You are on page 1of 2

Area of the Project: 1755 Sft

Item Description Quantity Unit


No.
SUPER STRUCTURE : MAIN FRAME
1 Beam With Pre Engineered I section 1,300 Kg
2 Truss 2,300 Kg
3 Plate & Galvanized Nut Bolts and Washer for Joint 40 Kg
4 20 mm dia high strength cables 6 M
5 Paint (Red oxide Premier) 1,755 Sft
6 Alucobond framing 2,875 Kg
Sub-Total cost for Superstructure (Main Frame) = Tk.
SHEETING & ACCESSORIES:
1 Alucobond 3,860 Sft.
2 FASTENERS : a) -12-14 x 65 HGS (For Roofing) 150 Nos.
Sub-Total cost for Roof Sheeting & Accessories = Tk.
Unit Rate (Tk./Sft)
***
Transportation charge from our Factory to the Project Site will be borne by the Buyer at actual
(approx).
L. S.
***
Erection of Pre-engineered welded steel Column, Rafter, Purlin, Girt etc. and Fitting & fixing
charge of Roof & Wall sheeting in/c Capping, Flashing, Gutter, Down Pipe etc. (basis on floor
area) (Tk)
1,755 Sft.
***
Retrofitting of existing Structure (Welding & hole Creation at Site) (Including welding rod and
all necessary item to creat hole)
878 Sft.
Unit Rate (Tk./Sft)
Grand Total Cost TK.
Date:26/04/2013
Unit Price Amount Rate
(in Tk.) (in Tk.) (in Tk./sft)
110.00 143,000.00
110.00 253,000.00
230.00 9,200.00
1,200.00 7,200.00
60.00 105,300.00
110.00 316,269.25
Sub-Total cost for Superstructure (Main Frame) = Tk. 833,970.00 475.20
700.00 2,702,000.00
20.00 3,000.00
Sub-Total cost for Roof Sheeting & Accessories = Tk. 2,705,000.00 1,541.31
Unit Rate (Tk./Sft) 3,538,970.00 2,016.51
30,000.00
3975.896
3,568,970.00 2,033.60
12.00 21,060.00
8.00 7,020.00
3,597,050.00 2,049.60
Unit Rate (Tk./Sft)
Grand Total Cost TK.

You might also like