Memo

Ref.
To

F.PAILLE BARRERE,A.BAUDORRE,J.BRUNEVAL

Department

OPEX

Copy

P.LE GULUDEC,F.VOLLE,F.LANGLOIS

From

M. LOUBET

Department

OPEX

Date
Subject

10/07/006
D110WI status / handover dossier

Visit performed on site on 10th July 2006


Following points to be attended :
D110 WI South Cluster

Wellhead cave to be cleaned


Scaffolding to be removed from the cave
Cellar top box to be redo
Wing & Swab valve handles : Pin are missing.
3/8 plug missing on DBB valve on instrument flange(u/s wing valve)
Annulus bleed line :Guick coupling is missing
2 choke on depressurising line to be removed
Painting as per specifications to be finalized
Update wellhead Xmas tree Schematic(Annex 3) in the file.
o One kerotest + gauge missing on 20
o Gauge to be cancelled on kerotest tree cap(to be replaced by plug)
o Gauge + kerotest on Y solid block blind to be removed

Regards
Prod.Spdt
M.LOUBET