The document provides information on activities, their predecessors, and estimated times to draw a Gantt chart, PERT network, and identify critical activities for two assignments. For the first assignment, activity information and estimated times are given. For the second assignment, a formula is provided to calculate estimated times from optimistic, most likely, and pessimistic times also given for each activity.
The document provides information on activities, their predecessors, and estimated times to draw a Gantt chart, PERT network, and identify critical activities for two assignments. For the first assignment, activity information and estimated times are given. For the second assignment, a formula is provided to calculate estimated times from optimistic, most likely, and pessimistic times also given for each activity.
The document provides information on activities, their predecessors, and estimated times to draw a Gantt chart, PERT network, and identify critical activities for two assignments. For the first assignment, activity information and estimated times are given. For the second assignment, a formula is provided to calculate estimated times from optimistic, most likely, and pessimistic times also given for each activity.
Activity Immediate Predecessor Estimated Time A - 9 B - 8 C - 10 D B 3 E B 4 F A 4 G A 3 H G 5 I G 4 J C, E, F, H 8 Assignment part 2 1.Draw Gantt Chart 2.Draw PERT Network 3.Identify Critical Activities Q-1: Calculate the Estimated Time from the given table and then perform the above mentioned activities Estimated Time = (optimistic + 4X most likely + pessimistic) / 6
Activity Immediate Predecessor Optimistic Time (Hrs) Most Likely Time (Hrs) Pessimistic Time (Hrs) A - 4 6 8 B - 1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B, C 3 4 5 G B, C 1 1.5 5 H E, F 5 6 7 I E, F 2 5 8 J D, H 2.5 2.75 4.5 K G, I 3 5 7