Assignment part 1

Q- 2 Use the following information to


1.Draw Gantt Chart
2.Draw PERT Network
3.Identify Critical Activities

Activity Immediate Predecessor Estimated Time
A - 9
B - 8
C - 10
D B 3
E B 4
F A 4
G A 3
H G 5
I G 4
J C, E, F, H 8
Assignment part 2
1.Draw Gantt Chart
2.Draw PERT Network
3.Identify Critical Activities
Q-1: Calculate the Estimated Time from the given table and then perform the above
mentioned activities
Estimated Time = (optimistic + 4X most likely + pessimistic) / 6

Activity
Immediate
Predecessor
Optimistic Time
(Hrs)
Most Likely Time
(Hrs)
Pessimistic Time
(Hrs)
A - 4 6 8
B - 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B, C 3 4 5
G B, C 1 1.5 5
H E, F 5 6 7
I E, F 2 5 8
J D, H 2.5 2.75 4.5
K G, I 3 5 7