AREA(in sqm) 20 Thickness of Cement Mortar bed (in mm) 12 Tiler Productivity (in sqm) 5 Size of Tiles Length (in cm) 15 Breadth (in cm) 15 Time of completion (in days) 2 Parts of Cement (in mortar) 1 Parts of Sand (in mortar) 2 Mortar wastage (in Percentage) 15 Tiles wastage (in Percentage) 5 MATERIALS REQUIRED CEMENT (inclusive of 15% wastage)(in cum) 0.092 SAND (inclusive of 15% wastage) (in cum) 0.184 No. of Tiles (inclusive of 5% wastage) 934 Dado Tiling Item Materials Unit Quantitiy Rate White Glazed Tiles Nos. 934 8 Cement Bags 2.6496 340 Sand cum 0.184 2650 Tile Fixing Adhesive kgs 13.248 35 Labours Tiler labour(s)/day 2 400 Helper labour(s)/day 2 350 Baeldar labour(s)/day 2 300 Sundries Pecentage 10 Water Percentage 1 Contrator's Profit and Overhead Percentage 15 Grand Total For 20 sqm Rupees Rate for 1 sqm Rupees Rate as per DSR Rupees Amount 7472 900 487 463 1600 1400 1200 1352 148 2253 17276 863.8 832