Calcular as novas impedncias de cada equipamento, bem como de cada uma das
linhas, da rede de distribuio de energia, adotando a potncia de base do
Gerador de 75 MVA e tenso de base de 18 KV? G = (frmula do Zpu2) G = 0,158 * (13,8/18)^2 * (75/45) G = j0,1547 PU T1 = 0,122 * (13,8/18)^2 * (75/45) T1 = j0,0894 PU REGRA DE 13,2 69 X= 94,09
3: 18 X Kv
T2 = 0,135 * (69/94,09)^2 * (75/10)
T2 = j0,5445 PU T3 = 0,128 * (69/94,09)^2 * (75/75) T3 = j0,6883 PU T4 = 0,094 * (69/94,09)^2 * (75/35) T4 = j1,083 PU ZLT1 = 4,16+J2,76(Ohm) = 5[33,56 GRAUS ZB = (94,09)^2/75 = 118,03 ZLT1(PU) = 5/118,03 = j0,0423 PU ZLD1 = 2,56+j0,75 - 2,667[16,32 graus 69 - 94,09 13,2 - X X= 18 Kv ZB= (188)^2/75 = 4,32 OHM ZLD1PU = 2,667/4,32 = j0,617 PU L2PU = 13,7*(13,8/18)^2*(75/0,3) = j2013,13 PU M1 = 2,89*(13,8/18)^2*(75/3,5) = j36,4 PU ZLST1 = 3,36+j1,29 OHM = 3,6[21 GRAUS 69 - 94,09 3,45 - X X = 47,045 Kv ZB = (47,0458)^2/75 = 29,5 ZLT1(PU) = 3,6/29,5 = j0,122 PU M2 = 4,12*(32/47,045)^2*(75/4,35) = j33,63 PU
ZLST2 = 4,57+j2,39 OHM = 5,157[27,6 GRAUS
69 - 94,09 44 - X X = 60 Kv ZB = (60)^2/75 = 48 ZLT1(PU) = 5,157/48 = j0,107 PU M2 = 3,75*(42/60)^2*(75/2,7) = j51,04 PU