CubeSat Acceptance Checklist

Revision: 12
Revision Date: August 1, 2009
Author: Riki Munakata

This document is intended to be used concurrently with the CubeSat
Integration Procedure (CIP) and should be used by developers before
and after each testing phase to verify the CubeSat dimensions did
not change.
List Item Actual Required

Mass
g 4000

Remove Before Flight
Protrudes < 6.5 mm

Spring Plungers
Option (A/B)
Functional (Y/N)

Rails
Anodized (Y/N)

Deployment Switches
Option (A/B)
Functional (Y/N)



Width [x-y], Top

List Item Actual Required
Side 1 mm 1 . 0 0 . 100

Height [z]
Side 2 mm 1 . 0 0 . 100

Rail 1 mm 3 . 0 5 . 340
Side 3 mm 1 . 0 0 . 100

Rail 2 mm 3 . 0 5 . 340
Side 4 mm 1 . 0 0 . 100

Rail 3 mm 3 . 0 5 . 340
Width [x-y], Middle

Rail 4 mm 3 . 0 5 . 340
Side 1 mm 1 . 0 0 . 100

Diagonal [x-y]
Side 2 mm 1 . 0 0 . 100

Top 1&3
mm
0
5 . 1
2 . 141
+


Side 3 mm 1 . 0 0 . 100

Top 2&4
mm
0
5 . 1
2 . 141
+


Side 4 mm 1 . 0 0 . 100

Bottom 1&3
mm
0
5 . 1
2 . 141
+


Width [x-y], Bottom

Bottom 2&4
mm
0
5 . 1
2 . 141
+


Side 1 mm 1 . 0 0 . 100

Protrusions


Side 2 mm 1 . 0 0 . 100

Side 1

mm 0 . 0 5 . 6 +
Side 3 mm 1 . 0 0 . 100

Side 2

mm 0 . 0 5 . 6 +
Side 4 mm 1 . 0 0 . 100

Side 3

mm 0 . 0 5 . 6 +



Side 4

mm 0 . 0 5 . 6 +


Side 5

mm 0 . 0 5 . 6 +


Side 6

mm 0 . 0 5 . 6 +

Authorized By:

IT #1: ________________

IT #2: ________________
Testing Info:

Date: _____________

Passed: Y / N
+Z
+Y
+X