. Others
again have had to deal with completely new types of operations (the Regional Framework
Operations (RFOs) in the IIIC inter-regional cooperation programmes are a good example)
and the time involved in establishing these has led to de-commitment losses. In conclusion,
too much emphasis has perhaps been put on de-commitment very few programmes have
de-committed two years or more in a row. This is, however, partly the fault of the
programmes, as too many have been unable to provide realistic spending forecasts. The
unfortunate impression created is that meeting the targets has often been a matter of chance.

How to help ensure programme de-commitment security?

SC needs to be guided by finance managers on the required pace of allocation
Get projects up and running early in the programme cycle
Generate project payment claims at least in the second year after OP approval
Establish reasonable de-commitment safety margins by committing large percentage of
programme funds in the first two years

A good supply of quality project applications from the start is crucial
What sort of projects will you go for at programme start: Large or small & short?
Avoid unsound projects calling for conditional approval
Good programme spending forecast

4.2 Calls for applications
Closely linked to the allocation process is the approach to getting project applications for the
programme. Again, there are two basic approaches. Some cross border programmes allow
continuous applications, allowing project developers to submit an application whenever it is
ready. The allocations process continues until the funds in a priority are fully committed. This
approach is relatively straightforward and can result in quick allocations provided SCs are
held very frequently and/or some decisions are delegated to the programme bodies or taken
by SC members by written approval (often used for very small projects).
The other programmes and particularly the transnational and inter-regional programmes have
calls for proposals. These usually take place twice a year when funds are plentiful with SC
meetings following each call to decide which projects should be approved. This approach is
favoured largely because of the greater difficulty in holding meetings of transnational and
inter-regional representatives who, by and large, have to travel greater distances to meet up.
It also makes direct comparison of similar projects easier and so promotes competition for
funds (leading hopefully to quality gains).
The most common system to date has been to launch open calls whereby any project can
apply under any priority provided that there are still funds left in that priority. Towards the end
of the current programmes there has been a tendency to launch focused calls requesting
very specific types of projects to fill gaps in programme objectives. This may well become
more common in future because of the increasing shift to strategic projects, which will have
to fulfil stricter criteria. Other variations on the call system have also been tried. Sometimes
the total funds available for the call are limited to ensure that funds remain for later calls.
Financial Management Handbook
71
Flexibility is a must here, as it is ridiculous to reject or delay quality applications on this basis.
Some programmes limit calls to projects in certain priorities allowing a comparison of all
projects coming forward under these priorities and giving the programme the chance to get
specialist help on the themes concerned. This system can work provided that all priorities
have a call early in the programme to ensure that work on a particular theme is not
unnecessarily concentrated into the later years of the programme. Finally, almost all
programmes set indicative minimum and maximum project budget sizes. This is an essential
guide for project developers to decide on the scale of activities to be involved but again
requires a flexible approach to special cases exceeding these limits.
The continuous application system perhaps allows finance managers to better monitor the
flow of applications into the programme and the likely allocations at the next SC meeting. The
implications for financial management are, however, small. Both systems require a meeting
of the Steering Committee before projects can be approved and start so there will always be
some delay until this meeting can be held. The most important thing in both systems is to
ensure continuous project development activity and provide detailed advice to applicants so
that large numbers of high quality applications are received. All programmes should also
provide the date of the next SC meeting and the likely date for issuing contracts to successful
projects so project managers can set a realistic start date and with it a realistic budget for the
first part of the project.
4.3 Project approval and rejection
Decisions on project applications are taken by the SC according to criteria agreed by the MC
at the start of the programme. It is the responsibility of the MA to ensure that these criteria
are used and that the reasons for decisions are properly documented. The criteria should
include assessment of project budgets both in terms of value for money and the realistic
distribution of resources over activities and years. Finance staff should also consider the split
of funds between partners as an effective way of assessing the real involvement of different
organisations in the project.
The basic decisions open to the SC are approval or rejection. In some cases rejections are
given with an invitation to re-apply if project activities are generally good but some
modification is needed or the SC wants two projects to combine their ideas. A fourth type of
decision has also been used and is often related to doubts about project finances:
Conditional approval. Under conditional approvals, the project is allowed to go ahead
provided that it makes a number of modifications. These generally involve budget cuts and
the conditions have to be fulfilled before a grant offer letter or subsidy contract is issued (or in
some cases before the first project claim for payment is submitted).
Opinion is divided about whether projects should be approved with conditions and the
success of the procedure depends very much on the attitude to setting conditions and making
sure they have been fulfilled.
Financial Management Handbook
72

Ground rules for conditional approvals

Only set clear conditions. Make sure that asking whether conditions have been met
can be answered with a simple yes or no.
o E.g. Include one German regional partner

o Increase private sector involvement

Set clear deadlines for when conditions have to be met
o E.g. Within two months

o Before a contract will be issued

Do not set conditions that fundamentally change the project
o E.g. Add a publicity work package

o Remove the research work package

Reduce the budget by 250.000

Do not allow the conditions stage to drag on. Either the conditions are met in time and
the project is approved or they are not and the project must re-apply.

Conditions that break these basic rules are likely to be the result of requests for quite major
project changes. In such situations the correct approach is to instead reject the project and
ask it to return with a sound application that can actually be used as the basis for
contracting and implementation. Major changes to budgets are particularly common and
particularly problematic (and often stated by project managers as one of the most negative
features of programme management).

Programmes have to assume that budgets are based on a realistic assessment of the
resources required to complete activities. Budget changes can therefore be expected to
fundamentally change the activities that will be carried out. Of course, some budgets are
unrealistic but these projects should be rejected and asked to return with a usable budget;
budget conditions should be limited to fine-tuning as is done very successfully in some
current programmes.

There is, however, in many cases an unfortunate link between conditional approvals and
automatic co-financing (see section 3.1.3). It can be important for co-financers to get their
co-financing funds allocated by certain deadlines and one way of doing this can be to
approve bad projects with major conditions to try and make them better. This either takes a
long time or it never happens and the programme is stuck with weak projects.

Conditional approvals can also increase when programme calls for applications are
organised by priority, as it is not certain when a rejected project will have another
opportunity to apply under its theme. Again, flexibility is the key here by allowing these
projects to re-apply under any call.

Conditional approvals have sometimes led to long delays and considerable anger among
project developers. One benefit of these delays can be that they give programme
management a chance to get management of the project off to a good start. But it is better to
avoid unsound projects in the first place. For relatively minor conditions it may be appropriate
to write the condition into the subsidy contract and check that it has been met when the first
payment claim is made.
4.4 Contracting
The final step of the approval process before project operations can begin is issuing the
contract. Although programmes encourage projects to start as soon as they receive formal
notification of approval, many will not or cannot. Contracting should be a formality and
contracts should be standardised as much as possible. A maximum of two months should be
Financial Management Handbook
73
the deadline for issuing all contracts after a SC meeting. This obviously becomes impossible
if projects have extensive conditions to fulfil.
The contract is generally signed between the MA and the Lead Partner of the project. It
should include the approved application as the basis for the activities to be carried out and
the budget agreed, the start and end date for eligible expenditure, partnership members,
grant rate and control provisions. It must allow sufficient flexibility. Some programmes, for
example, are currently using contracts that do not permit transfer of funds across borders.
This will be unworkable once the Lead Partner principle becomes compulsory and the
documents will have to be changed.
The legal aspects vary enormously between different Member States but as a rule the
contract should be kept as simple as possible. In future programmes, all contracts should
also contain a requirement that projects are implemented in line with the budget provided (i.e.
that they meet annual spending targets). If this is not done and the programme loses funds to
de-commitment as a result, the contract should allow the programme to reduce the grants to
under-performing projects.
4.5 Basic programme financial flows
As soon as the first projects are approved, the programme cash flow can become an issue
particularly if there has been strong allocation in the first part of the programme to avoid de-
commitment. The advance from the Commission covers immediate operating costs and only
ex-post payments are made to projects (i.e. the money is spent first and then reimbursed by
the programme). The most important consideration is to ensure that generally speaking there
is always enough money to pay project claims as soon as possible after they arrive.
Financial Management Handbook
74

Basic financial flows

As can be seen the aim of the advance payment is to pay the first project costs before the
first claim is submitted to the Commission and to fund the TA activities required during start
up. Generally speaking problems tend to occur in the early stages if there are problems in
certifying project expenditure. There are very few cash flow problems as the totals of the
project claims received at any one time rarely exceed the amount of the Commission
advance. When cash flow problems are expected there are two basic approaches:
Small partners and limited resources. In some programmes average partners do not have
the funds to pre-finance project activities and they cannot afford to wait long periods for
programme payments. In these cases the aim is always to make payments as soon as
possible and to ensure that the programme always has sufficient funds in its account to
cover the claims expected. This requires reliable spending forecasts and quick
procedures for drawing up claims to the Commission. Programmes in this situation often
also use rolling reporting allowing projects to report and claim whenever they have
sufficient expenditure rather than according to set deadlines. This allows project partners
to monitor and manage their own cash flow.
Project spends own
funds and/or possible
advance payment of
co-financing. Partners
must have enough
own funds to start
project activities.
CA
approve
s claim

CA draws up
statement of all funds
paid to projects +
approved claims
awaiting payment +
TA expenditure
Commission
approves the claim
and makes
payment to
programme
account
Programme
(JTS/MA) approves
claim
No funds
available

CA initiates
claim to
Commission

Programme reporting
deadline: Project
provides report,
certified statement of
expenditure and claim
for payment
Approx 3 times
per year CA
makes a claim to
the Commission

Funds
available
from
advance

CA pays
project
CA pays
outstanding claims

Claim
cycle
repeated

?

?

Financial Management Handbook
75
Larger partners and good resources. Other programmes (and in particular the
transnational and inter-regional programmes) tend to have larger partners such as
regional authorities. These partners can often afford to pre-finance activities and wait for
payments. Here the advance is still used to make the first project payments but there is
less pressure on receiving the payment from the Commission before the advance is
exhausted: If there are no funds available, the last projects to submit a claim must wait
(and a clause in project contracts should explain that this is possible). Obviously, there is
still a need to ensure that projects do not wait too long for large amounts but the
programme can afford to submit a smaller number of larger claims to the Commission.
Even the biggest partners can have problems if payment is delayed until an unspecified
future date, particularly if this means that amounts claimed are not paid until the next
financial year.
Sometimes advance ERDF payments are also made to projects to finance their start up. This
is an effective way of minimising delays but involves a certain risk: If there are problems the
money will have to be recovered rather than just deducted form the next claim and recoveries
can be difficult. It should be noted also that these advance payments do not count as incurred
programme expenditure before the programme has certification that the project has actually
spent the money. This means that the programme cannot issue advance payments to meet
de-commitment targets.
4.6 Spending forecasts
Managing the correct rate of funds allocation and cash flows both depend on reasonably
accurate project spending forecasts: Programmes need to know how much will be claimed
and when.
Projects should produce their own spending forecasts in the budgets they submit with the
application but experience has shown that these are often inaccurate (this is discussed in
much more detail in the project section). This means that if project spending forecasts are to
provide a reliable basis for programme spending forecasts, they will almost certainly have to
be adjusted downwards in the early years of project implementation (i.e. the programmes
spending forecast is reduced rather than the actual project budgets). This adjustment should
be made based on data from earlier projects and only after this adjustment will most finance
managers have a reliable way of forecasting programme spending.
Once adjusted, individual project spending targets can be combined to provide a realistic
spending forecast for the programme. Programme experience of average project spending
performance can also be developed to predict the amount of funds that will have to be
allocated in a certain period if spending is to meet de-commitment targets. This will generally
show that large amounts have to be allocated in order to achieve even a relatively low spend
in the first two years of the programme. Until project budgeting becomes more accurate (and
there are limits to how accurate we can ever expect budgeting to be) this interpretation of
project data will be an important task for finance managers.
The project spending forecasts are aggregated and combined with the TA forecast to provide
the programme spending forecast for the Commission. This has to be sent by the end of April
every year and must cover the current year and the year to come. It is important to note that
these forecasts serve two different purposes. Firstly, they are a requirement from DG
BUDGET and are used by the Commission to make its own funding forecast to the Member
States. DG BUDGET therefore wants a forecast of how much the programme actually
expects to get paid in the year concerned and this should include amounts claimed but
actually paid out in the previous year. So this is the figure that should be sent in the forecast
to the Commission.
This figure is not, however, very useful for the programmes, which need to forecast how
much they will be able to claim from the Commission by the end of the year for de-
commitment purposes regardless of whether it is actually paid that year. Programmes
should therefore also keep this data, as it is an essential de-commitment management tool
(and they will almost certainly be asked for it by Commission Desk Officers).
Financial Management Handbook
76
Two different spending forecasts

The forecast sent to the Commission for 2008 should include the amount claimed in the
end of year claim for 2007 and the mid-year claim for 2008 and both of these amounts will
be paid in 2008. It should not include the end of year claim for 2008 because this will not
be paid until 2009. All claims for payment received by the Commission before 31 October
each year will be guaranteed payment in the same year and should therefore be included
in the forecast. Claims sent later should be part of the forecast for the next year.

Programmes, however, need to monitor how much they will be able to claim from the
Commission each year not how much is actually paid in that year because all amounts
for which the Commission receives a claim on or before 31 December each year count
towards meeting de-commitment targets. The programmes forecast will therefore cover
the claims included in each year.

In the past, programme forecasts have often been extremely inaccurate - in part due to
confusion about what is actually required. This has unfortunately contributed to the
perception that the INTERREG programmes are in some cases badly managed, as the
figures forecast bear little relation to the actual spend achieved. If effective project monitoring
tools are in place and project management is of a sufficient standard, the data for making
reliable forecasts should be easily available.
At least one common practice in the current period has made effective forecasting in some
programmes impossible. This is the granting of allow time extensions to projects. All
programmes are willing to consider this type of request from projects but approval should be
granted by central programme management bodies and implications should be integrated
into programme forecasts. In some cases however, Intermediate Bodies make this decision
independently with some programmes reporting that the number of projects given extra time
may be as high as 80%. Clearly this means that it is impossible to predict project spending
over time. In addition to the forecasting problems this presents, it also raises serious
questions about the quality of project management and the effectiveness of programme
cooperation. It also means that the management of N+2 becomes almost impossible as
programmes can never know what a project will actually spend in any given year.
4.7 Project claims for payment
The programme financial tables decide the required allocation and spending rates in the
programme. Project budgets give information on the contribution each project will make
towards meeting the financial targets each year (though project spending forecasts should
always be treated as being over optimistic, especially in the early months or years of
implementation). If the calculations behind the programme targets have been done properly,
the programme should not have any major problems as long as the projects are able to claim
and receive the funds they have been allocated.
In order for this to happen, the programmes payment claims cycle needs to run smoothly
from the start with quick certification and processing of project claims for payment. There are
a number of factors that influence this. Firstly, there is the decision on whether to have a
system of rolling claims (projects submit claims whenever they want) or to use set deadlines
for claims each year. The aim must be to get as much of the expenditure from each year
certified and included in the last claim to the Commission submitted at latest on 31 December
each year.

2007

2008

Programme claims to the Commission
Financial Management Handbook
77
The rolling claims system spreads the workload of those processing the claims and is
therefore particularly useful when a centralised first level control system is in place, as
small numbers of staff have to certify project spending. It also allows the projects maximum
flexibility and provided the minimum amount for the claim is not set too high, it gives small
project partners a good chance to manage their cash flow. The main problem with this
system is that some projects may decide to limit their administrative burden and not submit
claims for a long time even though they have incurred significant spending. The usual
response is for programmes to set a maximum time limit between claims and possibly a
deadline for submitting the first claim.
A fixed claim system allows programmes to predict their workload and plan other activities
around the claim procedure. It also ensures a regular flow of information on the
implementation status of all projects and makes it easier to decide when action should be
taken on under-performing projects. Nevertheless, when the programme is in its main
implementation phase, it may receive hundreds of reports and claims simultaneously. Some
bottlenecks and delays are inevitable.
Another important issue is the timing of the claim deadlines. There are two dates involved:
On the one hand the end date of a reporting period (usually 30 June and 31 December) and
on the other, the date by which the report and certified claim for payment have to reach the
programme. At the start of the current period, most programmes using deadlines asked for
reports to arrive around mid-February and the end of August in order to be able to prepare
the last claim for the Commission by 31 October (therefore allowing 1 - 2 months for the
project to draw up the report and 1 months for the programme to process the claims and
compile them into a claim to the Commission). These dates also gave the possibility of
scheduling an extra claim for payment at the start of October if targets were not going to be
met. It also of course meant that spending incurred in later months of the year could not be
included until the February report in the next year. As a result some programmes have
moved their deadlines back with the second report due in October / November in time for a
claim to the Commission in December.
Another alternative to standard reporting dates is to base the reporting date for each project
on the date of its date of approval or the date the subsidy contract is issued. The key
advantage here is that the workflow for programmes to process reports can be spread
throughout the year and this can be especially useful for programmes with large numbers of
projects. A good database should allow programmes to keep track of when each project is
due to report.
There are three potential delays in the process. Firstly, projects need to be able to collect
reports and claims from each partner and put them together. Not all Lead Partners will realise
how long this can take (approximately 1 months as a guideline), especially in programmes
where the Lead Partner principle is new, and some projects may miss deadlines. The project
section contains more on how to avoid this. Secondly, the certification of project expenditure
has taken as long as a year in some programmes. Clearly this totally disrupts the claims
cycle and the new regulations contain a time limit of three months for certifying project claims
for payment (even this is quite a long time). Finally, programme processing of claims can be
a factor and TA resources need to be allocated to ensure that there is sufficient staff capacity
to avoid this.
The biggest delays are, however, the result of project claims that cannot be approved for one
reason or another, as it can take a lot of work to resolve the problems involved. Most project
claim problems are detected during first level control before the claims reach the programme.
These problems should be dealt with by the controller and the relevant amounts should be
deducted from the claim but controllers sometimes make unquantified reservations and pass
on the problem to programme authorities. For example, controllers may point to insufficient
documentation or failure to comply with publicity requirements without saying that this has led
to incorrect expenditure. This type of issue takes time to resolve.
Aside from this, many problems arise because formal requirements have not been met such
as notification of budget line changes before expenditure is incurred. This is one of the main
areas where programmes need to be flexible and improve information activities if problems
are repeated in several projects: Project partners gain nothing from submitting reports that do
Financial Management Handbook
78
not fulfil requirements and this generally only happens because they are not aware there is a
problem. Below is a list of common problems and there is more discussion of these issues
later in the handbook. Some are more serious than others and will mean blocking the report
until they are resolved. Some can be sorted out with a phone call.
Late reporting
Bank information wrong
Payment request amount does not match finance report and/or cover letter
Budget of a budget line or a project partner is exceeded
Missing signatures and/or stamps
Costs are reported under wrong budget line and/or work package
Submission of incomplete progress reports
Changes made without prior agreement of the programme
Costs do not correspond to the activity report
Wrong exchange rate used
Controllers change the confirmation text and limit their liability
Investments and other costs not clearly specified
Location / project partner of equipment / investment not in line with the application
Amount of the equipment / investment is higher than stated in the application
Changes in the partnership: Project partners withdraw or there are new partners
Costs reported by project partners with no approved ERDF budget
Financial Management Handbook
79
1. Project
6. CA
5. Commission
4. CA
3. MA and/or JTS
2. First level control
bodies
Common problem points in the project payment cycle
CA can be slow to make payments. Projects
become less willing to support the
programme and make claims
Claim must fit figures in the OP
financial tables. Maths mistakes
common.
May reveal significant
problems with claims
and can take as much
as 1 year in some countries.

Max 3 months in future!
Understaffing and uncertainty on interpreting
project data may cause bottlenecks in
processing. More information may be needed
from projects.
Delays in submitting claims and reporting information is
inadequate
Will block project claims if information is
inadequate or there are unresolved control
issues with the payment declared
Missing and / or inaccurate information
means report has to be resubmitted
Financial Management Handbook
80
4.8 Tackling poor project spending
Even if programme spending forecasts are good and the administration of claims is efficient,
programmes may still face de-commitment problems if projects simply do not spend the funds
allocated. An important distinction needs to be made here. Project efficiency that results in
cost savings is of course to be encouraged. This is, however, not the case in the majority of
projects that fail to meet budget targets. The projects are instead delayed and normally catch
up on spending eventually. Many of them have also over-budgeted their projects and simply
do not need all of the funds they have been allocated. When we refer here and in later
sections to under-spend, it is this latter situation we are describing.
The first issue is to identify the projects that are under-performing. Provided that all projects
are required to provide annual spending targets as part of the application form, project
performance can be easily assessed on an annual basis. A split by partner by year gives
valuable additional information. Programmes tend to deal directly with Lead Partners but
reporting on partner spending may well reveal that the true problem lies elsewhere. This
should of course influence the advice that the programme gives the project. Flexibility is also
essential here. We have already discussed the need for sufficient safety margins, and
projects with minor under-spends should not be concerned. The programme only needs to
step in when the under-spend becomes major and threatens programme performance. It also
needs to recognise that some delays are beyond project control. A bad summer can be a
massive setback for an infrastructure project and should not be penalised.
The second step is for programme management bodies to secure a mandate from the MSC
to take action on under-performing projects. Committee members need to be informed about
the potential effects of under-performance (most obviously the de-commitment threat) and
the extent of the problem. Measures then need to be decided for dealing with under-
performance. These should certainly include the possibility to reduce project grants if the
programme de-commits as a result of poor project performance (and this must be included in
the project contract). This should however be the final step and a range of corrective actions
can be tried first with the ultimate threat of de-commitment serving as a powerful motivator.
In some programmes nothing is done and projects are given (sometimes repeated) time
extensions to allow them to use their full budget. This clearly strengthens the position of the
projects and gives them a great deal of flexibility though it does nothing to promote effective
project management. Unfortunately, it also means that avoiding de-commitment becomes a
matter of luck, as programmes have no firm control over what will be spent when. In effect,
poor project management in these projects can mean that other ideas do not even have a
chance because the funding they would have used has been de-committed from the
programme.
Good financial management therefore requires that action is taken before the situation
becomes acute. This is especially true because of the trend in the current programmes
towards supporting material investments, which has implied bigger projects. Although this
trend may be reversed in programmes with reduced budgets in the new period, the focus will
remain on strategic projects that deliver measurable results to the programme area. This
implies that substantial funds will be concentrated in a number of large projects. If a few of
these projects seriously under-perform they will cancel out the work of all the others. This is
clearly unacceptable.
Most programmes are already taking action and using a variety of methods to ensure
reasonable performance. In many cases all projects are also flagged as low, medium or
high risk based on past performance so programme actions can be focused on the biggest
problems. Other effective actions taken include:
Setting a deadline for incurring the first expenditure (e.g. three months after approval).
This forces the project to activate the partnership straight after approval and begin
implementation.
Sending reminders / warning letters and explaining the impact of project under-
performance on the programme and other projects. Projects need to be fully informed
Financial Management Handbook
81
about the problems they are creating for the programme and other projects. Simple but
effective.
On-site visits. It has often been effective to visit Lead Partners to discuss the problem. It
is not the job of programmes to manage the projects but these visits force project
managers to analyse and confront the problems they face and work with the programme
to find solutions. There is a need for programme flexibility as budgets and resource levels
may need to be changed. As a general rule, projects that are under-spending will
continue to do so if changes are not made to way the project is being managed.
Limiting carry over of unspent funds. If a project uses only a small amount of its budget
for a particular year, i.e. 20%, it can only carry over the unspent part of its budget into
the following year and not later in the project thus forcing the project to catch up or cut its
budget. The programme can then monitor the success of these budget reallocations and
offer assistance to projects that are still in difficulty.
Cutting unspent annual budgets. At least one programme simply reduces budgets if
under-spend is more than 25% after two years. Other programmes require projects to
explain the reasons for a serious under-spend in any year and what the project is going to
do to correct the situation. If the project cannot provide an adequate plan, the under-
spend is cut from the budget.
Keep the MC informed of the situation and what actions have already been taken to
correct it. There is understandable reluctance from most committee members when it
actually comes to cutting budgets. If there is a serious threat of a cut, national / regional
pressure on project partners through MC members may have an effect if programme
actions have failed.
All programmes should include the possibility of cutting budgets in project contracts to
provide a firm legal basis. It seems likely that this will become standard in most programmes
in future and that there will be less tolerance for bad project management. This is justified by
the scale of the problem with almost all programmes reporting that this is their biggest
difficulty in the main implementation phase. The alternative to cutting project budget is
allowing project under-spend to continue and risking de-commitment of programme funds.
If this means project budgets have to be cut, these cuts should obviously only be applied to
under-performing projects. Monitoring systems must therefore provide information that allows
the programme to decide which projects deserve to lose money and which do not. If there
are unallocated funds remaining, they can be used to meet the de-commitment loss but this
will mean depriving potential new projects or project extensions of funding. Helping projects
to get their budgets right and putting pressure on under-performers is clearly a better way
forward.
Cutting project budgets can, of course, create further problems. For example, large
infrastructure projects may depend on receiving the full grant in order to complete their work.
A budget cut here may lead to the collapse of the project and only make de-commitment
problem worse. Budget cuts should therefore be the last measure to be used and should only
happen if advice and assistance have been offered but have failed.
There is one further reason for caution as well. Many projects blame problems on
programme procedures such as delays in issuing contracts, sorting out conditions after
approval and carrying out first level control. Unfortunately, this criticism is in some cases
justified. If the programme has delayed a project, it must be ready to renegotiate project
targets and accept the consequences. This is particularly true of delayed contracts.
Programmes cannot expect projects to comply with their start date if the contract is not
provided until months afterwards. If the same programme failure is affecting several projects,
this suggests systemic problems and it needs to be taken up urgently by the MA and
Monitoring Committee.
Financial Management Handbook
82
4.9 Tackling a de-commitment threat
As has been emphasised earlier, the main elements for avoiding de-commitment are a
strong allocation of funds and a proactive approach to project management problems.
Having enough projects approved at an early stage in the programme ensures that even if
some under-perform, the spending of the others will absorb the shortfall. If the programme
has failed to achieve this, there is often little that can be done and the situation becomes one
of minimising de-commitment rather than avoiding it (though see below for some possible
emergency measures).
The second important consideration is that programme forecasting and monitoring
systems must be able to identify that there is actually a problem and the scale of that
problem. If programmes only realise that targets have not been met when the last project
claims come in, it is too late to take action. Monitoring systems should be able to provide a
quite an accurate assessment at the start of each year and this gives time to take action.
If forecasting is poor, the emergency actions available are very limited. They include
retrospective approvals of projects which have not yet finished but which have already
incurred significant expenditure that can then be claimed from the programme. These actions
should only be considered with the advice of the Commission and should preferably be
avoided at all costs.
Longer-term actions include:
Project Extensions and Waiting Lists: Programmes which expanded to encompass new
Member States and neighbouring countries following enlargement held calls restricted to
existing projects to allow them to bring in partners from the new participating countries.
This appears to have been a successful way of quickly allocating new funds. This
technique can be used in any programme to extend the activities and coverage of
particularly successful projects. The decision to expand the partnership must, however,
be subject to SC approval. Another practice used to help quick take up of funds when
they become available is to create stand-by lists of projects already approved subject to
funding becoming available. There is a danger that partnerships may weaken and start-
up periods may be extended if projects are left to wait too long so good communication is
needed and a realistic estimate of when funds will be available.
Including all possible expenditure in claims to the Commission: To help meet de-
commitment targets, the Commission has allowed claims from the PA on the basis of
unaudited project expenditure which has been the subject of a project claim but not yet
been paid by the PA. This is an exceptional measure to avoid de-commitment and should
not be standard practice. Payment of such project claims by the PA should be delayed
until the appropriate project controller has certified the expenditure claim. Even though
this option has been used by some of the programmes in the 20002006 funding period,
in early 2007 the Commission issued an opinion that no such option will be allowed in
future and consequently no unaudited expenditure declared by the CA in the programme
payment claim will be accepted.
24
Over-commitment. In theory over-commitment of funds to a small degree would not be
risky given the consistency with which projects have under-spent overall to date. If
projects typically spend only 90% of funds, the programme should be safe allocating
105% of the funds available. In practice, however, over-commitment has not been
entered into deliberately in Territorial Cooperation programmes given that participating
countries would ultimately have to fund the difference if spending did reach over 100%.
The risk is perceived as being too great.
If all of these actions fail, the programme will de-commit. This generally happens in the first
three or four years of the programme (i.e. because of failure to meet the first and second de-
commitment targets). At this stage there are generally unallocated funds still available and
programmes absorb the de-commitment loss by reducing the total amount that will be


24
Recent Commission audits have been critical of the use of this rule. It is very unlikely that this
practise can be accepted in the future.
Financial Management Handbook
83
committed to projects. Later on in the programme, once all funds have been allocated, the
only possibility is to cut project budgets. In the current period, however, this has not been
necessary: By the time all funds are allocated, there should be enough projects approved and
spending to easily meet later de-commitment targets. The cuts that have been made to
project budgets in the current period are instead motivated by the desire to exploit the full
potential of the programmes funds and this is discussed below.
4.10 Recycling funds and end of programme de-commitment
We have so far considered de-commitment during the early years of a programme but any
funds left unspent at the end of the programme must also of course be returned to the
Commission (in the sense that they will never be paid out). For example, during the last
period of INTERREG (the old INTERREG II programmes), almost all programmes managed
to allocate 100% of their funds but the total spend reported at the end of the programmes
typically ranged between 80% and 95%. The reason is that most projects do not spend 100%
of the funds that are allocated to them so the programme ends up with an under-spend. This
has led to a determination to try and improve overall spending rates in the current
programmes by recycling funds.
Once money has been allocated to a project, it is generally locked in this project until the
project closes and the programme can calculate how much money has not been used. The
aim of recycling is to calculate these amounts as soon as possible and use them to approve
new projects. This should be quite easy with projects approved early in the programme
lifecycle: They generally finish well before the end of the programme and there should be
plenty of time to reallocate their unspent funds.
Programmes have realised, however, that this addresses only a small part of the problem. By
the time final reporting and closure have been completed for projects approved later in the
programme, there may not be enough time to launch new projects using their unspent funds.
This is despite the fact that it is often obvious for some time that these projects will not spend
their full budgets. As a result many programmes are moving towards recycling funds from still
running projects if it becomes clear they will not spend the full budget. This allows them to
make active use of the funds rather than leaving them locked in the project.
The difficulty is in deciding when it is clear that a project will not spend the full budget. This is
generally obvious to the programme staff monitoring the project but for the sake of
transparency clear criteria need to be set for when a cut will be made and these criteria need
to be applied equally to all projects. Section 4.8 contains some examples of criteria already in
use and these should be combined with dialogue with project managers to discuss the
implications of the cut. Project partners are naturally hostile to cuts in their grants they may
accept that the funds will probably not be used but cuts reduce their budgetary safety
margins. MSC backing is therefore essential for this kind of measure but can be difficult to
obtain. Reliable figures on the actual extent of project under-spending are the most
convincing argument. Finally, it needs to be stressed again that projects must have annual
budgets so programmes can assess their performance over time. Where annual figures are
not available, there is no way of demonstrating that spending is not on schedule and
programmes are powerless to take action.
Once funds have been freed up from projects, it is important to get them reallocated as soon
as possible so the new projects can be completed before programme closure. The most
effective methods are project extensions (subject to SC approval) and trying to develop a
pipeline of small project ideas that are ready for almost immediate implementation. In this
connection it is important to note that calls for applications do not always have to be open.
Funding opportunities can instead be offered to a limited number of projects to save time as
long as they are then assessed with the same criteria used on all other projects.
Financial Management Handbook
84
4.11 Payment Claims to the Commission
Approximately three times a year
25
(many programmes only do it twice) the Certifying
Authority submits a claim for payment to the Commission. If the programme wants to ensure
payment before the end of the year, the deadline is 31 October. All claims received on or
before 31 December count towards spending for the year (and thus meeting de-commitment
targets).
These statements of interim expenditure, certified by the CA, use a simple template (currently
Annex X of the Implementing Regulation) and include a statement of expenditure by priority
on the basis of expenditure actually paid out and audited. Any amounts that have previously
been paid out incorrectly and have now been recovered need to be deducted and reported
on. Aside from occasional problems with the type of co-financing reported (as discussed
previously), most problems with claims to the Commission arise from inconsistencies in the
figures reported at different times and places or simple mathematical errors.
Some desk officers will look at draft claims to detect any errors but others do not have time.
Once the completed claim is formally submitted to the Commission, however, any error has
to be addressed in a formal letter from the Commission to the programme. This of course
takes time so it is essential that mistakes are avoided.
The Commission pays claims until the total paid (including the advance from the
Commission) reaches 95% of programme funds. The last 5% is withheld until the
programme has been officially closed.


25
General Regulation 1083/2006, 87.1
Financial Management Handbook
85
5. Start-up phase: Project Level
The following sections are written from a programme perspective and focus on what
programmes can do to assist projects at various stages. Most of the content will, however,
also be useful for project managers. The project perspective is covered more fully in another
INTERACT publication
26
.

Start up phase at project level: Summary

Project budgeting is as important as developing a project idea. Programmes can help
projects with financial management through written advice, fact sheets, guides to the
application form and LP seminars
Key elements in drawing up a project budget include: Resource planning, cost
estimating and cost budgeting in the form of a Detailed Costed Workplan. Advice
should also be given on eligible expenditure.
The assessment process should include scrutiny of eligible costs, assessment of risk
that a partner or project may fail or not meet all objectives and how realistic the budget
is.
Straight after approval extensive advice should be provided to projects on a wide range
of financial management issues.

We have already seen that many projects are over-budgeted and that budgetary
management during implementation is often poor. The results are slow spending and the
eventual return of unspent funds to the programme. Many project managers admit that they
do not know how to develop the budget and there is very little programme advice available on
this. Most also say that when budgeting tools like the Detailed Costed Workplan are not part
of programme requirements, they are not used. Budgets are instead based on guesses and
estimates and it is little wonder that they are often wildly inaccurate.
This section therefore looks at how programmes can support the development of soundly
based projects, which will be well managed over the project life cycle. This need will be
particularly urgent in cross-border programmes that are using the Lead Partner principle for
the first time, as there will be important changes from existing procedures.

What is a project and what is a project budget?

These questions may seem too obvious to even ask but the answers influence a
programmes whole approach to managing the implementation phase. Projects are defined
by two features:

They have limited and fixed objectives. These are additional to the activities normally
carried out by the organisation involved.
They have a limited lifetime. Objectives should be met within the time specified and the
project should then be closed.

These two features should allow project developers to develop a budget based on the
activities needed to meet the objectives and the resources required to carry out these
activities within the time allowed. The role of the project manager is to ensure that
objectives, time limits and budgets are respected. If they are not, project management is
failing.



26
Territorial Cooperation Project Management. Produced by INTERACT Point Qualification and
Transfer in Denmark.
Financial Management Handbook
86
5.1 How to get project budget right
It is vital that projects start to consider financial issues from the very beginning. As planning
meetings move from general objectives to specific objectives and an outline of the activities
needed to meet them, each activity proposal should be budgeted. All partners should be
involved in this process and it is important to also include a realistic budget for the Lead
Partners project administration role. Of course this approach requires preparatory work and
planning meetings during the development of the project application. Time invested here,
however, results in strong partnerships with clear responsibilities and well-justified budget
allocations. Successful project managers consistently name good preparation as the main
factor in smooth project implementation.
It would be unrealistic to suggest that this process does not sometimes work in reverse: A
total budget is decided that will probably be approved by the programme and this is then
filled in with activities. In the worst cases this definition of the actual activities to be carried
out is not done until after the programme has approved the budget, with the application form
kept vague enough to allow considerable re-interpretation post-approval. Programmes need
to make sure that the level of detail required in applications makes this approach impossible.
Another common bad practice is for Lead Partners to develop projects in isolation and try to
assign activities and budgets to possible partners. This generates resentment in the
partnership and results in unrealistic proposals: All partners need to take responsibility for
their own budgeting.
These approaches to project development do not always result in bad projects. An
estimation of the funds potentially available can be an important factor in defining the scope
of the project. Experience in the current period has shown however that saving time on
proper budgeting almost always results in tensions within the partnership and with
programme management. Finance staff need to be aware of such practices and develop
application, assessment and monitoring procedures that keep them to a minimum.

Two approaches to deciding the project budget

Activities to be carried
out
Budget available
THE RIGHT WAY THE WRONG WAY
Budget required Activities to be
carried out
Financial Management Handbook
87
How in more detail should a project move from an activity plan to a realistic budget? There is
a three-step process that should provide the right level of accuracy: Resource planning, Cost
estimating and Cost budgeting. These steps form the basis for cost control once the project is
operational. At first sight this process may seem overly complicated and intimidating. In
actual fact it is not. It is really just the same process you would use if you were going to re-
decorate your kitchen just on a bigger scale. Put basically, you need to decide what your
new kitchen will look like, how and when you will do the work, what supplies you will need
and how much outside help you will need for the specialist jobs. You then use this to put a
price on everything. If you have done something similar in the past, your experiences will help
you make sure that your plan is realistic. If not, you might want some expert advice to make
sure you have not missed anything. You will probably also want to allow a little bit of extra
money and time for those nasty unexpected surprises that always happen.

Three-step project budgeting

5.1.1 Resource Planning
First of all, you need a clear idea of what you want to achieve and how you plan to do it.
Break this down into work packages and decide what you will need to do to complete each
work package. In partnership projects it is particularly important to think about how different
work packages fit together: The work of one partner often depends on delivery of another
partners work. This needs to be emphasised to all partners and possible delays should be
built into the time plan.
Identify the objectives and sub-objectives of the project
Define the work packages and determine how the objectives will be achieved, who will do
it and what physical resources i.e. people, equipment and materials will be needed. It is
essential that all the partners are involved in this process.
Define a time plan with milestones.
Resource Planning

Defined objectives
Breakdown of work
packages
Time plan with
milestones
Cost
estimating
Bottom-up
estimate
Resource rates
Historical
information
Cost
budgeting
Detailed Costed
Workplan
Annual spending
targets per partner
Cost
control
Compare actual and
planned expenditure

Progress reports
Budget updates
Project budgeting
Financial Management Handbook
88
Identify the additional tasks required for the effective cooperation of the partnership and
allocate resources to the partners who will incur these costs (regular face-to-face
meetings of the partnership are a key success factor).
5.1.2 Cost Estimating
You should now have a reasonable accurate picture of what will happen over the course of
the project. The next step is to try and work out how much it will all cost
Develop an approximation of the costs of the resources needed to complete project
activities. Some costs are reasonably easy to calculate. For example, you will know the
number and type of staff required and the standard salary for this type of staff. Other
costs are more difficult. For example, if you plan a pilot activity based on the results of
initial research carried out by the project it will be impossible to know exact costs at the
start. The best approach is to define a realistic maximum price for the activity.
One question when drawing up the budget is always, What if we do not have enough
money to do what we plan? The answer is easy. Project managers ensure that there is a
surplus of funds by adding a bit to the estimates. Even if things cost a bit more than
expected, the project will have enough to pay. The problem is that by adding a bit to
every estimate, you soon end up with a seriously over-budgeted project and you prevent
other projects making use of the funds that have been unnecessarily allocated to your
project. Some activities will actually be completed under-budget, others can be adjusted if
the money is running low. The partnership should therefore try to keep estimates as
accurate as possible and then agree a reasonable surplus to meet unexpected problems.
This bottom-up estimate of the cost of individual activities should be aggregated to get
the total estimated amount.
5.1.3 Cost Budgeting
You should now know the main activities, which partners will carry them out, the estimated
start and end dates and the approximate resources (and therefore budget) required. The final
step involves re-organising these figures to show the main categories of spending
(sometimes called budget lines for example staff, travel, publications etc.), the partners
that will spend the funds and what year this will happen. Every programme has slightly
different requirements for how this information should be presented and the level of detail
required. Whatever the formal requirements, every project should have a Detailed Costed
Workplan showing this information in detail: It is the most important part of the agreement
between the partnership on how the project is going to be implemented. Examples of the
main tables needed for the work plan are included below they should obviously be changed
to suit the requirements of each project and programme.
Allocate the overall cost estimates to individual activities and partners. Programmes often
require this in some form (the Detailed Costed Workplan) as part of the application form.
One key element of the Detailed Costed Workplan is annual budget targets in total and
per partner. These form the basis of the projects spending targets and give indicative
information on the scope of involvement of each partner. It also makes it easier in the
operational phase for the Lead Partner and programme management to see which
partners may be lagging behind in spending.
Project schedule and resource allocation. The schedule includes planned start and
expected finish dates for the components of the project to which costs have been
allocated. These timings should be reflected in the descriptive material accompanying the
financial tables.
Financial Management Handbook
89

Detailed Costed Workplan 1 Split by partner and year

Detailed Costed Workplan 2 Split by partner and budget line

Expenditure in Euro
Lead
Partner
Partner
2
Partner
3
Partner
4
Partner
5
Total
1. External experts and consultants

2. Staff

3. Travel and accommodation

4. Meetings, conferences, seminars

5. General costs (specify in appendix)

6. Promotion and publications

7. Material investments, including
infrastructure

8. Audit

9. Other (specify)

10. Irrecoverable VAT

Total eligible expenditure

ERDF

Own contribution

Total funding

Financial Management Handbook
90

Detailed Costed Workplan 3 Split by partner and work package

Tasks
1 2 3 4 5 6 7 8 9
Phase 1
Task 1.1 xxxxxx
Task 1.2 xxxxxx
Task 1.3 xxxxxx
Phase 2
Task 2.1 xxxxxx
Task 2.2 xxxxxx
Task 2.3 xxxxxx
Phase 3
Task 3.1 xxxxxx
Task 3.2 xxxxxx
Task 3.3 xxxxxx
Days
1 2 3 4 5 6 7 Total
Phase 1
Task 1.1 1 1 1 1 1 1 1 7
Task 1.2 2 2 2 2 2 2 2 14
Task 1.3 3 3 3 3 3 3 3 21
P1 - sub total 6 6 6 6 6 6 6 42
Phase 2
Task 2.1 1 1 1 1 1 1 1 7
Task 2.2 2 2 2 2 2 2 2 14
Task 2.3 3 3 3 3 3 3 3 21
P2 - sub total 6 6 6 6 6 6 6 42
Phase 3
Task 3.1 1 1 1 1 1 1 1 7
Task 3.2 2 2 2 2 2 2 2 14
Task 3.3 3 3 3 3 3 3 3 21
P3 - sub total 6 6 6 6 6 6 6 42
Grand total 18 18 18 18 18 18 18 126
Partners
Project timetable
Months
Resource allocation

5.2 Budget detail vs. flexibility
The project budget is always an estimate. How many pages will the project final report have?
How much will heating prices increase over the project lifetime? These types of questions are
impossible to answer at the start of the project. Good planning can only mean that the
estimate is more accurate.
Financial Management Handbook
91
The main implication of this is that programmes need to be realistic about the level of detail
required in the application form. This decision is a reflection of where each programme feels
the reasonable limits lie and an assessment of the capacity of its project partners. In some
cases a very detailed budget and work plan are demanded identifying individual costs. This
allows programmes to ensure that inexperienced partners have done the necessary planning.
Requiring this level of information also allows the programmes to enforce strict cost control. It
must be realised, however, that much of this information cannot be decided so accurately in
advance and programmes choosing this approach need to be extremely flexible about
allowing later budget changes. This level of detail also demands a lot more project
preparation work, the bureaucracy involved may discourage applicants and the benefits are
uncertain: Generally, programmes requesting very detailed information have not seen this
translated into better project performance.
At the other extreme, budgets are limited to providing one figure (the total grant requested for
the project), as it assumed that project managers have the experience to have done their own
budget breakdown and stick to it (unfortunately this is often an over optimistic assumption).
This is advised against in the strongest terms, as it does not provide enough information to
properly assess or monitor projects.
The majority of programmes adopt various compromises taking into account the experience
and past reliability of project managers in the programme area and the information regarded
as essential for project assessment and monitoring. The most common approach is to require
information on how the budget is split into approximately 10 budget lines with additional detail
generally required on budget lines such as Material Investments. This allows the programme
to check that the basic division of funds is realistic and disproportionate funds are not being
allocated to, for example, overheads. These budget lines are often, but by no means always,
split between partners (allowing an assessment of who is really doing what in the project),
between years (giving an overview of expected progress) and sometimes between the main
work packages (seeing how it all fits together). If, as should probably be the case, the third
part of the Detailed Costed Workplan is required as part of the application, it should be
regarded more as proof that the work has been done rather than as unchangeable plan for
project implementation: Project managers will certainly need to make changes to this
document as they go along.

Key information to collect in the application form

Who is in the partnership?
What activities will be carried out?
When will they happen?
Who will be responsible?
What indicators are used to demonstrate that the projects objectives have been met?
What is the total budget?
What should each partner spend each year / for each main activity?
Is there reliable project management and a strong partnership in place?

In summary, the application needs to provide enough information for programmes and project
managers to assess and monitor:
Partner performance over time
Partner performance by budget line compared to outputs achieved
Whether work packages are being achieved on time and in line with the budget
This will allow them to identify quite precisely the cause of any problem and target their
response. In the worst case if money is de-committed from the programme and project grants
have to be cut, this information can also be used to target these budget cuts so partners who
are delivering as agreed are not affected. This makes it possible to judge whether the budget
corresponds to the activities proposed in the application form and whether resource allocation
to, for example, staffing seems reasonable in terms of the activities planned.
Financial Management Handbook
92
Once the initial project budget information is collected, flexibility is required. As every project
progresses there will be differences between estimated costs and the actual costs incurred.
These will be cumulative and the longer the project lifetime and the bigger the budget, the
greater the difference between the estimate and actual expenditure can be expected to be.
This needs to be accepted as normal and programmes should expect and allow budget
adjustments (particularly if the original budget was very strict.
Typically programmes allow movements of funds between budget lines up to 10%-20% of the
total project budget. Normally these changes are limited to one per year to reduce
administration for projects and programmes. In some cases MA/JTS approval is required. In
most cases it is sufficient just to notify the programme. Larger changes normally require SC
approval because they may fundamentally alter the nature of the project. Some programmes
apply conditions, such as a need for detailed information and programme approval, for
certain changes where it is felt that these may also significantly alter the project. Common
examples are changes in the amount of funds being spent on staff and infrastructure and
movements of funds between partners.
5.3 Helping projects get it right
There are repeated requests from the project level for assistance with budget preparation.
The most important advice programmes can probably give is that projects need to invest time
in the process. To support this preparation many programmes allow projects to claim costs
incurred during the development phase.
In some cases, approved projects can claim expenses incurred during a fixed period before
the date of approval say 6 months and up to a maximum of perhaps 10.000 (subject to
the usual financial controls). In other programmes, projects can apply for seed money a
small grant to fund development activities
27
. Seed money reduces the risk faced by project
developers when they allocate resources to putting the project together and should increase
the quality of applications. It has to be kept in mind, however, that such schemes are by their
nature granting small amounts of money to many people - relatively time consuming to
administer. As a result some programmes that used seed money in the current period have
decided against continuing the scheme. It may still make sense, however, in large
programme areas where travel costs to project planning meetings are high or in programmes
that are having trouble attracting applications.
Beyond assisting with preparation, the key requirement is to provide clear information.
Programmes should be willing to give advice on budgets while making it clear that the SC will
not automatically approve applications that have followed this advice. There are various
communication channels that can be used. Ideally a combination of all of them should be
developed.
Written advice, which is easily available and clearly presented on programme websites
including:
o The Operational Programme clearly stating objectives and the activities
eligible for financing.
o Programme Fact Sheets on particular aspects of finances e.g. eligibility of
expenditure, State Aid rules, cooperation requirements, Exchange Rates,
the Lead Partner Principle, Infrastructure Projects, Private-Public
Involvement, De-commitment and Detailed Costed Workplans.
o Guidelines on how to fill in application forms and underlying budgeting
techniques.
o Frequently asked questions sections on the programme website
Programme contact points to assist project development in each participating country
or region. They tend to focus more on the content and partnership aspects of projects
rather than finances but in some programmes they are able to provide information on
financial aspects.


27
See the Handbook on financial support to draft INTERREG project applications produced by
INTERACT Point Toolbox in Valencia for more details on the administration of these schemes.
Financial Management Handbook
93
Bilateral meetings and seminars with project developers covering basic financial
aspects in project development.
Formal or informal pre-assessment before the main SC assessment. Informal
assessments appear to be the easier way of giving advice but strict limits need to be set
on the documents that will be considered and the level of advice provided. It is essential
to avoid conflicts of interest and giving the impression that pre-assessment will lead to
automatic approval of an application.
Encourage Lead Partners to take an active role in tutoring partners and securing their
commitment to following financial requirements in the operational phase. Projects may be
based on large, inexperienced partnerships which may not at first even recognise the
need for strong project management and proper accounting systems. The LP should be
encouraged to involve a finance expert in drawing up the application form. It appears that
those projects which have not done this may take as much as an extra 6 months after
approval to get off the ground. Projects may also need advice on establishing agreements
within project partnerships including financial obligations. Some programmes publish
model partnership agreements, although projects should always take their own legal
advice before using any standard model.
Professional project management. Not all participating organisations have an interest
in developing their project management capacity. These partners will prefer to focus on
content and to leave project management and administration to others. Consultants are
an option here and some have extensive experience, which can significantly improve the
quality of the application. There are two main risks to monitor. Firstly, it is important that
the full partnership remains involved in developing the project and that they support the
activities and objectives as finally expressed in the application. Secondly, the partnership
needs to agree a practical implementation plan for after the projects approval if the
consultant is not staying with the project. This ensures that partners understand how the
plans in the application are going to be put into effect.
5.4 The assessment process
The assessment process focuses on the activities proposed but also includes an analysis of
the budget in comparison to these activities. As noted previously, programme requirements
for the application form vary enormously but in all programmes the keys to success are
presenting all activities clearly and logically, showing how each member of the partnership is
important for overall project implementation and demonstrating that these activities are
under-pinned by a well-planned budget. The project should be assessed only on the basis of
the information contained in the application and confused or vague proposals are a main
reason for rejection.
The job of assessment falls to different bodies in different programmes. In many cases the
JTS does the job, particularly the formal eligibility check described below. In other
programmes (the inter-regional programmes are a good example), outside experts are
contracted to do the assessments. In other cases again (and particularly cross-border
programmes) regional and / or sectoral sub-committees play an important role. Regardless of
the method chosen, it is important that none of the assessing bodies have played a role in the
development of the projects and that the assessment is based on clear criteria
28
.


28
See Good Practice INTERREG III Strands A, B & C selection and eligibility criteria produced
by INTERACT Point Toolbox, Valencia. The main argument presented here is to ensure that criteria
are not based on subjective, qualitative judgments.
Financial Management Handbook
94
5.4.1 Eligibility check



What is eligibility?

Eligibility is a key term in project implementation. There are EU, national and programme
rules on the type of costs that will be accepted and those that will not be accepted.
Generally these are a matter of common sense it is clearly unacceptable to use
taxpayers money on first class travel, five star hotels and champagne. This type of rule is
discussed in more detail in the section on financial control.

As well as addressing costs, however, eligibility is also concerned with activities. Each
programme defines the type of activities it will support. These are designed to address the
most urgent problems in the programme area and must be in accordance with relevant EU,
national and regional policies. Programmes must also check that the activities they plan to
fund are not covered by other EU programmes operating in the environment, agriculture,
transport sectors etc. This may mean that some actions that are relevant for regional
development are not allowed under the programme. Project developers need to accept this
and follow programme guidance even if it means dropping otherwise valuable activities.

There are also rules about the types of organisation that can be involved in a project.
Some programmes exclude the private sector (see the section on private co-financing) and
all have strict rules about involving partners from outside the programme area. Finally,
eligibility covers some basic project requirements. For example, are there enough partners
from enough countries? Is all of the co-financing in place?

These rules come from various levels and there is generally a good reason for them.
Projects must know them and respect them: Once they are in place programmes are
required to enforce them rigidly.

The eligibility check during the assessment stage is mainly concerned with assessing
whether the activities proposed fit the programme and the relevant rules and regulations as
well as checking formal requirements such as letters of commitment for co-financing. It is not
concerned with assessing individual items of expenditure, which is the job of first level
control. A good application should contain sufficient detail about the activities to be carried
out for the programme to be able to spot obviously ineligible activities and areas where there
is a possibility of later problems. The more effort put into the process, the fewer the problems
likely to arise at payment claim and monitoring stages.
The eligibility check should also confirm that project activities comply with national laws and
rules. Unlike other Structural Funds programmes, in Territorial Cooperation programmes this
is not normally the job of the MA. Because of the large number of countries that may be
involved in a programme, it is unrealistic for one body to assess compliance with all of the
different national rules. As a result, representatives in each Member State play an important
role in the assessment of eligibility as they often carry out the first check against national
rules. In some cases this is done by Steering Committee members after they receive the
assessed applications and before the committee meeting. In other cases there are separate
sub-committees that consider all applications including a partner from the Member State
concerned. The formal member of the Steering Committee then presents the views of the
sub-committee. Whichever system is used for making these decisions, any problems should
be reported to the programme as soon as possible and before the official meeting of the
Steering Committee.
Financial Management Handbook
95

Two new eligibility criteria: Cooperation criteria and the partner capacity check

Many cross-border programmes will experience one significant change at the start of the
new programme period: It will no longer be possible to have projects with partners from
just one country: All cross-border and transnational projects must have partners from at
least two countries and all inter-regional projects must have at least three countries (of
which at least two must be Member States). In addition, there are a number of cooperation
criteria and every cross-border and transnational project must fulfil at least two of these
criteria. All inter-regional projects must fulfil all four criteria.

The cooperation criteria all future projects will have to comply with are:

Joint development. Meaning that the project must be designed by representatives
from both sides of the border. Project proposals must clearly integrate the ideas, priorities
and actions of stakeholders on both sides of the border. The Lead Partner is the
coordinator of this process but should include other partners from the start of the design
process.

Joint implementation. Meaning that activities must be carried out and coordinated on
both sides of the border. It is not enough that activities run in parallel: There must be clear
content based links between what is happening on either side of the border and regular
contact between the two sides. The Lead Partner is responsible for ensuring that activities
are properly coordinated, that schedules are kept and that the right quality levels are
achieved.

Joint staffing. Meaning that the project should not duplicate functions on both sides of
the border and staff on both sides of the border should work together on the project.
Partners should not merely carry out activities in parallel without coordination and
exchange. As a minimum there should be a joint project manager with overall responsibility
for project activities on both sides of the border. The Lead Partner is generally the
employer of core project staff, but project partners should also allocate staff according to
their responsibilities within the project. It is essential that the Lead Partner is allocated
sufficient resources for overall project management.

Joint financing. Meaning that there will be only one joint project budget. This budget
should be divided between partners according to the activities carried out. There is also
only one project bank account (held by the Lead Partner) and payments are made from the
programme to this account. The Lead Partner is responsible for administration and
distribution of these funds and for reporting on their use (through collecting partial reports
from partners). Co-financing should come from both sides of the border and from all
partners and illustrates the commitment by each partner to the joint project.

It should be stressed that meeting two of these conditions is a minimum requirement. In
many programmes projects already meet all four conditions and this will be expected to
continue.

The number of projects fulfilling two, three or four of the cooperation criteria is also a
programme performance indicator in Territorial Cooperation programmes and fulfilling
more than two of the criteria will strengthen project applications. Also, once the process of
integration has started through, for example, joint project development it is probably
actually easier to cooperate on all four levels. Finally, it is possible for operations to be
implemented on the territory of just one country but they still need to be presented by
organisations form at least two countries and fulfil two of the cooperation criteria. These
points are covered in the ERDF Regulation 1080/2006, 19.

The second new check covers the capacity of the partners to fulfil their role in the project.
This check is defined under the responsibilities of the Managing Authority in the Draft
Implementing Regulation, 13.1 where it is stated that the MA:

Financial Management Handbook
96

shall ensure that beneficiaries are informed of the specific conditions concerning the
products or services to be delivered under the operation, the financing plan, the time-limit
for execution, and the financial and other information to be kept and communicated.

It shall satisfy itself that the beneficiary has the capacity to fulfil these conditions before the
approval decision is taken.

As a result future application forms can be expected to request basic information on
partner capacity. Most of this checking will, however, probably be delegated to the Member
States in Territorial Cooperation programmes. It is easier for each country to check the
partners on its own territory and this already takes place in most programmes as part of
the preparations for Steering Committee meetings.

In conclusion, the eligibility check provides basic information such as whether activities will be
carried out in the eligible area and whether partners are from eligible organisations. It may
sometimes be possible to identify specific activities that are ineligible because, for example,
they break State Aid rules but assessment of the application can never guarantee that
ineligible activities will not be carried out and can never replace post-approval advice and
control of eligibility.
5.4.2 Assessing project budgets
If the project passes the eligibility check, the next step is a detailed assessment of the
activities and the budget proposed. We focus here on aspects of the budget that are worth
considering. As discussed earlier, project budgets are often unrealistic in terms of the amount
needed and/or the time required to complete activities and claim the funds. This is often the
result of poor planning and finance staff need to be able to spot the biggest problems and
recommend revision of the budget (preferably in anew application but perhaps in post-
approval conditions). There are two main reasons for taking a hard line on project budgets.
Firstly there is the question of de-commitment and the problem of unused project funds,
which mean that programmes need to try to assess whether projects are likely to meet their
spending targets or under-spend. Secondly, there is the question of value for money.
Quantitatively assessing project value for money is difficult. For example, assessing the cost
of infrastructure investment (and particularly innovative pilot projects) can only be done by
experts and first and foremost the project managers who drew up the budget. A great deal
can, however, be done to assess whether the projects contribution to programme objectives
justifies the grant requested taking into account the added value of cooperation. This can
then be compared to similar existing projects to provide a basic assessment of value for
money.
The budget can also reveal a lot about the partnership involved and particularly whether there
is a reasonable split of resources in terms of the work to be carried out. Clearly, every project
is different and what is a problem in one may have a good explanation in another. This work
therefore depends on a good understanding of the activities to be financed.
Potential danger signals include:
Budget too big compared to expected outcomes and other similar projects.
Uneven split among partners. If there are major imbalances they may indicate that it is a
weak partnership, which is likely to run into trouble when the project is operational. The
allocation of funds to different budget lines can also be a cause for concern. For example,
if there are no staff costs but only costs for a service, such as production of a report, this
can mean that the partner involved is delivering a contracted service and has been
included in the partnership to avoid public procurement procedures.
Too many funds are allocated to staff and too few tangible outputs are forecast.
A high proportion of funds are allocated to organisations permanent staff. This can mean
that programmes are being asked to cover normal operating costs and the activities
planned are not additional.
Financial Management Handbook
97
High external expert costs may signal limited involvement of the various actors and
handing over responsibility to external consultants. Some programmes put a limit of 40%
of the project budget to be used by external experts. Nevertheless, in some countries
major public service cuts have been made and consultants are encouraged to take on
tasks formerly carried out by public organisations. Background knowledge of the situation
in each partner country is therefore required before making this kind of judgement.
Unrealistic annual spending targets. Particularly if large amounts of funds are forecast to
be spent at the beginning or end of a projects lifecycle. A realistic project spending profile
will generally show a very slow start up phase, particularly if this is the first project the
partnership has undertaken together, which will then speed up as start-up problems are
resolved. The budget and activity plan should reflect the time required for building the
partnership, getting to know each other, initiating talks, deciding on detailed action plans
and dividing tasks among partners. Many of these issues should of course have been
decided in outline during the application phase. Decisions on how to practically implement
these plans can, however, be expected to generate many additional questions and
complications. Generally, a slower start up phase indicates that the project is taking these
issues seriously and is coordinating future actions.
Many first-time Territorial Cooperation projects are simply not aware of the added
complication and delays involved in cooperation. It is essential that programmes provide
them with information on typical start-up problems and budget impacts and give new project
managers the chance to discuss these issues with more experienced colleagues. Projects
also need to be very clear that they will be expected to stick quite closely to the targets they
fix and that there may be implications for the project grant if they do not.
5.4.3 Risk assessment
Risk assessment of projects is a largely subjective but still valuable part of the assessment.
Generally speaking, the type of risk factors typically used in identifying projects for inclusion
in second level control checks can be combined with an assessment of the quality of the
application to provide a guide on the risks involved in approving the project. The type of risk
factors to be considered include:
Partners from the private and/or voluntary sectors
Large budget
New partnership. Territorial Cooperation programmes generally seek innovative projects
and to spread involvement in co-operation projects to new partners. As a result, it would
be inappropriate to rule out new partnerships as too risky but the chance of problems is
greater than in a partnership that knows the system.
Large partnership
None of these factors are sufficient reason for rejecting a project but if they are
combined with an application that leaves doubts about the exact activities to be
carried out and the allocation of resources to these activities, the project risk is
probably too high. The size of the risk (i.e. the size of the project budget) should
definitely be considered. Large projects should be expected to be very specific
about their plans, while a micro-project of 10.000 can be accepted on the basis of a
much briefer outline. It is worth considering this element of risk and trying to develop
a portfolio of approved projects that have a reasonable balance of higher and lower
risks. This will allow programmes to absorb delays in some projects without
encountering significant de-commitment problems.
5.5 After approval
The main things that need to happen are to inform the project of the Steering Committee
decision and issue a contract as soon as possible
29
. Within the partnership, a kick-off meeting


29
See the section on programme documents and Recommendations for the implementation of
INTERREG III subsidy contracts produced by INTERACT Point Toolbox in Valencia. Note that this
Financial Management Handbook
98
needs to be held as soon as possible (some programmes have strict deadlines for starting up
project activities). The partnership also needs to finalise and sign a partnership agreement
30
.
The main aim of this document is to ensure that all partners are aware of their responsibilities
and there is a binding agreement about how these will be met (see the info box below for
more). As soon as possible after approval, Lead Partners should be invited to a programme
seminar to go over reporting requirements and ask any questions they may have about the
rules.

Lead Partner and partner responsibilities

By signing the contract with the programme (generally the MA), the Lead Partner (or Lead
Beneficiary) takes on a number of responsibilities. The purpose of the Partnership
Agreement is to make sure that all partners deliver the information that the Lead Partner
needs to fulfill its responsibilities and that if anything goes wrong, the partner concerned
will accept responsibility and pay back any incorrectly used funds.

There is one major change here between the future period and programmes that have
used the Lead Partner principle in the current period. Previously, the Lead Partner bore
financial responsibility for implementation of the project for all partners actions. In future,
the partner spending the funds is clearly (financially) responsible for the use of these
funds. All partners therefore need to fully understand the rules and commit to paying back
these funds if necessary.

First and foremost then, the project partnership agreement needs to cover provisions for
sound financial management including ensuring that separate project accounts are opened
and that all spending is properly certified. It must also contain the name of the (nationally
approved) designated first level controller for each partner, as the LP must check that all
partner expenditure has been validated by the approved controllers. There should also be
a reference to all rules governing Territorial Cooperation expenditure so partners are clear
about where to find information on eligibility issues.

The agreement should also include the approved application: The LP is responsible for
ensuring implementation of all parts of the project and checking that spending has been
incurred only on agreed and approved activities. Information on both activities and
spending needs to be included in all reports to the programme and the agreement should
provide guarantees that every partner will provide this information in good time.

Finally, the agreement should cover financial flows in the project with the LP committing to
transfer funds to all partners as soon as they are received from the programme and
partners guaranteeing to repay incorrectly paid funds. There may also be provisions
covering shared project management costs and various project specific requirements.
Some programmes provide a template.

The Lead Partner responsibility is primarily to check compliance of all project partners with
the main rules. It remains the responsibility of every partner to carry out the activities
assigned to it in the approved application, to ensure that expenditure has been certified by
the approved controller, and to take financial liability for any irregularity in the expenditure it
has declared.



second document covers the current period 2000 - 2006 and some modifications may be required for
the new period 2007 2013.
30
See Good practice INTERREG III partnership agreement, produced by INTERACT Point
Toolbox.
Financial Management Handbook
99
6. Operating phase: Project Level

Operating phase at project level: Summary

Programme bodies should give advice to projects on budget management, payments,
reporting and certification following project approval. While focusing on Lead Partners,
care should be taken to ensure advice is being passed on to other project partners.
Financial managers and auditors of projects should be targets for advice.

Inexperienced projects may be particularly in need of advice. Others can be identified
through the payments and reporting systems, visits and annual project partner meetings.

Projects should be encouraged to monitor spend and make minor adjustments to their
budgets, with the written approval of the programme body. Handling of minor adjustments
can be streamlined through making only one change a year.

Approval for major budget changes may cause delays to project spending whilst approval
is sought and subsidy contracts are reissued.

There is much valuable expertise within experienced projects, which can be used to help
other projects.

The first and most important point to make is that for many projects, implementation is
relatively problem-free and financial management is limited to monitoring and adjusting
budgets, and doing the reports and claims for the programmes every six months or so. A
lot of projects start more slowly than expected but many catch up. Most are over-budgeted
but in many cases the amounts concerned are not excessive.

That said, some projects go badly wrong and in extreme cases the programme will refuse
to pay funds to the project concerned and legal action is possible. This section therefore
focuses on the relatively easy actions projects and programmes can take to avoid this
situation. We start with the projects.

6.1 Avoiding project financial problems
It is important to remember exactly what project approval means. When projects are
accepted they agree to act:
In accordance with the latest approved application. The description of activities in the
application gives the project its mandate and it is only allowed to carry out these activities.
The reason is that programmes need to be able to assess whether activities are
appropriate / valuable / legal etc and adding activities can be used as a way of avoiding
the assessment process. Most activity changes actually involve improving on what was
planned or doing extra work and programmes will generally accept them. It is vital,
however, that projects inform programmes and get approval before starting work on such
actions.
With the approved partnership. For the same reason, only approved partners are eligible
to spend project funds. If any other organisation spends project funds without the prior
approval of the programme, this spending will be ineligible. If the partnership needs to be
changed (partners do sometimes drop out), the programme must be informed. Possible
replacement partners need to be found (with co-financing) and arrangements need to be
made for deciding how much should be paid to the partner that has left, making possible
recoveries of funds and ensuring that such partners are aware that programme financial
control requirements still apply to all of the funds they have received.
Financial Management Handbook
100
According to the approved budget and timeline. This is covered in detail in previous
sections. Projects will never be paid more ERDF than they have been granted (even if
they have provided extra co-financing). Projects should only be granted time extensions
with the prior written approval of central programme management bodies.
In accordance with the relevant rules and regulations. There are EU, national, regional
and programme rules and they should be made available to all project managers at
project start-up. If in doubt, ask.
As long as these basic rules are followed, there should be no problems with financial control
or following the standard programme procedures described below.

How to avoid project spending problems

Set up separate accounts for project funds. Or at least ensure that every partners
accounting system can clearly separate project costs. Control visits have sometimes
revealed that this basic requirement is missing. When this is the case, there is no
evidence for which costs have been assigned to the project or why. The probable result
is that large parts of the expenditure involved will be judged ineligible.

Involve partner finance managers from the start. Organisations have their own financial
management systems and procedures. All partners need to check that these comply
with programme requirements and the systems can deliver the evidence that is
needed.

Secure the audit trail. All partners must keep all invoices. Supporting documents are
also needed such as timesheets for part-time staff and calculations of overhead costs.
If these documents are missing, the costs involved will not be accepted.

Keep your filing up to date and find out what to file. Control visits typically have to be
announced only two weeks in advance. You should make sure that you always have all
documents available. Commonly missing documents are contracts and evidence of
public procurement procedures. If you cannot provide these documents, it will be
assumed that you have not followed the rules.

Find out what the national public procurement thresholds are in each partner country.
Put basically, public procurement rules require that public organisations request offers
for providing services and products. They are designed to promote a free and open
market and give value for money. There are three values that generally need to be
considered. Very small contracts do not need to be tendered. Larger contracts can be
the subject of a limited tender, whereby a smaller number of offers are requested.
Large contracts must be the subject of a full public tender with strict rules and
procedures. Small and large are relative terms here: There are enormous differences
between countries in the threshold values (the amount of the contract that determines
which tender procedure needs to be used). In some countries, full public tendering is
required for very small amounts and project managers should be aware of the delays
this will cause. You must respect the threshold values and the relevant rules - you
cannot divide contracts into smaller jobs to get around these rules. If you award a
contract for products or services, you must be able to prove that you used the right
tender procedure. These documents are often missing and the most common reason is
that partners say they did not know anyone else who could do the job involved. This is
not an acceptable reason and the full value of the contract will probably be judged
ineligible.

Financial Management Handbook
101
6.2 The payment chain Project reporting and claims for payment
Normally twice a year, projects are required to report on their progress so far (in an activity
report) and provide a statement of the money that all of the partners have spent (in a financial
report and claim for payment). The statement of expenditure must be certified by each
partners designated first level controller. The aim for projects is to ensure that all partners
deliver the proper documents on time and that enough information is provided to avoid the
need for programme follow-up.
The aim for programmes should be to secure ongoing project spending according to annual
targets and within audit rules. In part this involves making sure that projects have the
information needed to get things right first time. It also involves looking at programme
procedures to make sure that they allow for quick processing and follow-up on project claims
and have sufficient flexibility to allow for the inevitable changes projects will sometimes need
to make.
To secure a speedy payments system it is worth looking at the critical path of events right
from project approval to payment of a claim. The most effective improvements are to the
early part of the process, such as contracting, and have been covered already. Actually
making a payment should only take a short time so there is less to be gained from
efficiencies in this part of the process.
As a general rule, the simpler the chain, the lower the risk of mistakes and the quicker the
cycle can be completed. It is also worth making sure that the different programme bodies
involved CA, MA, JTS are adequately staffed to handle this part of the programmes
operations.
6.2.1 Reporting requirements
As discussed previously, some programmes allow projects to claim whenever they are ready
but most have claim deadlines to make sure that spending is reported in time to be included
in programme claims and to ensure that projects are progressing. Two claim deadlines per
year is standard and should allow regular enough project checks to ensure that problems are
spotted before they become serious. Sometimes a full activity report is required each time.
Sometimes only a short report is provided with one of the claims. Some form of activity report
is almost always required to cross check that expenditure has actually been incurred in
pursuit of project activities.
Some programmes have up to four claims rounds a year trading off increased workloads
and audit costs against the added security of frequent progress checks and financial control.
This may be particularly helpful where partners are inexperienced or there have been
frequent problems in the past. Programmes with two rounds have also sometimes been
forced to hold extra rounds to help avoid de-commitment in the early years of the programme.
Measures to avoid de-commitment problems are covered in depth earlier in the handbook but
may not always be enough to prevent this kind of situation in the future period. Not
surprisingly, it is unpopular with projects because of the extra effort involved in generating an
additional report and it is better to drop the requirement for an activity report if these extra
claims are needed. Activities must then be explained in the next standard report. Projects
may also not have anticipated the cost of auditing an extra claim (in programmes where there
is a charge for providing this service). While audit costs are an eligible expense it can be
difficult to cover these costs if they have not been budgeted for. In most cases, audit costs do
not vary significantly with the size of the claim so it is best to try to avoid procedures that
force projects to audit small amounts.
Financial Management Handbook
102

Payment chain: Summary

In most cases there are two claim deadlines per year
An extra claim round may help programme avoid decommitment
Consider the balance between the number of reporting claims required and the
increased workload and audit costs for projects
Programmes should set-up a quick payment system
The simpler the payment chain, the lower the risk of mistakes and quicker the cycle
can be completed
The payment chain should be looked at in its entirety. Apart from delays due to
certification difficulties, time-savings are often easier to find early on in the chain during
issue of subsidy contract stage.
A customer orientation is needed, especially from the CA. It is good practice to pay
claims within no more than 5 working days of receipt of a correctly certified claim by the
CA.
Electronic claims systems can help speed up payments and avoid mathematical
mistakes - the most common error in payment claims.
The most serious delays in payment are caused by financial control problems

The actual content of financial and activity reports reflects the content of the application form
so there are again big differences between programmes. In general, financial reports need to
show expenditure by budget line and by partner. Activity reports need to describe all main
activities and progress on meeting project targets (the indicators). This allows controllers and
the programme to assess progress against expenditure and identify any significant activities
that are not in line with the approved application or relevant rules and regulations.
Assessment of individual items of expenditure is the task of the first level controller.
Some programmes have introduced online claims systems, which give access to the
applicant, JTS, MA and CA. Online claims can help to speed up payment and cut down on
simple mistakes in filling in the claim form by using formulas to make most calculations
automatically (mathematical errors by projects account for most mistakes in making claims).
It is important that the system, if adapted from the mainstream Structural Funds, adequately
reflects Territorial Cooperation programme needs. It is also important to set up electronic and
protected signatures in advance for comparison with claims signatures from controllers. For
longer-term audit and record keeping, paper copies may still be needed.
6.2.2 Control / certification of claims
Any claim for ERDF funding must be checked by first level control at some point. The burden
of checking the correctness of claims falls initially on the first level controller who certifies the
expenditure claim from the project. A full description of what should be checked and common
problems is included in the separate chapter on financial control.
6.2.3 Assessment of reports
First level controllers tend to focus on the financial aspects of project implementation a
study of invoices and a check on whether totals have been calculated correctly (though as we
explain later, a more detailed check is actually required). Once a certified claim and report
reach the programme, they are often subject to an additional check focusing on the activities
carried out and making sure that the amounts claimed can be safely certified by the CA.
In some current programmes, claims are submitted directly to the Paying Authority, which
then carries out checks itself on whether all documentation is in place. Sometimes project
claims are first approved by the JTS, which carries out checks on activities and
documentation before passing the claim on to the PA. Sometimes, the claim goes from the
JTS to the PA via the MA. There is a full discussion of good practice in the performance of
these various checks in chapter 2. Basically, the MA (or the JTS) is required to approve
Financial Management Handbook
103
individual project claims while the CA draws up and certifies the claim for the programme.
The split is emphasised in the Implementing Regulation, which contains more details on the
MA checks (also covered in the financial control chapter).
Once programme level report assessment starts, a customer-based approach is important.
Delays in payment generally have little effect on large public bodies (but send a very bad
signal to projects about how seriously they should treat programme deadlines). Some smaller
project partners on the other hand run on very small budgets and any delays in payments can
have a serious effect. A few programmes make small advanced payments to these sorts of
bodies if they are confident that their accounting systems and management are good enough.
Some programmes also set the minimum amount for a payment claim as low as ?25.000 to
allow small claims for organisations with very small budgets and tight cash flows. This needs,
however, to be balanced against the cost of auditing such small claims.
The customer centred approach also extends to the treatment of problems in claims and
reports. In some cases the whole claim is blocked if a problem is found and this should
certainly be done if the problem is major or suggests that there may be further problems not
yet discovered (e.g. lack of basic of accounting evidence). In other cases, however, where
doubts are limited to an isolated case (e.g. a missing time sheet), this amount can be
deducted from the claim until it is resolved and then the main claim processed to allow the full
continuation of project activities. Programmes also need to be flexible if first level control
systems in one of the countries make it impossible for one or more partners to be included in
a claim. In these situations it should be possible for the rest of the partnership to go ahead.
The partner in the country with delays unfortunately has no option but to wait for the
certification to arrive.
It is good practice for Certifying Authorities to set target times for payment to projects from
date of receipt of a certified claim and to inform the project of the reason for any delay in
payment (for example if the programme is waiting for a payment from the Commission).
Efficient Paying Authorities in the current period have set a 5-day maximum payment target.
It is good practice to pay claims for preparatory costs with or before the first payment claim.
6.3 Helping projects with implementation problems
Aside from problems with eligibility of expenditure and activities, the main finding of report
assessment tends to be that some projects are seriously delayed. To give an idea of the
extent of this problem, in some programmes all projects are behind budget and behinds
schedule. As an extreme case, one project in the current period had only spent 2% of its
budget after two years of operations. The de-commitment rule creates a pressing demand for
financial discipline at the programme level and programmes cannot function if the project
level under-performs to this extent. There is therefore a growing realisation amongst
programmes that many projects need help in meeting their spending targets well before
serious slow or under spending becomes apparent through the payment claims process by
which time it is often too late.

In most programmes there are too many projects and too few programme resources to give
support directly to each partner. Programmes instead offer post approval advice to Lead
Partners at seminars but care should be taken to make sure that the advice given to a LP is
being passed on to other partners. Fact sheets on budget management and the payment
claims, reporting and certification processes can help to supplement this face-to-face advice.
The topics most often covered in Lead Partner seminars include making payment claims,
reporting and certification requirements. It is also useful to discuss general budget
management and procedures for changing budgets. It is worth trying to secure attendance at
Lead Partner seminars from project finance officers, as well as project managers.
A variety of other approaches have also been developed by joint secretariats and other
programme bodies to help the projects most in need of advice once implementation starts.
These include:
Targeting projects led by an inexperienced Lead Partner or where there is a new
partnership
Financial Management Handbook
104
Automatic follow up if a project fails to submit a report and payment claim on time
Requiring regular (sometimes even monthly or weekly) reporting on activities even if a
project is not due to claim payment. If a project has slipped in carrying out an activity the
associated spending will clearly be late
Carrying out site visits to a project early on in the projects life, although some
expenditure
has to have been incurred before this is worthwhile
A project is required to notify the programme body of when they are going to hold a full
partnership meeting so that the programme can send a representative if they wish to
The project can also be asked to go through a checklist of factors which might limit or
slow down spending i.e. securing planning permission for an investment, the loss of a
project partner. This type of risk management should feature in all Lead Partner project
planning.
All of these methods should help to detect danger signs and allow the programme to take
action. When taking this action, it is important that the programme does not try to take over
project management, which remains the responsibility of the partnership. The programme
can, however, request action in a number of areas or ask for an updated and more realistic
budget or time plan.

Over-budgeting

Project developers have a natural tendency to over-budget it gives them a reserve for
unexpected costs.
It becomes a problem when projects significantly under-perform against their budget
targets either because they are badly delayed or the original budget was too high.
Over-budgeting locks funds in projects and makes it impossible for other projects to
use them
Unused funds trapped in projects threaten programme de-commitment performance
Time invested by programmes in tutoring projects on developing budgets is time well
invested

It is unlikely that the measures described above will prevent all problems and programmes
also need to make sure that they provide themselves with the tools needed to tackle under-
performance once it does occur. In this connection, the estimated project budget per year
provides an essential monitoring baseline for the programmes. It represents the projects own
calculation of acceptable spending levels and therefore provides a fair indicator for assessing
under-spend. If there are no annual targets, there will be no standard against which to assess
whether the project is actually under-performing. The N+2 rule means that there are strict
limits to the under-performance a programme can tolerate in project budgets because it
cannot afford to have large amounts of inactive funding. It is important to firmly establish the
principle of projects keeping close to annual spending forecasts and the risk of losing funds if
this is not done. See section 4.8 on tackling poor project spending for more ideas on what
can be done about this problem.
Nevertheless, few projects run exactly according to plan and most projects will need to make
changes to their budgets during the projects lifetime. Adjusting plans is not a symptom of
failure. It shows that the project manager is making necessary alterations and programmes
need to be flexible and ensure that this kind of change can be made quickly and easily. If,
however, there is any attempt to change project objectives, there is a reason for extreme
concern. With all changes it is important to note that failure to keep proper records of all
alterations is perhaps the single most common cause of mistakes detected in programme
finances. It is therefore essential that the programme has a procedure for updating budgets
and making sure that all management bodies use the latest versions.
Financial Management Handbook
105
Minor Changes. Requests for minor changes (generally up to 10% of a projects budget)
are not surprising and do not generally denote a serious underlying problem. However, it
is always advisable to require written requests or notifications of budget modifications
with an explanation of the reason for the modification. Frequent budget changes should
also be avoided. If a budget adjustment looks necessary it may be worth advising a
project to wait until the end of the year to see if any other changes are required so as to
avoid making several changes in the same year (and more work for everyone involved).
Some changes cannot wait. If the amount allocated to a budget line has been exceeded,
more funds will need to be transferred to this budget line before the next claim can be
certified. Some changes should automatically require further information (e.g. material
investment), as these changes can lead to major alterations in the work to be carried out.
Major Changes. There may also be a need to adjust the budget to reflect modifications
in the activities envisaged. These tend to be larger adjustments requiring the approval of
programme management (generally the MSC which originally approved the project).
Referring budget changes to these bodies can cause delays and a written procedure
should be used if possible to minimise this. There may be further delay if a contract has to
be reissued. This level of change is a clear warning sign that there may be big problems
in the project and that either the budget has not been prepared properly or serious
changes are going to be made to activities. This kind of change therefore needs to be
well supported with explanatory documentation.
Shift of budget between partners. Programmes have different attitudes to budgets
shifts between partners. In some they are generally not permitted except in exceptional
situations they suggest a change in the balance of activities between partners and may
have implications for co-financing as the original co-financers are unwilling to support
activities in another country. In other programmes, they are regarded as unimportant as
long as all members of the partnership remain actively engaged in the project. Such
changes can after all reflect nothing more than deciding to run an event in another
country or may happen when a project is ending and a Lead Partner still has a lot of
administrative work to do. In all programmes, budget shifts will normally be allowed in
such cases provided that the amount involved is small. When large amounts are involved,
the SC will need to take a decision.
Spare money and new activities. There may be situations when a project would like to
make a change in the budget because there has been some saving, i.e. an activity has
cost less than originally planned. In these cases, however, the money should instead be
returned to the programme unless there is an SC decision approving new activities for
these unspent funds as only activities included in the original application are eligible.
One other solution to project implementation problems also needs to be utilised. The
greatest source of knowledge on improving project management and finding effective
solutions to the most common problems is undoubtedly the projects themselves. Some
experienced projects have developed very good and innovative financial management
practices within their partnerships, which can be promoted to other projects. Other Lead
Partners publish handbooks or guidelines on management procedures for all project
partners. Some have set up online monitoring systems, which are systematically updated
by all project partners, and having shared digital data systems can help secure
commitment and information from partners. There are also good examples of local
expertise in public agencies or local authorities for advising on project finances. This type
of resource should be identified as part of project monitoring and good practice should be
passed on to the rest of the programme
31
.


31
Most main points and documents will also be included in the upcoming handbook on project
management produced by INTERACT Point Qualification and Transfer
Financial Management Handbook
106
7. Certification of payment and financial control

The aims of financial control in the Territorial Cooperation Objective

Prevent misuse of funds
Prevent paying funds back to the Commission
Provide security that expenditure claimed is correct and spot problems
Identify projects with management problems and undertake corrective actions
Allow problem free programme closure

Problems with control in 2000 2006

Lack of communication between control bodies
Different control bodies use different interpretations of the same rules
Member States fail to prioritise control: Control arrangements are made too late and
too few staff are employed

Tips about control

Ensure dialogue between control bodies
Communicate early and clearly what is required from projects and controllers

The aim of financial control is to prevent misuse of funds and, as the ultimate consequence,
the need to reclaim incorrectly paid funds. Control work should provide security for the
Commission, Member States, programme bodies and, importantly, the projects themselves
by ensuring that problems are spotted and dealt with before they get too big. A multi-level
system has been established to do this based on a process with each level passing on
information, documents and specifications on what kind of certification will be provided to the
next level in order to build confidence that all expenditure declared is correct and the
programme can eventually be closed safely.
It perhaps helps to think of this process as a production line with each level working towards
the end product: Problem free programme closure. Each level in this process needs to know
what has been done before and what will be done afterwards in order to ensure that its own
work will contribute to and not interfere with the process. Everyone needs to know what
information they will be required to provide and what standards will be enforced. This means
that every level of the control process needs to be involved in a dialogue on control issues
and ensure that the information is passed on to the project partners who must meet these
standards.
The diagram below shows the main actors involved in the current period (2000-2006). The
terminology will change in the new period but the basic process is fundamentally unchanged.
First level control should be regarded as a day-to-day check and consists of:
...verifications made by management within an organisation should ensure that the processes
for which it is responsible are being properly carried out and are in compliance with the
relevant rules and regulations.
32
First level control covers 100% of programme expenditure. Second level control should be
regarded as a quality check of this work. It covers only a 5% sample of programme
expenditure. Third Level Control should be a formality. It involves checking that all other
control work has been completed and any recommendations have been carried out before
the programme is closed.


32
CDRR 06-0002-00 Draft working document concerning good practice in relation to management
verifications to be carried out by Member States on projects co-financed by the Structural Funds and
the Cohesion Fund (21/12/2005). The following section draws heavily on this paper.
Financial Management Handbook
107

Financial control structure in INTERREG (2000-2006)

In the current period, however, things have not always run smoothly. Some control bodies
were not identified until late in the programme and as a result problems that should have
been spotted were allowed to continue unchecked. Communication between first and second
level control bodies has often been poor and this has led to different organisations in the
same Member State using different interpretations of the same rules with disastrous
consequences for the projects, despite the fact they have no influence on these decisions.
This section of the handbook focuses on the new period 2007-2013. A detailed description of
first level control procedures in the current period is contained in Annex 2.
In order to improve control work a clearer control structure has been proposed in the
regulations governing the new period, with better defined divisions of responsibilities. This
Article 4 / First Level
Control
Carried out by: Competent first
level control bodies and JTS / MA

Purpose: To check project
activities and expenditure
Carried out by: The winding up body.
Sometimes the same body that carries
out Article 10 checks
Purpose: To check that Article 10
checks have been satisfactorily
completed and it is safe to close the
programme
Carried out by: PA
Purpose: To check that project
controls have been satisfactorily
carried out

Carried out by: Competent
second level control body
Purpose: To check programme
systems and procedures and
verify quality of project level
checks
All article numbers refer to Commission Regulation
(EC) No 438/2001, setting out control requirements
Article 10 / Second
Level Control
Article 9
Article 15 / Third
Level Control
Financial Management Handbook
108
should prevent duplication of control work. Each control body must now also be identified
soon after programme start and, as national rules are so important, each Member State will
also be required to publish the rules it is using.
7.1 First Level Control

First level control: Summary

First level control is central to programme implementation. It clears the way for
payments to be made to projects and is the best place to identify and correct
ineligible expenditure. Higher levels of control are fundamentally a check of the
quality of this first level control work.

Member States are obliged to designate a first level control body for each OP
Delays in certification during first level control may lead to very serious delays in
the payments claim process. Member States in a programme should help to speed
up the certification process by ensuring adequate staffing and clear rules.
Member State shall ensure that expenditure can be certified within a period of
three months

The audit trail: You always need it and it must allow controllers and auditors
to enter the management system at any level and trace back all declared
expenditure to original invoices or documents or equivalent value

Most problems identified at FLC arise from misunderstanding rather than fraud.
Programmes must therefore provide information on what is required from projects
(through the Lead Partner) and first level controllers. Repeated mistakes may well
be a result of poor programme information.

In formal terms, the first level control of project expenditure should verify:
Delivery of the products and services co-financed
Reality of the expenditure claimed
Eligibility of the expenditure
Compliance with the Commission decision on the programme, Community and national
rules
on eligibility, other national and Community rules including those on public procurement,
State
Aid publicity and information, protection of the environment and equal opportunities.
In practical terms this means verifying:
If the project report is correct with no essential errors or omissions
If the conditions for receiving the grant are fulfilled
If the grant is used for the purpose documented in the subsidy contract
If the information given by the final beneficiaries is correct and documented
If the reported expenditure complies with relevant rules
The first level controllers declaration has to cover 100% of the expenditure claimed and
100% of invoices are normally checked to provide sufficient security for signing the claim.
Generally this happens every time a project makes a payment claim.
Financial Management Handbook
109

Basic guide to financial control terminology

One of the most intimidating aspects of financial control for outsiders is the wide range of
terms in use. We try and cut through some of the confusion here with a guide to some of
the most important.

Audit / auditor: In Territorial Cooperation programmes this refers only to second level
control. An Audit Authority is set up and with the help of a Group of Auditors from the
countries participating in the programme, an audit strategy is developed. This audit checks
the quality of first level controls for at least 5% of the total programme expenditure.

Audit trail: The documentation kept by every partner that proves how all funds have been
spent.

Beneficiary: A beneficiary is defined as an operator, body or firm, whether public or
private, responsible for initiating or initiating and implementing operations. In financial
control terms this means all of the partners participating in a project.

Certified: Certification means that expenses have been approved by the body officially
responsible. It occurs at two stages in the claims process. Firstly, all expenditure from
every project partner is certified by that partners first level controller. Secondly, the
Certifying Authority certifies every programme claim before it is sent to the Commission.

Claim for payment: Every time a project reports to the programme it sends a statement of
expenditure showing how much money it has spent. This statement also acts as a claim for
the ERDF that the project expects to receive from the programme (based on the approved
ERDF grant rate). Programmes follow a similar procedure when they want to claim money
from the Commission.

Control / controller: In Territorial Cooperation this is used to refer only to the first level
control check. 100% of project expenditure is checked by a designated controller in each
partners country. This may result in deductions if some of the expenditure is incorrect.
When the correct amount has been confirmed, the controller will sign a controllers
declaration certifying that the expenditure has been approved.

Eligible: Used in financial control to describe expenditure that complies with all of the
relevant EU, national and programme rules. Spending that breaks one of these rules will
be found ineligible and will not be paid by the programme.

Irregularity: An irregularity is defined as any infringement of a provision of Community
law resulting from an act of omission by an economic operator which has, or would have,
the effect of prejudicing the general budget of the European Union by charging an
unjustified item of expenditure to the general budget. In practical terms this means any
attempt to claim ineligible expenditure whether deliberately or accidentally. Most
irregularities are accidental and are dealt with in first level control before funds are even
claimed.

Real costs: The whole system of payments is based on this principle. Projects can only
claim amounts that they have really been charged (amounts incurred) and can only claim
them from the programme after these amounts have actually been paid by the project.

Recovery: When funds are incorrectly (or unduly) paid to a project, the programme has to
get them back from the project partner concerned. Programmes do everything possible to
avoid this sometimes difficult procedure by holding back the last part of project payments
until they have control guarantees that the spending claimed is correct. The Commission
does the same to the programmes.

Systems audit: Generally also a task for the Audit Authority. This is done at the start of
the programme and checks the procedures established by all of the different management
bodies for administering the programme.

Financial Management Handbook
110
Systemic error: These are problems detected in management systems, which can be
expected to cause wide-ranging problems. They can occur at project level (e.g. failure to
secure the audit trail) or programme level (e.g. giving incorrect advice on public
procurement). They generally result in a suspension of payments and large grant cuts.

Third level control: In future this will also generally be carried out by the Audit Authority. It
involves preparing and approving the final statement of programme expenditure, the final
report and a winding up declaration certifying that all expenditure declared is correct and
that the findings or all controls and audits have been implemented. This control must be
completed before the programme can close.

7.1.1 Who is checked?
In the new 2007 2013 period all projects will be run according to the Lead Partner principle.
The Lead Partner is the administrative head of the project and the contact with programme
management bodies. Project partners will need to include organisations from at least one
other country. It is an important principle that first level control is carried out in each partners
own country and checks compliance with the national rules governing each partner. The Lead
Partner collects certified statements of expenditure from each partner and checks that the
approved controller has signed the claim and whether each partner has spent the funds on
the agreed activities only. They then calculate the claim for the whole project and draw up a
total statement of expenditure, which is sent to the programme together with each partners
statement. Controllers therefore do not need to check expenditure incurred in other countries
where other rules will apply.
7.1.2 Who are the controllers?
One major change in the new period will be that all Member States are obliged to designate a
first level control body for each OP. Some programmes in the current period have allowed
projects to select their own internal, qualified controller and this will no longer be possible.
Only external first level control bodies will carry out certification of expenditure incurred by
project partners. This new requirement should increase independence of the first level
controller from the project partner, transparency of the control process, the consistency of
standards applied and will encourage the development of control expertise. It is also to be
hoped that having more centralised control bodies will promote dialogue between these
bodies and second level controllers. It will be possible for programmes to designate one
controller for the whole programme area
33
but this is unlikely to be used in most programmes
because each participating country uses different rules.
The regulations for the new funding period also require each Member State to ensure that
expenditure can be certified within a period of three months
34
. Planning for how to make this
requirement work in practice should start as soon as it is possible since many programmes
are not currently meeting this target. Delays in payments to projects have been a significant
contributory factor to loss of funds under de-commitment rules. It is clear that programmes
should not expect efficient, financial management in projects if they are unable to live up to
these standards themselves.
The MA (but often the JTS on its behalf) will also continue to play an important role. Checks
by these bodies focus on the delivery of activities and compliance with non-financial rules
such as those on publicity and information. The MA is also responsible for again checking
that all partner claims have been certified by the approved controller (the Lead Partner should
already have checked this once before submitting the claim). Controllers and programme
management bodies can make deductions for the amount a project has claimed if they find
incorrect expenditure. As such they form inter-linking parts of the first level control procedure.


33
ERDF Regulation (1080/2006), 16.1
34
ERDF Regulation (1080/2006), 16.2
Financial Management Handbook
111

First level control procedure (2007-2013)









Partner

LP

LP

MA

MA

PP
2

CA

CA checks a
sample of
the project
claims to
confirm that
the work that
has been
done
provides a
sound basis
for making
the
programme
claim.
MA (possibly
delegated to
JTS) does on
the spot
checks of a
sample of
operations
checking
administrativ
e, financial,
technical and
physical
aspects as
appropriate.

LP checks
that all
claims have
been
certified by
the approved
controllers.
Draws up an
aggregate
project claim
(calculations
may also be
checked by
LP controller)

MA (possibly
delegated to
JTS) checks
certification
again. Also
checks
reports to
ensure the
project is
being
delivered in
accordance
with the
approved
application.

All project
partners
(including
LP) draw up
statement of
expenditure
and have it
checked by
nationally
designated
first level
controllers
Financial Management Handbook

113

One final body should also be included in the programme first level control structure the
Certifying Authority. Even though the name is new, the Certifying Authority will play a similar
role to the Paying Authority in the current period. The new name indicates the major role the
Certifying Authority plays in certifying programme expenditure before a payment claim is
submitted to the Commission. This third control of the payment process checks the quality of
the control work carried by the MA and LP as the basis of the programme claim to the
Commission. It is important to bear in mind that the control work carried by the CA must not
repeat all of the control work already carried out. If the programme system audit has been
positive, CA checks can focus on checking a few key procedures and perhaps a small
sample of claims.
7.1.3 What is checked by the first level controller?
First level controllers will check every item of expenditure entered in the programme
accounts, supporting documents such as time sheets and the calculation of the totals for
each budget line and the claim as a whole. The whole system is designed to provide
guarantees of the eligibility and correctness of all expenditure declared and this is the focus
of the checks.
As such, first level controllers will also look at key documents in the audit trail to make sure
that the costs claimed are real costs (e.g. overhead calculations), that the activities really took
place (e.g. participant lists from seminars) and that rules are being followed (e.g. evidence of
tendering procedures). The audit trail must allow controllers and auditors to enter the
management system at any level and eventually trace back all declared expenditure to the
original invoices (or documents of equivalent value). It should also be possible to verify the
transfer of funds to final beneficiaries. A clear description of the accounting evidence to be
held at each level is therefore essential as is communicating this information to everyone
involved. This is particularly important in the case of project partners, who play a key role but
are not always properly informed about programme requirements by Lead Partners.
As a general rule for all programme actors, expenditure that is not documented cannot be
claimed. An indicative list of the accounting evidence needed to secure the audit trail has
been developed by the inter-regional IIIC programmes. It seems like a lot of detail but all of
the information should be standard and easily obtained: All partners should get into the habit
of collecting this evidence from project start up. It is always worth remembering that one of
the main reasons that claims are reduced is missing evidence. Key points include:
Staff costs
List of staff working on a project stating name, qualifications, function, percentage of work
dedicated to the project and total salary
For people working part-time: Total salary, calculation of daily cost and total amount
charged to the project
Payroll and social security documents
Monthly time sheet, properly filled-in and signed, both by the employee and the
supervisor
Overheads
Explanation of the calculation method for setting the real cost of overheads
List of costs included in the calculation of the pro rata attribution of costs to the project
External experts
Contract explaining the type of task/ activities to be developed, duration and costs
Detailed invoices in accordance with the contract
Where applicable, deliverables produced by the expert
Where applicable, evidence that public procurement has been respected
Travel and accommodation
Travel invoices paid directly by the company/ institutions
Reimbursement request, with the relevant documentation required according to national
rules or institutional procedures, related to expenses incurred directly by the person
travelling.
Financial Management Handbook

114

When private cars are used, reimbursement request through mileage sheet, according to
national procedures and using agreed values.
Documentation providing evidence of participation in the activity involved.
Meetings and events
Evidence that the cheapest appropriate option has been chosen and, if applicable,
evidence that public procurement has been respected.
Contract with the service provider clearly stating the type of service to be provided, the
date of the service and the total cost.
Detailed invoice, clearly stating date of the invoice, the payee, the payer, description of
the services, quantification of the services, price per unit and the total cost.
Supporting documents such as the agenda and/ or minutes of the meeting.
Promotion costs
Evidence that the cheapest appropriate option has been chosen and, if applicable,
evidence that public procurement has been respected.
Contract with the service provider clearly stating the type of service to be provided, the
date of the service and the total cost.
Detailed invoice, clearly stating date of the invoice, the payee, description of the services,
quantification of the services, price per unit and total price.
Investments
In infrastructure:
Evidence of selection procedure for service provider
Contract with the service provider clearly stating the type of service to be provided, the
date of service and the total cost.
Invoices in accordance with the contract
In equipment:
Evidence that the cheapest option has been chosen for the required quality level
Detailed invoice, clearly stating date of the invoice, the payee, the payer, description of
the goods, quantification of the goods, price per unit and total price.
If relevant, depreciation method and amount charged in every payment request.

The audit trail: You still need it even if the controller does not ask to see it

The actual documents that a first level controller asks to see vary enormously. Some will
check everything while others will assume that a lot of the supporting evidence is in place
without looking at it. You still need these documents even if they are never used
during first level control. If you are part of a programme on the spot check, a second
level control check, a Commission audit or a check by the European Court of Auditors, you
will be required to produce the documents. If you cannot do so, you face having to pay
back large amounts of money just because you did not file a few papers.

Controllers are also required to certify not just whether expenditure has been properly
documented but also whether it is eligible or not. Most of this work will again be based on the
documents in the audit trail with a particular focus on expenditure for which there are no
invoices (generally the overhead calculations and the staff costs). The level of ineligible
expenditure detected during first level control varies enormously between about 3% and 25%
of the expenditure claimed in different programmes. Almost all of the incorrect expenditure is,
however, due to lack of knowledge about the rules and what can be claimed rather than
deliberate fraud.
Most programmes have started special seminars for project finance managers in order to
reduce the number of problems before they reach the control stage. If the basic tips included
throughout this handbook are used, there should be few problems.
Financial Management Handbook

115

Eligibility basics

Eligibility is often a cause for concern for project managers, as the rules can seem very
complicated and different national rules apply in each programme. When there is doubt
about an item of expenditure, the following questions should be asked:

Is it covered by the regulations?
There are a very limited number of rules (see below). For example, interest on debt is
never eligible.

Is it covered in national rules?
These mostly cover value for money. For example, some countries set maximum rates
for hotel stays in different European countries. You should make sure that the rules in
your organisation fit these national rules.

Is it covered in programme rules?
For example, private partners may be excluded.

Is this expenditure part of delivering the approved application?
If the activity involved is not clearly mentioned in the application, it will not be eligible.

Is this expenditure really necessary for delivering the project?
For example, do you really need to update office computers? You will be expected to
prove any claims you make.
Eligibility in the current period 2000 2006

In the current period the eligibility regulation (EC 448/2004) only covers a small number of
problem cases in twelve eligibility rules
35
:
Expenditure actually paid out
Accounting treatment of receipts
Financial and other charges and legal expenses
Purchase of second-hand equipment
Purchase of land
Purchase of real estate
VAT and other tax charges
Venture capital and loan funds
Guarantee funds
Leasing
Costs incurred in managing and implementing the Structural Funds
Eligibility of operations depending on the location
All other eligibility questions are subject to national rules (EC 1260/1999) and the answer to
one essential question: Is the expenditure necessary for the implementation of the project?
The same system will apply in the new period though with a slightly reduced set of rules in
the regulations. This means that most eligibility questions should be referred to national
authorities. This should be aided by the new requirement for all Member States to include the
eligibility rules they are using for the programme in the programme documents.
Difficulties are usually the result of projects trying to stretch the basic principles into grey
areas. A good example is the attempts in the current period to divide staff hours into
productive time and non-productive time and calculate hourly rates on productive time only.
This artificially inflates the staff costs claimed from the programme and contradicts the real
cost principle. Claim what you really pay and you will avoid problems. The interpretation of


35
For more information and practical examples on the 12 eligibility rules see: The Eligibility
Handbook developed by INTERACT Point Managing Transition available at: http://www.interact-
eu.net/913123/1068570/0/0
Financial Management Handbook

116

eligibility rules follows some very basic principles. Costs necessary for carrying out the
operation being funded are eligible unless clearly stated otherwise. Unnecessary costs are
ineligible. Some programmes have published their own guidelines with the agreement of
national audit representatives. If this kind of document can be agreed in the programme, it
provides an invaluable tool.
Eligibility in the new period 2007 2013
The basic principles of eligibility remain unchanged. Expenditure will be eligible for a
contribution from ERDF funds if it has been incurred between the date of submission of the
operational programme to the Commission or 1 January 2007 (whichever is the earliest) and
31 December 2015. Most programmes will only accept projects that start after approval by
the MSC but technically operations co-financed by ERDF can have started but must not have
been completed before the starting date of eligibility. Expenditure will be eligible for funding
only where incurred for operations decided on by the Steering Committee in accordance with
criteria fixed by the Monitoring Committee.
Most of the eligibility issues in the new funding period will again be regulated by Member
State national rules. Member States are obliged to publish their national eligibility rules within
12 months of OP approval and to make them easily accessible. This will increase
transparency as projects have not always been able to get reliable advice on the rules in the
current period and some countries seem to have applied different rules in different
programmes. It may also be a step towards harmonising eligibility rules as obvious and
unnecessary discrepancies may become apparent. It will mean that again that different
partners within the same project may be allowed to different things (for example claiming a
flat rate for every night away from home or only being able to claim real costs).
These differences are normally unavoidable and must be accepted by project partners. Some
programmes in the current period with differences in national eligibility rules have, however,
managed to develop a common set of rules based generally on the strictest interpretations of
the rules involved. Such common rules should be decided by the programme MSC and
described in the programme documents (e.g. Fact Sheets).
As mentioned above there are also slightly fewer Community rules on eligibility of
expenditure in the new period. Those that have been published so far are laid out in basic
form in the table below. It is also important to note that some of the twelve rules have simply
been incorporated into the main text of the regulations so while they no longer exist as
separate eligibility rules, the principles are essentially unchanged (for example the rules on
expenditure actually paid out and the accounting treatment of receipts). In all eligibility
questions it is, however, essential that the regulations are always consulted as the only
binding text and the relevant article numbers are also supplied.
An innovation in the new funding period is the possibility for transnational programmes to
spend part of the programme funds outside the programme eligible area (20% of ERDF
allocated to the programme) and for all programmes to spend funds outside the EU (10% of
ERDF allocated to the programme). This is regulated by 21 EC 1080/2006. It is important to
remember that spending funds outside the programme eligible area is possible only where
such expenditure is for the benefit of the regions of the cooperation area. However, this
decision should be made by programmes and projects planning their activities outside the
eligible area must get the programmes permission (this is generally an MA decision, as the
MA remains financially liable for these funds). There are a number of issues, which need to
be considered before funds are spent outside the programme area. One of them is securing
the audit trial and financial control situation. Handing funds over to a non-Member State
would still leave the Managing Authority responsible for how the funds have been spent, but
without the legal coverage of the regulations. In this case an agreement with the non-MS
involved should be required where the non-MS takes on the ultimate responsibility and
liability for the funds spent on its territory. If the 10% rule is to be used, the Member States
participating in the programme must make arrangements for ensuring that it will not be
misused 24 EC 1828/2006)
Financial Management Handbook

117

Summary: Key articles on eligibility in 2007 2013

Regulation

Article

Eligible

Not Eligible

1083/2006

56

In-kind contribution

Depreciation costs

Overheads

(See below for more details on
all of these costs)

1080/2006

7

Expenditure on housing for the
new MS only (and subject to
the conditions laid down in the
Draft Implementing Regulation,
47)

Interest on debt

The purchase of land for an
amount exceeding 10% of the
total eligible expenditure for
the operation

Decommission of nuclear
power stations

Recoverable VAT

1828/2006

1828/2006

1828/2006

1828/2006

49

51

52

53

Charges for transnational
financial transactions + bank
charges for accounts required
for implementation of the
operation

Legal consultancy fees,
notarial fees and costs of
technical or financial experts
necessary for implementation

Accounting and audit costs
related to MA requirements

Bank guarantees required by
legislation

In-kind contributions when
calculated according to the
approved methods

Overheads based on real
costs. Flat rates are possible
based on the average real
costs of the type of operation
(properly documented) and
subject to review. Flat rates
may not exceed 25% of the
overhead generating costs of
an operation

Depreciation of assets actually
used for an operation for the
period of that operation

Fines, financial penalties and
expenditure on legal disputes

Purchase costs for these
assets
Financial Management Handbook

118

1080/2006

21

Flexibility rules:

In the context of cross border
cooperation, up to 20% of OP
ERDF can finance operations
in adjacent areas

In the context of transnational
cooperation, up to 20% of OP
ERDF may finance expenditure
incurred by partners outside
the programme area

In the context of cross-border,
transnational and interregional
cooperation, up to 10%of OP
ERDF may finance operations
outside EU

7.1.4 What is checked by programme management bodies?
The programme is required to carry out an administrative check of the project claims and
reports received. This is formally the responsibility of the MA but the task is often delegated
to the JTS. On a very basic level this check will confirm that all partner claims have been
correctly certified. The programme will also check the activity report to make sure that project
progress is on track, the activities carried out are in line with the application and no ineligible
activities have been included in the claim.
The new regulations also include a clear requirement for MAs to carry out on the spot checks
of projects
36
. At least a sample of projects must be checked with the possibility that any
project may be checked at any point in its lifecycle and repeat visits may be carried out.
Every programme should provide a checklist of the issues that could be covered during such
checks and they can cover administrative, financial, technical and physical aspects. What this
means in practical terms is that the check will, for example, require projects to again produce
evidence from the audit trail, explain and demonstrate accounting systems, prove the delivery
of the products and services financed etc. Because of the frequency of errors in calculating
overhead and staff costs, this expenditure will almost always be included in the check. Most
on the spot checks are targeted at Lead Partners but any partner may be checked,
particularly if a Lead Partner check had revealed weaknesses in the project. In order to be
effective, on the spot visits must control expenditure down to a project partner who actually
spends the money, rather than stopping at the LP level.
7.1.5 What happens if there are problems?

There are three basic results of first level control checks. Normally, project expenses are
approved and no further action is required. In cases where problems are detected, the
incorrect expenditure will be deducted from the project claim and will not be paid by the
programme. In other cases, controllers may have reservations regarding, for example, the
lack of important documentation. In these cases the programme will require that
documentation or other clarification is provided within a fixed time. If the evidence is not
provided, the expenditure will be refused. In the most serious cases control findings may
create doubts about funds previously paid out to projects. These situations normally arise
after on the spot visits. Controllers check expenditure that has not yet been paid out so it is
easy to make deductions. On the spot visits, on the other hand, can go back over the whole
expenditure declared by a project and may find problems in amounts that have already been
certified. Once again, a lack of reliable evidence for staff and overhead costs is a typical
problem. This may create a reasonable suspicion that all such costs reported by the project


36
Implementing Regulation, 13
Financial Management Handbook

119

partner concerned are incorrect and as a result the programme may actually claim back
money that has already been paid. The amounts concerned may also need to be reported to
OLAF (the European Anti-Fraud Office).
Reservations and recoveries both take time to resolve and the whole partnership will have to
wait for payment. It is therefore essential that the whole partnership is made aware of
requirements and the Lead Partners with suspicions about the expenditure of a partner
consult the programme as soon as possible.
7.2 Second Level Control / Audit

Second level control: Summary

The Audit Authority is a new programme body responsible for Second Level Control
Audit Authority may be supported by a Group of Auditors
Second Level Control consists of audits of programme management and control
systems and an appropriate sample of project expenditure
Second Level Control is carried out according to the Audit Strategy presented by the
Audit Authority to the Commission within nine months of the OP approval
Audits should be carried out at least once during the programmes life on all
programme bodies in the financial circuit

Second level control consists mainly of a quality check of a sample of first level control work.
In the 20002006 period the sample to be audited was not less than 5% of total programme
expenditure. Regulations for the new period 20072013 do not specify how big the sample
should be but according to 62b EC 1083/2006, audits should be carried out on the basis of
an appropriate sample of expenditure declared and should be sufficient to ensure a
confidence level of no less than 60%. This generally means that more than 5% will have to be
audited.
The other important element of second level control is a check of management and control
systems to ensure that the systems in place are being used and should be able to detect and
correct problems at project and programme level. Second level control is therefore an audit of
all aspects of the programme at both the management and project levels to make sure that
everything is working as it should be.
Second Level Control should be carried out according to the Audit Strategy decided by the
Audit Authority no later than 9 months after programme approval. The Audit Strategy should
outline how Second Level Control audits will be carried out and should draw up common risk
assessment criteria to select an appropriate, representative sample of programme funds
subject to the Second Level Control audits.
Financial Management Handbook

120

Second level control process

Responsibilities of the control bodies in the new period have been defined in Regulations:
General (EC) 1083/2006, ERDF (EC) 1080/2006 and Implementing Regulation 1828/2006
The content of second level control will change little in the new period but there are some
changes to the structures that will be responsible. A new management body the Audit
Authority will be set up in the Member State hosting the MA and will be in charge of the
controls. It will normally be assisted by a Group of Auditors with one representative from each
participating country though programmes can decide to let the Audit Authority work alone.
The auditors will be responsible for checks carried out in their country. The actual checks will
either be carried out by these auditors or will be sub-contracted to an outside audit firm. In
actual fact most of the changes involved here are a matter of terminology: The role of the AA
has in the current period been carried out by the national controller of the Member State
hosting the MA and he/she has been assisted by a Financial Control Group consisting of the
national controllers from the other participating countries. The main difference between the
Audit Authority and the current arrangements is that the AA will be a formal, fixed programme
body and must be set up within 3 months of OP approval. This should reduce the problems
caused by delays in initiating second level control checks in the current period.

Project

First Level Control

Designated
controllers
Responsibilities
assigned by
Member States
On-the-spot
Administrative
check

Certifying Authority

STAGE 1

STAGE 2

STAGE 3

STAGE 4

Check by Audit Authority
and nationally designated Group of
Auditors

Checked

Checked

Financial Management Handbook

121

Audit Authority and Group of Auditors work flow

National auditor

Compiled

project

control report


(

was

Article

10

report

)

Project checks

Audit

Authority

(MA country)

Commission

Group

of

Auditors

Project checks

Annual control

report

(

was

Article

13)

INPUT
National auditor

Compiled

project

audit report

(

was

Article

10

report

)

Project checks

Audit

Authority

(MA country)

Commission

Group

of

Auditors

Project checks

Annual audit

report

(

was

Article

13)

INPUT

In regulatory terms, the Audit Authority must be a national, regional or local public authority or
body, functionally independent of MA and CA, designated by the MS of each OP. The Audit
Authority will:
Ensure that audits are carried out to verify the effective functioning of the management
and control system of the operational programme; (= systems audit)
Ensure that audits are carried out on operations on the basis of an appropriate sample to
verify expenditure declared; (= check of an appropriate, representative sample
of programme expenditure)
Present to the Commission within nine months of the approval of the OP an audit strategy
covering the bodies which will perform the audits (as in point 1 and 2), the method to be
used, the sampling method for audits on operations and the indicative planning of audits
to ensure that the main bodies are audited and that audits are spread evenly throughout
the programming period;
By 31 December each year form 2008 to 2015:
Submit to the Commission an annual control report setting out the findings of the
audits carried out during the previous 12 month period ending on 30 June for the year
concerned in accordance with the audit strategy of the operational programme and
reporting any shortcomings found in the systems for the management and control of
the programme. The first report to be submitted by 31 December 2008 shall cover the
period form 1 January 2007 to 30 June 2008 (= annual audit report)
Financial Management Handbook

122

Issue an opinion, on the basis of the controls and audits that have been carried out
under the responsibility of the Audit Authority, as to whether the management and
control system functions effectively, so as to provide a reasonable assurance that
statements of expenditure presented to the Commission are correct and as a
consequence reasonable assurance that the underlying transactions are legal and
regular (= annual audit report)
Submit any declaration for partial closure assessing the legality and regularity of the
expenditure concerned
Submit to the Commission at the latest by 31 March 2017 a closure declaration
assessing the validity of the application for payment of the final balance and the
legality and regularity of the underlying transactions covered by the final statement of
expenditure which shall be supported by a final control report. (= winding up
declaration)
The Audit Authority shall ensure that the audit work takes account of international
accepted audit standards;
Where the audits and controls are carried out by a body other than the Audit Authority,
the Audit Authority shall ensure that such bodies have the necessary functional
independence;
37
The programme systems audit ensures that programme bodies, procedures and documents
have been set up and function in line with the principles described earlier in this handbook.
Very importantly it will also check the day-to-day working of programme systems - particularly
in relation to the link between programme management and projects. Some of the project
checks will then follow-up on the project side of these procedures to combine the results of
the systems of audit and the audit of projects and gain an overall picture of the programme
38
.
We focus here on the audit of projects. These audits must cover a minimum of 5% of the total
programme expenditure. The projects to be included in the checks are selected on the basis
of two sampling techniques carried out in line with various International Standards on
Auditing (ISA) and with different purposes. The main technique used is representative
random statistical sampling. As the name suggests, the aim is to find a random sample of
projects which can be assumed to be a fair representation of the programme as a whole: If
there are few problems in these projects it can be reasonably assumed that there are few
problems in the rest of the programme. The only weighting here is that projects receiving the
largest grants should be more likely to be selected (though some small projects must also be
included).
In addition, a complementary sample is selected. This aims firstly to ensure the completeness
of the checks by guaranteeing coverage of:
An adequate mix of different types and sizes of operations
All the priorities under the operational programme
Operations managed by the main Authorities and intermediate bodies
Operations concentrated under certain beneficiaries
The second aim is to allow the use of risk analysis results to target the projects that are most
likely to have problems. The intention here is clearly to identify and correct irregularities by
going after the weakest projects rather than those that fairly represent the programme as a
whole. As a result, the results of audits on these projects are treated separately and are not
used when calculating the overall irregularity rate for the programme.
The methods used for selecting different samples, the projects selected and a plan for
carrying out the actual audits are combined in a regularly updated audit strategy.


37
Based on General Regulation (1083/2006), 62
38
The information here draws heavily on the Implementing Regulation, 16-18 and the relevant
annexes (especially Annex V, VI, VII, VIII, XII)
Financial Management Handbook

123

The purpose of second level control checks

is to gain an overall picture of the programme and how many errors there normally are in
the expenditure declared. Second level control should not just target the highest risk
projects, as this will create a distorted picture of the programme with a higher rate of
irregularities than is true for the whole programme. In the new period, high-risk projects are
targeted separately and the same principle needs to be applied in the control of the current
programmes.

Second Level Control work should start as soon as the programme has been approved. The
initial systems audit is carried out as part of the procedure to gain Commission approval for
the programmes systems and procedures. It should be completed in the early months of the
programme as its purpose is to confirm that sound management practices are in place: It is
pointless to suggest major changes later in the programme when most of the damage will
already have been done and needless effort will be required to correct errors.
The check of projects should also start as soon as possible though it is possible to wait and
audit a sample of the combined expenditure from 2007 and the first part of 2008, as few
programmes will have much project spending in 2007. Most auditors prefer not to consider
projects that have spent less than 50% of their budgets. There are two reasons. Firstly, the
auditors need a reasonable amount of spending to check if their conclusions are to be of
value. Secondly, they need to check an appropriate sample of the total programme spending
and are obviously able to reach this target quicker if they are able to check a project when it
has spent 1 million rather than 500.000. In some cases this means that auditors prefer to
check completed projects but this needs to be balanced against the difficulty of taking
corrective action: There is not much that a project can do after it has submitted its final report
and claim. Ideally therefore, second level control should be carried out on ongoing projects
and it is requirement of the regulations that these audits are spread evenly across the
programmes lifetime.
Audit visits are coordinated to take place simultaneously, with each auditor visiting the project
offices of a partner in their own Member State so different parts of the project partnership are
checked (only the expenditure of the partners checked counts towards achieving an
appropriate sample required by the regulation). These results are then merged into a report
on each project including an overall opinion and any follow-up actions that need to be taken.
Every year the Audit Authority also submits to the Commission an annual audit report
summarising the work that it has carried out and its opinion of the way that the programme is
functioning. If a large number of problems have been detected, this can lead to a suspension
of payments to the programme until the problems are resolved.
Financial Management Handbook

124

Likely division of tasks between the Audit Authority and the Group of Auditors

AA (= Audit Authority)

AA + GoA (=Group of Auditors)

Compliance assessment opinion on the Art
71 Description of management and control
systems

Members of the Group of Auditors may be
involved in compliance assessment of
management bodies outside the MA host
country

Audit strategy

Audit strategy
Audit methodology

Audit methodology and selection of an
appropriate sample

Systems audit

Audits of operations
Compiling integrated project audit reports

Partial (national) reports
Integrated annual control reports to
Commission

Annual opinion on the management and
control systems

AA is a coordinating body for the MSs,
contact point with the Commission and
usually auditor in the MA Member State

The costs for this audit work can be met in full or in part from the TA budget. However, it is
recommended by the Commission that the costs of second level control should be borne by
the MS as the establishment of control and audit systems are MS responsibilities. This should
be agreed in advance between Member States. The AA may also draw on the assistance of
the JTS though this relationship needs to be carefully defined and is normally limited to
administrative support because the JTS is a key part of the programme and project system
that is being audited.
Financial Management Handbook

125

Audit Authority and Group of Auditors basic procedures

JTS
Commission
Member
States
Audit
Authority
Group of
Auditors
Meeting arrangement
and papers
Project
documentation
Administrative
reports
Feedback /
follow-up
Instructions
Audit reports and
recommendations
Quarterly
irregularity
report
Annual audit
report
SOME BASIC PROCEDURES
JTS
Commission
Member
States
Audit
Authority
Group of
Auditors
Meeting arrangement
and papers
Project
documentation
Administrative
reports
Feedback /
follow-up
Instructions
Audit reports and
recommendations
Quarterly
irregularity
report
Annual audit
report
SOME BASIC PROCEDURES

7.2.1 Content of audits and common problems detected
As noted, second level control is fundamentally a check of the work carried out during first
level control and as such the things that are checked are very similar. One major difference
already mentioned is that first level control only considers the expenditure in the claim that is
being certified. Second level control addresses the whole of the project. In technical terms,
audit of an appropriate sample of the programme expenditure can include actions to:
Verify practical application and effectiveness of project management and control systems
Prevent and take actions against irregularities
Recover any amount lost as a result of an irregularity or negligence
Verify selectively declarations on expenditure made at the various levels concerned
Verify the correctness of accounting records held by the final beneficiaries and the firms
carrying out the projects and in particular that:
o Programme records correspond with supporting documents held by the
project
o The nature and timing of the relevant expenditure comply with Community
provisions and correspond to the approved specifications and the work
actually executed
o Services and actions funded under the Structural Funds are procured on the
basis of a proper call for tenders according to public procurement rules, if
applicable, and are fully evaluated before a final decision is made on the
supplier of the service
o Project LP/PP complied with the Community rules on publicity, information,
equality and the environment and any other relevant Community law
Verify the presence of a suitable audit trial and that:
o
o The first level controller is qualified and familiar with relevant regulations and
has experience with auditing EU-funded projects
o The first level controller signs a confirmation of project first level control
Verify that the appropriate national co-financing has in fact been made available
Facilitate the identification of possible weaknesses or risks in the execution of actions and
operations
Financial Management Handbook

126

Provide for corrective measures to be taken to eliminate weaknesses or risks in the
execution,
in particular as regards financial management
We could summarise this by saying that the audit again checks whether there is proof that
costs have been incurred only for relevant activities, whether the expenditure is eligible (note
the specific mention of public procurement) and whether project systems and procedures
provide reasonable assurance that this is the case for all of the partners expenditure. Where
problems are detected, auditors are also specifically responsible for making corrections and
ensuring that any money owing to the programme as a result is paid back.
As such, projects that are part of the second control audits should not expect anything
fundamentally different from other controls: It is a check of the same evidence that should be
available before any expenditure is claimed. The amount of deliberate fraud detected in
audits is low. Most problems arise because of confusion about programme requirements and
poor first level control. This is particularly true when first level controllers do not ask to see
supporting documents in the audit trail: Project managers sometimes assume this means
they are not needed or take a gamble and hope they will not be included in the second level
control sample. This can be an expensive mistake.
The list of common problems included below is based on the findings reported by one
Member State but seems fairly representative:
Requirements of regulations (particularly the eligibility rules) were unknown
Public procurement rules were unknown
Documentation was not available to demonstrate a clear link between work actually
executed and the declared expenditure (i.e. parts of the audit trail were missing)
The EU sign was missing on all publications and the relevant papers had already been
distributed (i.e. EU communication and publicity rules were broken)
No documents and evidence for the co-financing were available
The project partner had changed address without informing the programme
The project title was missing from some invoices
Financial departments are decentralised and the book-keeping system could not be
checked
Payments were without invoices, only bank account statements
The project partner did not submit all original invoices. Original invoices for travelling
costs were not available
Invoices from one sub-partner were paid after payments were received from the EU
Personnel costs included overheads without a comprehensible calculation
One invoice was included twice
Exchange rate - invoices contained two different exchange rates
The financial report was not signed by the first level controller
If you have read the other sections of the handbook, most of these problems will come as no
surprise they are exactly the same issues that turn up again and again at every level of
checking. Avoiding problems in programme audits is therefore a matter of sticking to a few
simple rules but these findings suggest that programmes still have more to do on
communicating these rules and projects have more to do on making sure they are respected.
7.3 Financial Corrections and Recovery
One last important point needs to be made about second level control. As it concerns the
audit of funds that have already been paid out by the programme, any errors detected may
result in the project having to pay back money. The errors are termed irregularities. The
process of getting the money back is called recovery
39
.


39
Based largely on the Implementing Regulation which in turn closely follows EC Regulation
2035/2005 amending Regulation (EC) No 1681/1994 concerning irregularities and the recovery of
sums wrongly paid in connection with the financing of the structural policies and the organisation of an
information system in this field.
Financial Management Handbook

127

Any irregularities detected must be demonstrated to have been resolved before the project
(or indeed the programme) can close. The Certifying Authority is responsible for launching
the recovery procedure and initially recovers the funds directly from the Lead Partner. The
Lead Partner then initiates a recovery of the funds from the project partner concerned.
Problems are relatively rare but can occur that the project partner involved will not or cannot
return the funds concerned (in cases of bankruptcy for example). In these cases the Member
State where the non-paying partner is located will pay the funds to the Certifying Authority,
which will then repay the Lead Partner
40
. This is another reason that a Lead Partner needs a
certain level of financial resources in order to be able to take on the role.
Beyond this programme level treatment of irregularities, however, there are also additional
procedures between the Member States and the Commission. Two months after the end of
every quarter, every MS must send the Commission a report with details of all irregularities
concerning amounts over 10.000 detected on its territory and a description of the follow-up
action taken on previously reported irregularities (information generally provided by the
second level controllers). If there have been no irregularities over 10.000, the report must
state this and still needs to be sent. These reports ensure that action is taken and that there
are continual deadlines at each step of the procedure.
As has been discussed previously, the official definition of irregularities is extremely broad
and covers not just funds incorrectly paid but also actions that could have led to funds being
paid out incorrectly. For this reason the Implementing Regulation introduces some
qualifications to the concept and what needs to be reported to the Commission. The following
are not reported:
cases where the irregularity consists solely of the failure to partially or totally execute an
operation included in the co-financed operational programme owing to the bankruptcy of
the beneficiary;
cases brought to the attention of the Managing or Certifying Authority by the beneficiary
voluntarily and before detection by either of them, whether before or after the payment of
the public contribution;
cases detected and corrected by the Managing or Certifying Authority before any
payment to the beneficiary of the public contribution and before inclusion of the
expenditure concerned in a statement of expenditure submitted to the Commission and
which do not involve suspected fraud.
However, irregularities preceding a bankruptcy and cases of suspected fraud must be
reported.
41
In these cases (which cover the majority of irregularities detected in cooperation
programmes) the programme has the power to resolve the issue independently though the
amounts concerned will still need to be recovered and reported on by the Certifying Authority.
One final improvement in the new system should also be mentioned. In the past some
Member States have refused to accept second level control findings because they create the
need for a recovery from partners on their territory. The new regulation therefore contains a
trigger point for defining when a problem should be treated as an irregularity or possible
irregularity the primary administrative or judicial finding which:
means a first written assessment by a competent authority, either administrative or judicial,
concluding on the basis of specific facts that an irregularity has been committed, without
prejudice to the possibility that this conclusion may subsequently have to be revised or
withdrawn as a result of developments in the course of the administrative or judicial
procedure.
42
The reports of the national auditors will constitute such findings and once the written
assessment has been provided, all Member States are obliged to include all the operations


40
ERDF Regulation (EC) 1080/2006, 17
41
Implementing Regulation, 28.2
42
Implementing Regulation, 27 (b)
Financial Management Handbook

128

covered in these findings in their quarterly irregularity reports to the Commission. In future it
will therefore be impossible to avoid taking action on control findings.

Comparison: Control in the current and new period

2000 2006

2007 2013

First Level Control

Not all MSs designate FLC bodies

FLC sometimes carried out at LP level only
MS designate FLC bodies for each OP

FLC carried out at all partners level

No deadline for certifying expenditure MS must ensure a 3 month deadline for
certifying expenditure is respected

Second Level Control

Second Level Control Group is not formalised
and sometimes not established until late in the
programme

SLC is carried out by Audit Authority, formal
programme body

Audit Authority is based in the same MS as MA

Audit Authority is assisted by group of auditors
from MS in the OP

Group of Auditors is established within 3 months
after OP approval

Audit Authority presents to the Commission the
audit strategy within nine months of the OP
approval

Audit Authority approves OP description of
systems and procedures

Recovery of funds unduly paid

LP ultimately responsible for the unduly paid
amount

LP repays the irregularly paid amount to CA
LP initiates a recovery process and recovers the
amount from a Project Partner responsible
MS of the project partner responsible for
irregularity is ultimately responsible for unduly
paid amount

Eligibility

-National rules
-(EC) General Reg. 1260/1999
-Implementing Reg. 448/2004 covering 12
Eligibility Rues

-National rules published by MS within 12
months of OP approval
-General Reg. (EC) 1083/2006
-ERDF Reg. (EC) 1080/2006
-Implementing Reg. 1828/2006

More transparent rules
A step towards harmonisation

Financial Management Handbook

129

8. Project and programme closure
The closure of the new programmes (2007-2013) is a long time in the future while the current
programmes will be closing over the next few years. This section therefore focuses on the
current period and uses the corresponding terminology.

Project and programme closure: Summary

The main aim in this phase is to properly account for the resources used to meet
programme objectives
Quick problem-free project closure depends on the effectiveness of the project
management that has been in place for the duration of the operational phase of the
project.
It also depends on the efficient working of the Member States or regions with the
financial controllers for the programme and the PA
Programmes should try to avoid delays in making final payments to projects particularly
those with very small budgets and cash flows
Programmes could use the opportunity given in final reporting from projects to seek
feedback on the future operation of financial activities at the programme level.
Programme closure documents must be submitted to the Commission no later than 15
months after final programme eligibility date (31 December 2008), i.e. 31 of March
2010.
It is possible for programmes which will continue in 2007 2013 to finance programme
closure related activities of the old programme with the new TA budget

8.1 Project closure

Project closure: Summary

Focus on the end goals, results and impacts
No questions can be left open
It is the last chance to identify and deal smoothly with irregularities
It is a final confirmation of the findings of all first level control checks
After closure projects are still subject to second level control or checks by Commission
auditors

Project closure is the final phase in the project implementation process and if implementation
has been successful, it should be relatively problem-free. The focus at project closure is on
the end-goals, results and impacts achieved in comparison to the activities proposed in the
application and changes approved by the programme. Attention therefore needs to be paid to
indicators and the completion of all work packages. If these have been successfully
completed within budget the project can close once it has completed the final financial
control.

Programmes need to be confident to answer a number of fundamental questions:

Has the project delivered the activities outlined in the application?
Is there sufficient evidence to support this?
Has first level control been good enough to ensure that no serious problems
should be experienced if the project is later controlled by another body?
Have all questions and problems identified by first level control been satisfactorily
resolved?

Financial Management Handbook

130

While projects are in the main implementation phase, programmes can afford to be flexible:
Deductions can always be made from later payments and it is not yet possible to provide a
final assessment of activities. Project closure means, however, that no more questions can
be left open. This is the main challenge of project closure: It represents the last chance to
identify and deal with irregularities relatively easily.
The extent of programme concerns will be determined by the systems in place for normal
project control. If a centralised first level control system is in place, there should be few
doubts about the eligibility of expenditure but there may be concerns about the need for
verifying the reality and quality of the outputs delivered (on-the-spot checks are rare in
centralised systems). If a decentralised model is being used, there may be doubts about the
quality of the first level control work carried out and whether controllers have sufficient
knowledge of INTERREG requirements. The special procedures for processing final reports
and claims for expenditure need to be designed to compensate for whatever weaknesses the
general system may be felt to have.
Another tool that programmes make use of is to withhold payment of a portion of the project
budget (typically 5%) until all project closure procedures have been completed (though this is
not a regulatory requirement). This means that even at this stage most irregularities can be
resolved by simply deducting the amount concerned from the payment to the project. Some
programmes go further and retain up to 20% in order to ensure that they are withholding
sufficient funds to deal with this type of problem.
Programmes that only retain 5% should also decide whether this should be 5% of the total
project budget or 5% of the total funds claimed: The average under-spend for projects in
INTERREG programmes seems to be about 5% so if programmes are working on the total
approved budget, they will actually have little room for manoeuvre. If programmes instead
work on 5% of the claimed budget, they will have to monitor projects closely when they are
nearing closure to be sure that none of this final 5% is actually paid out. In addition to
providing insurance against irregularities, the 5% retention also gives programmes leverage
to ensure that projects submit final reports in good time. After the 5% has been paid out,
errors can only be corrected by initiating a recovery procedure and programmes prefer
understandably to avoid this if at all possible.
Project closure should be a final confirmation of the findings of other first level control checks
and there is no real difference in procedure as far as financial checks are concerned (other
than the need to use an external controller if this has not been done before). Activity checks
are generally stricter in order to ensure that the project has delivered all outputs and that
there is a reasonable probability that expected results and impacts will be achieved.
One other important issue is to make sure that projects understand the meaning of closure. It
is a closure of the programmes grant to the project but does not represent the end of
programme requirements towards the project. Even though the programme has accepted the
final report and made the final payment, the project is still subject to second level control and
checks by Commission auditors and the Court of Auditors. All project records and
documentation therefore need to be retained and stored until three years after the formal
closure of the programme (in theory this could mean until 2013). The same applies, of
course, on the programme level and a key weakness on both levels is that key staff who
could explain project actions have usually left the organisation long before later control visits
take place. Project and programme records (the audit trail) should therefore be good enough
to allow new staff to provide these explanations.
8.2 Steps to project closure
Accumulation of project records. The initial step in closing an INTERREG project is the
accumulation of all official project records. These records include all accounts, papers,
photographs or other documentary materials made or received by the project partnership
in connection with the implementation of this project. These records should be kept by the
project partnership.
Preparation of project final reports. In order to receive the final payment, projects need
to submit final reports. There are no standard rules about deadlines and documentation
Financial Management Handbook

131

required to accompany final reports. In some programmes, the final report must be
submitted by the end date for the project. In others the end date is used as the time for
stopping implementation and the final report does not need to be submitted until three
months after this (the actual close date). No activities are eligible after the project close
date.
Only one exception is sometimes made in programmes that also regard the end date as
the close date. In these programmes it is sometimes possible to claim costs for activities
related to the development of the final report after the end date (e.g. staff costs, printing
and the final project audit) if these services have been contracted on a fixed cost basis
before project end. They may then be included in the final statement of project
expenditure even though they have not yet been formally incurred (the only time this is
possible).
Content of final reports. The required documentation differs across programmes though
in general, programmes tend to ask their projects for a lot of information in the final
reports. Programmes prefer to get more rather than less information to be sure they have
what they need in future.
A final report is divided into the activity and financial sections. The activity section
sometimes includes the last periodic report covering the activities carried out in the final
months of the project. Sometimes, however, the last standard report is kept separate and
the final report focuses on lasting impacts of the project activities as a whole. In general,
the activity report needs to include:
Executive summary. The executive summary is also a good source of information for the
programme database.
Results obtained referring to the targets for these in the approved application. Overall
project evaluation and project impact indicators
How the project results will be disseminated and activities followed up
Partnership evaluation. Programmes may use the project closure phase as an opportunity
to ask Lead Partners for the overall evaluation of the partnership, how it worked, what
kind of problems were experienced and what solutions were proposed. Programmes
should also ask projects to assess programme performance.
The finance section of the final report includes:
Completion of first level control - The final financial report must include audited
statements from all project partners and an audited statement for the whole partnership.
The final first level control refers not just to individual items of expenditure but to the
overall use of the funds granted in obtaining project goals. The controller here certifies all
expenditure for the whole project thereby declaring that all claimed expenditure is correct.
Controllers should also describe the first level controls carried out for each partner with
their findings and conclusions, sum up the extent to which the project has been carried
out in accordance with the approved application, subsidy contract and any other
conditions. The controller must also confirm that all control issues have been satisfactorily
resolved. Drawing up this report may also require that a new controller is used. Where
internal controllers have been allowed for interim claims in the current period, an
independent external controller must be used for the final report.
Assessment of the Final Report. At project closure, programmes assess final reports
against the project applications with approved changes. At this stage they may discover
that the project has not implemented all activities in the application or that it has carried
out activities not included in the application. Strictly speaking there should be a cut in the
ERDF grant in both cases as changes have been made but never discussed and agreed
with the programme and in many cases this is exactly what will happen. In some cases
programmes take a more lenient approach and try to analyse the activities performed and
paid for by projects even if they have not been approved before. If the activity is assessed
as having added value to the project and the amount in question is not significant, most
programmes approve it as an eligible cost. If the activity adds value to the project but the
amount is significant, the issue is discussed with the SC. If there is no added value (such
Financial Management Handbook

132

as using extra funds to purchase new computer equipment) the amount should be
declared ineligible. The total paid to the project can never exceed the initial grant.
8.3 Programme closure
Once projects have been satisfactorily closed, the programme itself can move towards formal
closure. This is the subject of an upcoming handbook from INTERACT Point Toolbox and we
cover only the main points here. The programme closure procedure represents a declaration
to the Commission that all spending declared has been confirmed correct, that all
irregularities have been satisfactorily resolved and that it is safe for the Commission to make
the final payment (i.e. that it is reasonable to assume there will be no need to later recover
part of these funds). It can be a difficult time for programmes as it requires that all project
issues have been resolved and there are normally a few problematic projects whose closure
is delayed.
A recent and considerable extension to the deadline for submitting closure documents to the
Commission (the new deadline is 31 March 2010 15 months after programme end
43
) should
ease some of the closure pressure. It will be important, however, that programmes do not
become too relaxed about closure and still try to do as much as possible as soon as possible:
If the process takes too long key stakeholders will lose interest or move on and deadlines will
slip. Furthermore in principle, there is no funding available for closure activities after 31
December 2008 and this tends to mean that they are given a low priority after this date.
However programmes, which will continue to operate in the new period 2007 2013, may
use part of their new TA budget to cover costs strictly related to the closure of the current
programme. These include e.g. printing of the final report, staff costs etc. Nevertheless, the
advice must be to only make use of the extra time and new TA funds if absolutely required
and otherwise close quickly so final payments can be made to projects.
Three documents are required for programme closure: An audited statement of accounts
and application for the final payment, a final report and a declaration on winding-up
the assistance, which gives an audit opinion on the programme. We focus here on
producing the winding up declaration - or third level control as it is sometimes known.
The last 5% of programme funds is retained until after these documents have been submitted
to the Commission and the Commissions auditors have assessed them as satisfactory. The
5% is calculated on the basis of total programme funds rather than funds claimed. If the
programme has lost money to de-commitment, this will be deducted from the programme
budget before calculating the 5%. This means of course that the last 5% of project payments
will also have to be delayed until the last funds are received from the Commission (project
final claims are generally paid on a first come first served basis until there are no funds left in
the programme account). If there is any problem with the closure statement this part of the
process can take a long time and some projects may be waiting for final payments for several
years. It is imperative that programme closure is completed as swiftly as possible and in a
way which enables quick Commission approval. The key actions which can be taken to assist
this are to have accurate financial management and control systems and records during the
lifetime of the programme.


43
General Regulation (1083/2006), 105.3. It is important to note that this part of the new regulation
applies to the current period 2000-2006.
Financial Management Handbook

133

Figure: Project closing phase
P R O J E C T C L O S I N G P H A S E

Stage 1
Accumulation

of project
records

Stage 2 Stage 3

Stage 2
Preparation of Final report

Report on activities

Report of finances

Stage 3
Submission of
the Final Report

Stage 1
Potential problems encountered-
Unresolved FLC problems
- Unresolved SLC problems

How to facilitate Stage 2?

- Start early so there is enough time
to resolve control problems
- Use retention of final project
payment to encourage early delivery
of project materials
Potential problems encountered -

Missing documents =
incomplete audit trail
Eligibility after closure:
- Staff costs
- Audit of the final report
Financial Management Handbook

134

1 January 2009
31 March 2010
2008

TA expenditure still eligible.
Advisable to get as much work as
possible done in this period.
Urgent need to close projects in
time to get final audited
statements of expenditure.
Provisional statement of total eligible
expenditure as soon as possible.
Completion of second level control work. Draw up final
statement of expenditure for programme including all
adjustments made as a result of control. Check against
final approved financial tables and programme accounting
records.
Costs incurred between 31.12.2008 31.03.2010 and
purely related to the programme closure can be covered by
TA of the new programmes. MA must be consulted about
it.

Completion of final report.
Preparation for Monitoring
Committee meeting.
MC meeting approves / comments on final
report
Revision of final report
All programme actions
completed. Completion of
winding up declaration.
Last chance to respond to
findings of winding up
declaration / take corrective
action.
Normal deadline for submission
Indicative timeline for programme closure
Financial Management Handbook

135
8.4 Third Level Control
The winding up declaration is sometimes prepared by the second level controllers of the
Financial Control Group and sometimes by a separate body (and therefore called Third Level
Control). This control work again checks the quality of earlier checks at both project and
programme level and has to ensure that any recommendations made have been followed up.
More specifically, preparation of the winding up declaration focuses on:
The independence of the bodies carrying out second level control work
The sampling method used for second level control checks
How the final statement was drawn up
The nature and quality of the audit work carried out
The implementation of audit recommendations and correction of errors (meaning errors
are reported to relevant bodies, amounts concerned are deducted from the statement of
expenditure, recovery procedures are launched when necessary and systemic errors are
corrected).
Two negative results are possible. On the one hand, the winding up body may state that it
has no opinion. This happens for example when second level control checks have been
inadequate or serious management failures have not been addressed. The winding up body
may also deliver a qualified opinion if the second level control sampling technique is weak or
there are no formal procedures for identifying and treating systemic problems. Both of these
decisions will result in delayed final payment and a request to the winding up body to quantify
the extent of the problems (how much money to deduct).
The winding up declaration will also address the frequency of irregularities and errors found
during the second level control checks and any other audits that have been carried out. This
is used to assess the overall reliability of management and control systems though errors are
also weighted according to the impact they can be expected to have (for example, whether
they are formal or substantive, will have a financial impact etc.) In general, however, a 2%
rate of errors or irregularities is the limit. If the rate is higher this will lead to a qualified opinion
unless the MA and PA can take effective corrective action. It is therefore important to start the
winding up process as soon as possible in 2009 so that programme bodies have a chance to
act on any negative findings.
Programme closure also rests ultimately on the quality of first level control work carried out
and the soundness of the systems and procedures described in the original description of
programme management systems and procedures. These systems are perhaps the most
important element if they have been used properly, as they should ensure that the
programme avoids systemic errors (broadly speaking, errors that will probably be repeated
every time the procedure involved is used). Avoiding this type of error is particularly important
as they can lead to cuts in funding for all measures / priorities where these systems /
procedures are in place if corrective action cannot be taken.
On past experience it may take two or three years to complete programme closure. After
2008, however, funding for this process is ineligible and programme bodies may no longer be
in place unless the programme will be prolonged in 2007 2013 and uses part of its new TA
budget to cover closure related costs. Member States need to agree who has responsibility
for holding programme records and dealing with any associated issues which might arise and
how they are to be paid for this.
In most current programmes the actual amount of the final payment can be calculated
relatively easily as the balance of funds to be paid from the final statement of expenditure
after deductions arising from control work. In programmes using different ERDF rates or
including private co-financing in the financial tables, the situation can be more complex. This
situation will be more common in future if programmes make use of the chance to vary ERDF
rates between priorities. In these situations the 2% flexibility rule may be used. Its basic
purpose is to balance out the ERDF rate if the final amounts claimed do not correspond
exactly with the ERDF / co-financing split in the programme financial tables. Anyone wanting
to know more should see the Commission Guidelines on closure.
Financial Management Handbook

136

Annex 1 Regulatory Framework
Current programme period 2000 2006
The INTERACT website http://www.interact-eu.net/604900/443793/0/0
provides downloadable list of EU regulations for Structural Funds and communications of
relevance to INTERREG.
INTERREG III - Communication from the Commission of 2 September 2004 laying down
guidelines for a Community initiative concerning trans-European cooperation intended to
encourage harmonious and balanced development of the European territory (2004/C 226/02)
Communication from the Commission of 2 September 2004
INTERREG III - Communication from the Commission amending the guidelines for
INTERREG III (2001/C 239/03)
Communication from the Commission amending the guidelines for INTERREG III
INTERREG III - Communication from the Commission to the Member States of 28 April 2000
laying down the guidelines for a Community Initiative concerning trans-European territory
INTERREG III
INTERREG - Communication from the Commission of 1 July 2003 COM(2003) 393 final -
Paving the way for a New Neighbourhood Instrument
INTERREG - Communication from the Commission to the Member States of 7 May 2001
'Inter-regional Cooperation' Strand C of the INTERREG III Community Initiative Commission
communication C(2001) 1188 final
Regulation - Commission Regulation (EC) No 448/2004 of 10 March 2004 amending
Regulation (EC) No 1685/2000 as regards to eligibility of expenditure of operations co-
financed by the Structural Funds and withdrawing Regulation (EC) No 1145/2003
Regulation - Commission Regulation (EC) No 1145/2003 of 27 June 2003 amending
Regulation (EC) No 1685/2000 as regards the rules of eligibility for co-financing by the
Structural Funds
Regulation - Commission Regulation (EC) No 2355/2002 of 27 December 2002 amending
Commission Regulation (EC) No 438/2001
Regulation - Commission Regulation (EC) No 438/2001 of 2 March 2001 laying down
detailed rules for the implementation of Council Regulation (EC) No 1260/1999
Regulation - Council Regulation (EC) No 448/2001 of 2 March 2001 laying down detailed
rules for the implementation of Council Regulation (EC) No 1260/1999
Regulation - Commission Regulation (EC) No 1685/2000 of 28 July 2000 laying down
detailed rules for the implementation of Council Regulation (EC) No 1260/1999
Regulation - Commission Regulation (EC) No 1159/2000 of 30 May 2000 on information and
publicity measures (...) concerning assistance from the Structural Funds
Regulation - Commission Regulation (EC) No 643/2000 of 28 March 2000 on arrangements
for using the euro for the purpose of the budgetary management of the Structural Funds
Regulation - Regulation (EC) No 1783/1999 of the European Parliament and of the Council of
12 July 1999 on the European Regional Development Fund
Regulation - Regulation (EC) No 1784/1999 of the European Parliament and the Council of
12 July 1999 on the European Social Fund
Regulation - Council Regulation (EC) No 1260/1999 of 21 June 1999 laying down general
provisions on Structural Funds
Financial Management Handbook

137

Regulation - Commission Regulation (EC) No 1681/94 of 11 July 1994 concerning
irregularities and the recovery of sums wrongly paid in connection with the financing of the
structural policies and the organization of an information system in this field
New programme period 2007 2013
Regulation Council Regulation (EC) No 1083/2006 laying down general provisions on the
European Regional Development Fund, the European Social Fund and the Cohesion Fund
and replacing Regulation (EC) No 1260/1999
Regulation Regulation (EC) No 1080/2006 of the European Parliament and the Council on
the European Regional Development Fund and replacing Regulation (EC) No 1783/1999
Regulation Commission Regulation (EC) No 1828/2006 setting out rules for the
implementation of Council regulation (EC) No 1083/2006 and 1080/2006
Financial Management Handbook

138

Annex 2 First level control in INTERREG 2000-2006
This annex covers some important features of the current system, which will however
disappear in the new period. Anyone wanting information on the content of first level control
checks should refer to the section handbook on first level control in the new period as there
are no substantial changes.
Who is checked?
This is an important question. In the current period FLC has been carried out at the final
beneficiary level: Anyone who is a final beneficiary gets controlled and likewise, if you are not
a final beneficiary, there is no direct control - invoices are instead sent to the final beneficiary
for control. The final beneficiary has been defined as the Lead Partner of a project meaning
that financial control of all partners should be carried out by the Lead Partners controller.
When this interpretation is used in INTERREG projects, it means that the Lead Partners
controller will have to control expenditure from other countries where other rules and laws are
in place and that he/she may also be unable to check supporting documents. Some
programmes have made this work by harmonising the rules on both sides of the border. A
shared language seems to be a minimum requirement for this kind of intensive cooperation.
Often, however, controllers have refused to certify expenditure incurred in other countries.
As a result, a number of different interpretations of the Lead Partner principle have developed
and each has different financial control implications. Different interpretations are appropriate
depending on the circumstances and in many programmes several different models are
possible with each partnership left to decide which will work best for them.
Some projects have operated under a central cash system. In these projects the Lead
Partner receives the majority of the grant and pays partner invoices in effect serving as the
bank for the rest of the project. The other partners generally have a small grant of their own
to pay for e.g. travel costs and meetings. The Lead Partner is therefore responsible for First
Level Control of the whole project but can monitor all spending carefully as it occurs. This
system is particularly useful for projects with large numbers of small and/or inexperienced
partners as it removes much of the administrative burden from them. It is also a good way of
reducing audit costs.
Another way of including small partners has been to make use of the sub-partner concept.
Sub-partners are not part of the formal partnership and do not therefore need to appear in the
application or contract - although the programme should be informed of all sub-partner
participation. Sub-partners are organisations that play a minor but integrated role in
implementation of the project. As such their costs are generally limited to small amounts of
staff time. Evidence for this time can be collected and controlled at the partner level and
expenditure included in the partners statements. If this is done, it is essential that the audit
trail is secured and arrangements are made for preserving documentation after the end of the
project. Sub-partners also need to fulfil the criteria laid out in the Interpretative note from the
Commission Services on Council regulation 1260/1999 Article 32 (1). These criteria ensure
that the Lead Partner retains ultimate responsibility, that there is a documented agreement of
the full partnership on the participation of any sub-partners and that standard financial
management requirements apply equally to spending incurred by sub-partners.
Financial Management Handbook

139

Control structure of Lead partner project with sub-partners (2000-2006)

In this connection, it is also worth noting the role of other final recipients. These are not part
of the partnership at all and make no contribution in terms of hours etc they only receive
funding. An example would be businesses receiving small grants under a scheme
administered by a partner. It is important to recognise that these final recipients are still
covered by financial control requirements and that steps must be taken to ensure the
correctness of their expenditure and document the audit trail. Responsibility for ensuring that
this is done will lie with the partner making the grant.
INTERREG also allows projects to use the Extended Final Beneficiary Principle according to
which all of the partners in a project can become final beneficiaries and are therefore
controlled independently. This means that each partner can be controlled by a controller from
its own country and this is the system in place in most programmes. The Lead Partner
controller then signs a declaration that they have received properly certified statements of
expenditure from all partners: They do not have to assess the quality of the control work done
as this remains the responsibility of the first level control body in each country.
In order for this system to work, programme management bodies have to agree on how the
Lead Partners responsibilities will be interpreted in terms of First Level Control. The
INTERREG Guidelines state that the Lead Partner will bear financial and legal
responsibility to the Managing Authority. (INTERREG Guidelines, Point 31) Many
programmes have interpreted this as meaning that the Lead Partner has financial liability for
all expenditure even if another partner incurred and the expenditure and had it certified.
Although most project partnership agreements transfer the responsibility for incorrect
expenditure to the partner concerned, the financial liability of the Lead Partner has been an
unreasonable demand in the current period and this will be changed.
Lead Partner
Sub-Partner

Sub-Partner

Sub-Partner

Project Partner Project Partner Project Partner
Financial Management Handbook

140

Defining the final beneficiary for first level control (2000-2006)

A complex partnership could in theory contain all of the elements outlined above - as in the
example below. Partners 1, 2 and 3 are standard partners and take care of their own first
level control under the extended final beneficiary principle. Partners 4 and 5 on the other
hand are part of a central cash system and have most of their budget administered by the
Lead Partner. Partner 1 is responsible for a small group of NGOs and administers them as
sub-partners. Partner 2 makes grants to small businesses and is responsible for collecting
and holding evidence for the audit trail of this expenditure. Using all of these features in one
project would be extremely unusual and the complexity alone would make this a high-risk
project. This shows the flexibility of the Lead Partner principle and that there is no single
right structure for Lead Partner projects.
Project Partner 1 Project Partner 2 Project Partner 3
All partners are final
beneficiaries. FLC
carried out in partner
MS
Lead Partner
Project Partner 1 Project Partner 2 Project Partner 3
LP as only
final
beneficiary.
Whole
projects FLC
done here Lead Partner
2. Extended Final Beneficiary System
Removes most FLC barriers
1. Central Cash System
Generally more difficult to work with
Financial Management Handbook

141

Who does the First Level Control?
First Level Control has been carried out by competent bodies in each Member State with the
Member States free to define the most appropriate bodies in their own country. There have
been two main systems though several programmes also operate a combination of the two.
Decentralised control. In decentralised systems invoices are controlled at the premises
of the final beneficiary by a controller appointed by the project. The Member State
concerned defines the competent bodies that can carry out this control work. Examples
include private audit firms, national public control bodies and controllers from the projects
organisation as long as they are completely independent from the projects management
(e.g. from the central finance or chief executives part of the organisation). This last option
is a cheap and easy solution in the short-term but can cause longer-term problems, as
the final control of the project must be carried out by an independent external controller.
Normally these external controllers are not identified by the Member States until the first
projects are ready to close. After they have been appointed, they have in some cases
refused to accept the control work carried out in internal controls. This again highlights
the need to identify all control bodies at the start of the programme and ensure that they
accept the rest of the control structure.
The main concern about the decentralised system is the quality of checks being carried
out. Each controller may only work with one or a few projects and it is not easy for them
to ensure consistency of approach to e.g. eligibility questions and to build up knowledge
of the particular demands of INTERREG project management. To combat this,
programme bodies are increasingly targeting these controllers with information and
guidelines on audit and checks. Many programmes also run training events for project
finance managers and/ or controllers immediately following project approval to ensure
that the necessary financial management and control systems are put in place from day
one.
First level control

Other project implementers


Project Partner 1 Project Partner 2 Project Partner 3
Lead Partner
1. Other aspects of
partnerships
Sub-partners 1,2 + 3 Final recipients
Project partner 4 + 5
Financial Management Handbook

142

Centralised control. Some countries have centralised systems where all expenditure
from all project partners is controlled by a regional or national level body. These
centralised systems allow those who carry out the controls to build up specialist
knowledge on INTERREG operations and ensure consistent and generally high
standards. On the other hand, almost all such organisations are under-staffed and in
some cases there are very serious delays in certification. In these systems there is
generally a separate control body for partners from each country but in a small number of
cases a centralised body will also control expenditure from other participating Member
States.
Programme controls. Controls tend to focus on financial aspects and checking invoices
but the regulations make clear that checking progress on activities is equally important.
For this reason, MAs and JTSs also normally play a role in first level control through the
report checking they do. The main task here is to check the activities reported against the
approved application and also try to identify ineligible activities (such as the purchase of
equipment not mentioned in the application). These checks can also lead to cuts in the
amount claimed and most programmes will not forward project claims to the PA until
these checks have been made. They are therefore be considered as an integral part of
the first level control process.
Co-financing controls. Some countries and regions also carry out separate checks of
the co-financed part of partner budgets. As noted previously, these checks can only be
extra and cannot replace normal first level control. (i.e. programme control must anyway
include both ERDF and co-financing). Project partners should anyway be following their
national rules. These additional checks seem redundant and should be stopped if at all
possible.
On the spot checks
Article 4 of Commission Regulation 438/2001 requires that First Level Control procedures
shall require the recording of verification of individual operations on the spot. There
have been considerable differences in interpretation of this regulation and whether it means
checks should be carried out where original invoices and other documentation are stored or
whether controllers should actually visits the sites where the project claims to have carried
out its activities.
Many programmes do now visit every project at least once in its lifetime but the status of
these checks varies. Sometimes they are informal and are offered as an advisory service. In
other cases they are related to other First Level Control activities and findings are fed into
second level control decisions. Every programme has to make its own decision on the nature
of these checks and ensure sufficient separation of management and control functions if on
the spot visits are not carried out by first level controllers. A CDCR paper
44
on good practice
in Article 4 checks recommends that a sample of projects should be visited and that it should
be possible to visit any project if necessary. This solution reduces the administrative burden
on the programme, which can otherwise become excessive if there are too many projects.
The extent of the visit depends on the nature of the project. Often visiting the office of the
Lead Partner is sufficient. With major investment projects, visits to see the resulting outputs
are essential: There are extreme cases of infrastructure that has been reported on and
invoiced but never built. The decision on whether a site visit is required will depend on
whether the reported outputs can be checked in any other way. In this connection it is worth
noting the advice of the Commission that the only projects which should be approved are
those which present a clear work programme with, for each activity, an identifiable product
which makes it possible to check afterwards whether or not the event occurred (e.g.
conference papers, a web site, implementation document, a report on activities undertaken.
When carried out, on the spot checks have proved to be useful. They have often revealed
weaknesses with project management and control systems that have otherwise gone


44
CDRR 06-0002-00 Draft working document concerning good practice in relation to management verifications
to be carried out by Member States on projects co-financed by the Structural Funds and the Cohesion Fund
(21/12/2005)
Financial Management Handbook

143

unnoticed. To make on the spot visits as effective as possible, programmes should send
projects a checklist informing them in advance about what information they should have
available. If projects cannot then provide key documents, this will be a clear sign of where
efforts should be focused. Identifying these problems at an early stage means that they can
be tackled before becoming a problem during later controls.

You might also like