Professional Documents
Culture Documents
Argosy University
Abstract
Project Management techniques are examined outlining preliminary considerations used to bid a
project. Linier regression is one of the possibilities discussed to evaluate labor, material,
equipment, and risk escalation calculation in the preparation of a construction bid.
Construction Cost Variables 3
Problem Statement
Your company builds roads, bridges, schools, and other multi-million dollar public construction
projects. Competitive bids are invited for the contracts to undertake these projects. For each
project, there are three costs involved:
Find out whether the cost estimates that are made before the bidding process are accurate
predictors of the actual costs of completed projects
Assumptions
Based on the problem statement it is assumed: the project is large in scope and at least
one year in duration. The economic, political environment, and infrastructure is stable and will
not produce variations outside the normal escalation range for material, delays, and labor costs.
Access to past project data similar to the project in question is available and has no serious flaws
in documentation of past costs and problems encountered. The majority of the material, labor and
equipment will be procured locally, or is owned by the company. Equipment used in the
construction of the project will be in reasonable working order or suitable back-up equipment is
readily available.
Examination of past project data will provide an order of magnitude for the basis of the
initial estimate. The best estimate can only be produced by constructing a work breakdown
schedule of to the task level necessary to evaluate the hours required to complete each task, the
materials used, and the equipment necessary for that step. In this manner, a Project Manager will
be able to evaluate the ability to calculate the best distribution of resources, labor, material,
Construction Cost Variables 4
equipment. In other words the project will not be overmanned, have too much material on site, or
suffer delays from equipment that is over utilized by the need to be at several task sites at one
time. Load leveling of manning, equipment requirements and evaluation of the materials needed
Assessment of Risk
The next step will be to consider the risks associated with labor or material interruptions,
of risk, transfer of risk, or acceptance of Risk. There are types of risk that can not be predicted
and have a very low probability of occurrence- unforeseen. Risk mitigation is accomplished by
the identification of the most likely of risks and taking steps to reduce the impact to the project.-
risk planning. This could include having extra equipment available, sub contracting portions of
the project. Risk transfer could be the purchase of insurance for fire flooding or theft of building
materials. And finally there is risk acceptance, things like storms or earthquakes that have an
increased possibility but still have a low probability of happening. Recover =y plans should still
be considered for these events and addressed in the bid contract- Force Majeure.
First Estimate
Using the labor, material, and equipment costs linier regression would be a method to
evaluate escalation costs of labor, material , and replacement of equipment during the length of
the project. Additional considerations would have to be given to the possibility of failure of one
or more of the areas, linier regression analysis, to create a parametric to establish an appropriate
contingency cost buffer. This completed the same steps would have to be taken with the
weighted average of the risks associated with the project. An initial bid can be constructed using
Construction Cost Variables 5
the appropriate contract language. The contract would offer an initial price subject to conditions
that may be discovered by inspecting the site. These conditions may not be apparent to
preliminary inspection such as subterranean ground conditions, the proximity of water to the
surface, or other environmental conditions that would affect the cost of the project and would
Actual Costs
Actual costs are the labor paid, the material used, and the equipment rental fees, or
equipment repairs and depreciation. Other indirect costs could be the loss of future projects if the
stakeholders are not satisfied and the project is not closed-out properly and met the full scope of
the contract-completed properly. This could result in rework or litigation that- very real costs.
Summary
Best estimate is based on ideal conditions but the contract should allow for contingencies
that may not be discovered, even with due diligence, during the bidding process. Appropriate
adjustments to the bid must be made to allow for escalation of labor, materials, equipment, risk
Reference