Olympic and Paralyrpic Games: Progress Report Ju ne 2008 796. 480 684 GRE Conslruclion slrort dote October 2006 October 2006 September 2009 September 2008 November 2008 Enobling Works {site preporofion} Power Lines Under Grounding {switchover only} Structures, Bridges ond Highwoys Utilities Moin Stodium Aquotics Centre Velopork Hondboll,/lndoor Sports Areno Bosketboll lnternotionol Broodcost Cenhe/ Moin Press Centre Olympic Villoge Eton Monor {troining focilities ond Porolympic eventsi Broxbourne {white woter conoeing} Eton Dorney (rowing) Weymoufi ond Portlond {sailing} i ,.,. .-, ,. r i, .' i 0 0 -2 4 -2 -l -2 -f:::;|::,:{: l: ....i -l-r. 0 2 {* Y,: r b:' t:i ':fi j I t .&a s, .t. -it ii & k- # # Julr {08 July 2008 \ April 2008 April 2008 Jcnuory 2008 Jonuory 2008 July 2008 Moy 2008 -21 September 2008 September 2008 December 201 I December ?01 I December 20,l I August 201 I Morch 200? August 2009 July 20O9 Moy 2009 June 2008 Morch 2OlO August 20O8 Morch 2OO9 Mqrch 20o9 June 2009 November ?009 Morch 2OO9 Moy 2008 Jonuory 20 I 0 Construction end dote Februcry 201 I Completion dote for conslruction snd initiol overloy for tesl evenk June 201 I Construciion end dqte April 201 1 Completion dote for consiruction ond initiol overloy for test evenis July 2011 April 20t I April 201I April20l l June 201 I December 2Ol I June 20 I 0 'April20l0 Consiruclion end dote April20l 1 2 Completion dote for construction ond initiql overlqy for leif events June 201 I 0 Construction end dote August 201 1 4 Completion dote for construction ond initiol overloy for test events August 201 I I Februcry 20,l I -2 Morch 20] I -l April20l I 0 July 201 I I December 20i I O October 2OlO July 2O09 Februory 20 I 2 April 201 I -10 Moy 2009 Jonuory 2009 -9 -2 Moy2008 Jonuory 2008 4 i ;1:;11 ;r;i i..:tit:i i::ti::a:.; :;tir::l lit: lt:f:t..i::.i Februory 2009 Jonuory 2009 : l_:1.:l ? : ::r: ; :: :r :, t :j;;:t:ii :::: *l Comments Elements of enobiing works ore criticol to ihe Auhorily's delivery progromme. Good progress hos been mode ond where deloys hove occurred this hos notdeloyed the stortof construction octivities. See porogrophs 3.5 and Figure 8. The pLUp project is criticol io ihe delivery of the Olympic Pork os itwill remove overlond power lines from the_site ond ollow the switchover to unddr giound po,"", cobles. ln June 2AA7 the Authority ochieved o crificol. projeci miiesione, completion of the lwo moin 6km power line tunnels 9n'iime ond to budget. This wos o high risk octivity given the need to bore tunnels through o complex site ond hod the potentiol to seriousl;l deioy the site preporotions. The ,Auihority expects lo switch power to ihe underground cobles by November 2008. Ebmer{ts of the Skuctures. Bridges ond Highwoys proiect ore criticol to the Authority's delivery progrqmme. Progress is on trock, with the first lour coniroct pockoges successfully procured ond work underwoy {the four mosi criticol elements of the proiect}. The Utilities proiect is criticol io the Authority's delivery progromme. The Authority hos re-scheduled utilities works to meetthe plonned needs of venues on the pork, in porticulcr the utilit'y requiremenls for test evenls. Construction of the Moin Stodium ond its reodiness for iest events is criticol to ihe Auihority's delivery progromme. At the iime of the November 2002 Progromme Boseline Report, which wos before controci signoiure, construciion ol lhe Moin Stodium wcs scheduled to be completed in Februory 20,l 1, to be followed by LOCOG overloy works for tesi events which were to be completed by June 201 I . 1o dole good progress hos been roi" on site prepcroiion, which hos oilowed construction io stqrt in Moy 2008, two months earlier fhon plonned^1 i, o 1.".rii of controct negotiotions the Authority hos ogreed o longer conslruction period lhon cnticipoted [35 months ro$er thon 32]. The Authoriry hos. however, drik "orly occess dotei {or LOCOG overloy works into the controct so overloy con be cqrried oui in porcllel with ihe construciion work. The forecast dote for reodiness for test events remoins otJune 201 l. Construciion of the Aquotics Cenire ond its reodiness for lest events is criiicol to the Authority's delivery progronrme. A'r:e - -e :-'-: November 2007 Progromme Boseline Report, which wos before coniroci signoture, construction of ihe Aquotics C:'--: u.:: r:-::- :: :: :: completedinApril 201 l,tobefollowedbyLOCOGoverloyworksforlesieventswhichweretobecompleieio;J,"2011 A::-es--:j controct negotiotions, the Auihority hos ogreed o longer construction period. The Authorify considers, however, ci irls sioge the inrpcct on the dote of ieodiness for test evenis is minimol. The Authority hos built eorly occess dctes for LOCOG overloy works into the coniroct so thot overloyconbecorriedoutinporollel withtheconstructionwork.Theforecostdoteforrecdinessfortesteventsof August20ll isonemonth loter thon originolly expected. Broodly on trock {ond currenily forecost io be completed oheod of schedule}. Storted eorly ond currently forecost to be completed oheod of schedule. The stsrt dote for construction of this temporory venue wos put bock four months. but the proiecl remoins on irock for delivery in April 201 I . The conshuction of the lnternotionol Broodcost Cenire/Moin Press Cenire is criticcl to lhe Authoriiy's delivery programme. The Authority expects to sign the controct on ihe deol by ihe end of June 2008. ln the meontime. the design ond construclion is on trock. The Olympic Villoge site is now cleor. Plcnning opplicotions for the first three blocks of the oportments hove now been submitted ond piling stcrted in Moy 20b4. See porogrophs 3.20 to 3.25 on the progress towords finolising the deol for the Villoge. The delivery strotegy for the Eton Mcnor orec on the Olympic Pork hos been significontiy refined since ihe November 2007 Progromme Bqseline. Construciion of the different elements moking up the Eton Monor proiect {for exomple Porolyrnpic Tennis ond Archery} will now be procured os one pockoge of work ond, os ot the end of Morch 2008, the Authority expects thot construction will be complete in April 20,l 1 lnvestigotions info ground contorninotion ct the Spifolbrook site in Broxbourne, Hertfordshire, (plonned for the white woter conoeing course) reueolid ihe siie is-unsuitoble. The venue will be relocqted to an olternsiive siie, six miles south of the planned site, ot the Showground in Broxbourne. The lotest pionned stort cnd finish dotes for the proiect {which is noncriticol to the delivery of lhe Auihority's progromme} hove been deiermined using improved informotion on Gcmes time requirements. Construction storted oheqd of schedule ond is forecosi to be delivered one month eorly-